Planning application
Stirches Renewable Energy Park Land To South And East Of Stirches Mains Hawick Scottish Borders
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Construction and operation of a proposed Renewable Energy Park, including a co-located solar farm and battery energy storage system with associated infrastructure, access and ancillary works
As published by the council, reference 25/00890/S36
Application record
- Reference
- 25/00890/S36
- Type
- Section 36 Application
- Status
- Decided
- Decision
- Section 36 No Objection
- Received
- 4 Jul 2025
- Validated
- 8 Jul 2025
- Decided
- 10 Aug 2026
- Ward
- Hawick And Denholm
- Parish
- Hawick Community Council
- Decision by
- Committee Decision
Timeline
Dates from the published record
-
4 Jul 2025
Received by Scottish Borders
-
8 Jul 2025
Validated
Checked as complete and ready for consideration.
-
5 Aug 2026
Added to PlanIndex
-
10 Aug 2026
Decision issued: Section 36 No Objection
Documents
Plans, drawings, consultee responses and the officer's report
69 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Scottish Borders granted permission on 10 August 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Scottish Borders's portal will say. Our guide explains the common types.