Planning application

Vidlin Shorebase Vidlin Voe Shetland ZE2 9QF

Granted Shetland Islands 2022/031/MAR Marine Fish Farm

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

To replace an existing steel and wooden pier with a new concrete pier

As published by the council, reference 2022/031/MAR

Application record

Reference
2022/031/MAR
Type
Marine Fish Farm
Status
Decided
Decision
Granted As published: Grant subject to conditions
Received
21 Dec 2022
Validated
21 Dec 2022
Decided
5 Apr 2023
Decision by
Delegated Decision
Postcode
ZE2 9QF

Timeline

Dates from the published record

  1. 21 Dec 2022

    Received by Shetland Islands

  2. 5 Apr 2023

    Decision issued: Grant subject to conditions

  3. 11 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

24 documents on file for this application

  • LOCATION PLAN Approved Plans · 05 Apr 2023
  • LOCATION PLAN (2) Approved Plans · 05 Apr 2023
  • LOCATION PLAN (3) Approved Plans · 05 Apr 2023
  • RECONSTRUCTION DRAWINGS Approved Plans · 05 Apr 2023
  • DECISION NOTICE Decision · 05 Apr 2023
  • DELEGATED REPORT OF HANDLING Delegated Report of Handling · 05 Apr 2023
  • SCREENING OPINION Report · 05 Apr 2023
  • RECONSTRUCTION DRAWING Drawing · 13 Mar 2023
  • APPLICANT RESPONSE TO NH COMMENTS Correspondence · 13 Mar 2023
  • CONSULTATION RESPONSE- NATURAL HERITAGE Consultee Comment · 17 Feb 2023
  • EMAIL FROM JOHN Correspondence · 10 Feb 2023
  • CONSULTATION RESPONSE- NESTING & LUN. CC Consultee Comment · 20 Jan 2023
  • CONSULTATION RESPONSE- NATURESCOT Consultee Comment · 10 Jan 2023
  • CONSULTATION RESPONSE- NLB Consultee Comment · 10 Jan 2023
  • CONSULTATION RESPONSE- DEVELOPMENT MANAGEMENT Consultee Comment · 09 Jan 2023
  • CONSULTATION RESPONSE- DRAINAGE Consultee Comment · 04 Jan 2023
  • SHETLAND TIMES ADVERT Advert · 30 Dec 2022
  • EMAIL FROM MSS Correspondence · 23 Dec 2022
  • MSS Consultee Comment · 23 Dec 2022
  • CONSULTATION RESPONSE- MSS Consultee Comment · 23 Dec 2022
  • APPLICATION FORM Application Form · 21 Dec 2022
  • APPLICATION FORM- SIGNATURE Application Form · 21 Dec 2022
  • OTTER SURVEY Supporting Documents · 21 Dec 2022
  • SUPPORTING INFORMATION Supporting Documents · 21 Dec 2022

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Shetland Islands granted permission on 5 April 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Shetland Islands's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles

  • Vidlin Ness Vidlin Voe Shetland

    2023/001/MAR Submitted 17 Jan 2023 50 yards away

    To enable the continued temporary siting of a 30m-circumference top net support fitted with an antenna for a further period of 12 months beyond 30 April 2023 following the expiry of planning permission 2021/024/MAR, to facilitate ongoing required telecommunications link between shorebase and salmon farm feed barge

    Granted 15 docs