Planning application
26/00191/FULPP
130 Morland Road Aldershot Hampshire GU11 3SG
Proposal
Erection of a single storey front extension
As published by the council, reference 26/00191/FULPP
Timeline
Dates from the published record
-
11 Apr 2026
Received by Rushmoor
-
20 May 2026
Validated
Checked as complete and ready for consideration.
-
26 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Rushmoor for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
26/00195/FULPP Granted
132 Morland Road Aldershot Hampshire GU11 3SG
Erection of a single storey front extension and a single storey side and rear extension
-
26/00155/NMAPP Granted
108 Morland Road Aldershot Hampshire GU11 3SF
Non-Material Amendment to 25/00208/FULPP (Demolition of the existing garden room and carport and erection of outbuilding with pergola and formation of block paved driveway with dropped kerb for vehicular access) to allow changes in material and fenestration to the outbuilding
-
25/00439/FULPP Granted
4 Bryce Gardens Aldershot Hampshire GU11 3SZ
Erection of a first floor side extension with two roof lights and erection of a single storey rear extension
-
21/00505/FULPP Granted
155 Cadnam Close Aldershot Hampshire GU11 3RN
Retrospective application for external wall insulated render system to the south flank wall of building (flats 155-160 inc Cadnam Close)
-
25/00396/FULPP Granted
Aldershot Lido Guildford Road Aldershot Hampshire GU12 4BP
Installation of free-standing aluminium-framed canopy structure with integrated solar panel system on roof external in grassed area
Other full applications applications
In Rushmoor
-
26/00429/FULPP Awaiting decision
27A Woburn Avenue Farnborough Hampshire GU14 7EQ
Proposed conversion of the existing integral garage into habitable accommodation, erection of a first-floor extension over the existing garage, and extension of the front garage wall by approximately 1.15m to facilitate the first-floor accommodation
-
26/00424/FULPP Awaiting decision
160 Alexandra Road Farnborough Hampshire GU14 6RY
Erection of a two storey rear/side extension
-
26/00420/FULPP Awaiting decision
50 Sidlaws Road Farnborough Hampshire GU14 9JN
Erection of a single storey side and rear extension, convert garage to habitable accommodation and new pitched roof over porch
-
26/00417/FULPP Awaiting decision
61 Queensmead Farnborough Hampshire GU14 7RL
External alterations including replacement of existing windows and insertion of new windows in front, side and rear elevations and insertion of new door in front elevation
-
26/00407/FULPP Awaiting decision
Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF
Installation of an EV charging hub comprising electrical upstands, a substation, an LV switchgear pillar, line markings and associated electrical infrastructure