Planning application
2025/306/PPF
4 Hillcrest Lerwick Shetland ZE1 0ST
Proposal
Demolition of existing entrance porch; erection of new garage and vestibule; erection of new external balcony from dining room; conversion of former ground floor garage and store to granny flat.
As published by the council, reference 2025/306/PPF
Timeline
Dates from the published record
-
10 Dec 2025
Received by Shetland Islands
-
11 Dec 2025
Validated
Checked as complete and ready for consideration.
-
10 Feb 2026
Decision issued: Grant subject to conditions
-
28 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
2025/302/PPP Granted
Plot Hillcrest Lerwick Shetland
New dwellinghouse
-
2025/203/PPF Granted
10 Upper Baila Lerwick Shetland ZE1 0SF
Erection of a dormer extension and decking.
-
2026/113/PPF Withdrawn
3 Swarthoull Lerwick Shetland ZE1 0SN
To construct new domestic detached garage building
-
2024/250/NMV Granted
Hjogaberg 3 Quoys Road Lerwick Shetland ZE1 0WH
Non Material Variation to vary planning permission 2024/250/PPF - to install additional roof window.
Other full applications applications
In Shetland Islands
-
2026/059/PPF Granted
Plot Clack Catfirth South Nesting Shetland
Erection of no. 2 dwellinghouses, formation of vehicular access, erection of 1m post and wire boundary fence, installation of septic tank and infiltration system, installation of air source heat pump and associated landscaping and drainage works.
-
2024/220/DCON Awaiting decision
Stove Kirk Inchrye Stove Sandwick Shetland ZE2 9FX
Application for consent, agreement or approval required by planning Condition: 04 (SW Agreement) of planning application 2024/220/PPF.
-
2026/154/PPF Awaiting decision
Lerwick Hotel 15 South Road Lerwick Shetland ZE1 0RB
To demolish existing two storey hotel bedroom wing and build new 3 storey bedroom wing in its place with SUDs and landscaping
-
2026/151/PPF Status unknown
Brough Lodge Fetlar Shetland
Change use of Brough Lodge and outbuildings from domestic to hotel, upgrade access track and parking area. Restore and upgrade fabric, install services including new septic tank.
-
2026/150/PPF Awaiting decision
Da Fustra Westing Unst Shetland ZE2 9DW
Erection of a single storey read extension, decking and soakaway.