Planning application
25/00688/FULPP
Devereux House 69 Albert Road Farnborough Hampshire GU14 6SL
Proposal
Demolition of existing building, excluding the original façade to Devereux House which is to be retained, and construction of part two/three storey building with accommodation in the roof space to provide a care home (Use Class C2) together with parking, landscaping and associated development.
As published by the council, reference 25/00688/FULPP
Timeline
Dates from the published record
-
24 Dec 2025
Received by Rushmoor
-
26 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Rushmoor for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
26/00012/TPOPP Split decision
73 Albert Road Farnborough Hampshire GU14 6SL
One Oak tree ( part of group G28 of TPO 439V) as per submitted photographs, overall crown reduction of no more than 5 metres and canopy lift to give no more than 6 metres clearance from ground level
-
26/00102/TPOPP Withdrawn
Farley Court Church Road East Farnborough Hampshire GU14 6PZ
One Beech (part of group G38 of TPO 439V) reduce branches of tree in the submitted photographs, by no more than 3 metres to create clearance from building
-
20/00361/PDCPP Decided
1 Canterbury Walk Farnborough Hampshire GU14 6GY
Lawful Development Certificate For Proposed Development: Formation of a dormer within rear facing slope and roof lights within front facing roof slope to facilitate loft conversion
-
26/00340/FULPP Awaiting decision
70 Albert Road Farnborough Hampshire GU14 6SL
Demolition of existing garage and erection of two storey side extension, single storey rear extension, insert roof lights to the front and rear to facilitate a loft conversion to habitable room, erection of an outbuilding for gym/storage and alterations to the highway access
-
20/00346/FULPP Granted
Glenside 82 Albert Road Farnborough Hampshire GU14 6SL
Proposed demolition of existing conservatory and the erection of a 2 storey and single storey extension to create 10 new beds and a therapy room
-
26/00204/TPOPP Awaiting decision
2 Belvedere Road Farnborough Hampshire GU14 6SP
One Beech (T2 of TPO 439V) as per submitted photographs, removal of two lowest branches overhanging property
Other full applications applications
In Rushmoor
-
26/00429/FULPP Awaiting decision
27A Woburn Avenue Farnborough Hampshire GU14 7EQ
Proposed conversion of the existing integral garage into habitable accommodation, erection of a first-floor extension over the existing garage, and extension of the front garage wall by approximately 1.15m to facilitate the first-floor accommodation
-
26/00424/FULPP Awaiting decision
160 Alexandra Road Farnborough Hampshire GU14 6RY
Erection of a two storey rear/side extension
-
26/00420/FULPP Awaiting decision
50 Sidlaws Road Farnborough Hampshire GU14 9JN
Erection of a single storey side and rear extension, convert garage to habitable accommodation and new pitched roof over porch
-
26/00417/FULPP Awaiting decision
61 Queensmead Farnborough Hampshire GU14 7RL
External alterations including replacement of existing windows and insertion of new windows in front, side and rear elevations and insertion of new door in front elevation
-
26/00407/FULPP Awaiting decision
Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF
Installation of an EV charging hub comprising electrical upstands, a substation, an LV switchgear pillar, line markings and associated electrical infrastructure