Newlands Hill Wind Energy Hub South East Of Gifford East Lothian

Decided Scottish Borders 25/01855/NECON Neighbouring Local Authorities

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

The Proposed Development is for the installation of approximately 2.5 km of 132 kV OHL (Overhead Line), between the proposed Newlands Hill Wind Energy Hub and the 400kV substation within the southern section of the existing Fallago Rig Windfarm

As published by the council, reference 25/01855/NECON

Application record

Reference
25/01855/NECON
Type
Neighbouring Local Authorities
Status
Permitted
Decision
Neighbour Consultation Decision
Received
27 Jun 2025
Validated
27 Jun 2025
Decided
21 Jul 2025
Ward
Outwith SBC Adminstrative Boundary
Parish
Outwith SBC Adminstrative Boundary
Decision by
Delegated Decision (Part 3's)

Site history

Applications at this address on the Scottish Borders register

This site has had 3 applications since 2023.

  • 25/01856/SCO Awaiting decision

    Newlands Hill Wind Energy Hub South East Of Gifford East Lothian

    The Proposed Development is for the installation of approximately 2.5 km of 132 kV OHL (Overhead Line), between the proposed Newlands Hill Wind Energy Hub and the 400kV substation within the southern section of the existing Fallago Rig Windfarm

    Submitted 27 Jun 2025 Outline
  • 23/01816/NECON Decided

    Newlands Hill Wind Energy Hub South East Of Gifford East Lothian

    Installation of 17 wind turbines up to 8MW each, generating up to 136MW of which 15 turbines will have a maximum tip height of 200m and 2 turbines will have a maximum tip height of 180m, battery storage up to 136MW and associated access and infrastructure.

    Decided 19 Jan 2024

Timeline

Dates from the published record

  1. 27 Jun 2025

    Received by Scottish Borders

  2. 21 Jul 2025

    Decision issued: Neighbour Consultation Decision

  3. 5 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

2 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

After the decision