Torfichen Wind Farm Torfichen Hill Midlothian
Decided. The decision notice on the council portal carries the outcome in full, including any conditions.
Proposal
The Proposed Development would comprise c.19 turbines, each c.180 m from ground to blade tip when vertical. Its total generating capacity is anticipated to be in the region of 114 MW
As published by the council, reference 23/00114/NECON
Application record
- Reference
- 23/00114/NECON
- Type
- Neighbouring Local Authorities
- Status
- Registered
- Decision
- Neighbour Consultation Decision
- Received
- 24 Jan 2023
- Validated
- 24 Jan 2023
- Decided
- 28 Feb 2023
- Ward
- Outwith SBC Adminstrative Boundary
- Parish
- Outwith SBC Adminstrative Boundary
- Decision by
- Delegated Decision (Part 3's)
Timeline
Dates from the published record
-
24 Jan 2023
Received by Scottish Borders
-
28 Feb 2023
Decision issued: Neighbour Consultation Decision
-
31 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
7 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsAfter the decision
Scottish Borders has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.
About this record