Crystal Rig Wind Farm Cranshaws Duns Scottish Borders

Granted Scottish Borders 25/01333/S36 Section 36 Application

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Construction and operation of a repower of Crystal Rig I wind farm. Consisting of up to 10 wind turbines including six turbines with a maximum overall height (to blade tip) of up to 230 m and the remaining four turbines with a maximum overall height (to blade tip) of up to 200 m.

As published by the council, reference 25/01333/S36

Application record

Reference
25/01333/S36
Type
Section 36 Application
Status
Decided
Decision
Section 36 No Objection
Received
24 Sep 2025
Validated
24 Sep 2025
Decided
10 Aug 2026
Ward
Mid Berwickshire
Parish
Lammermuir Community Council
Decision by
Committee Decision

Timeline

Dates from the published record

  1. 24 Sep 2025

    Received by Scottish Borders

  2. 28 Jul 2026

    Added to PlanIndex

  3. 10 Aug 2026

    Decision issued: Section 36 No Objection

Documents

Plans, drawings, consultee responses and the officer's report

221 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Scottish Borders granted permission on 10 August 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Scottish Borders's portal will say. Our guide explains the common types.