Planning application
21/00392/FULPP
110 Pinehurst Road Farnborough Hampshire GU14 7BF
Proposal
External works to 110 Pinehurst Square, including installation of new entrance canopy, provision of external seating and courtyard landscaping
As published by the council, reference 21/00392/FULPP
Timeline
Dates from the published record
-
13 May 2021
Received by Rushmoor
-
24 May 2021
Validated
Checked as complete and ready for consideration.
-
21 Jul 2021
Decision issued: Permission Granted
-
28 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
21/00393/ADVPP Granted
Buildings 110 120 130 140 And 150 Pinehurst Road Farnborough Hampshire GU14 7BF
Display of 4no. internally illuminated fascia signs and one 1 non-illuminated totem sign
-
25/00505/CONDPP Granted
Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF
Submission of details pursuant to Condition No.14 (30-Year Habitat Management and Monitoring Plan) of planning permission 24/00441/FULPP dated 1st August 2025
-
25/00469/CONDPP Granted
Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF
Submission of details pursuant to Condition Nos.5 (Surface Water Drainage Scheme details) of planning permission 24/00441/FULPP dated 1st August 2025
-
25/00468/CONDPP Granted
Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF
Submission of details pursuant to Condition Nos. 3 (External Finishes Schedule) and 11 (Construction & Environmental Management Plan) of planning permission 24/00441/FULPP dated 1st August 2025
-
25/00446/NMAPP Granted
Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF
NON MATERIAL AMENDMENT: Elevational and plan form amendments to development approved with planning permission 24/00441/FULPP dated 01 August 2025; and amendment to wording of Condition No.5
-
26/00003/PDCPP Decided
150 O'gorman Avenue Farnborough Hampshire GU14 7DL
Certificate of Lawfulness for a Proposed Use: Installation of door at ground floor level to north elevation
Other full applications applications
In Rushmoor
-
26/00429/FULPP Awaiting decision
27A Woburn Avenue Farnborough Hampshire GU14 7EQ
Proposed conversion of the existing integral garage into habitable accommodation, erection of a first-floor extension over the existing garage, and extension of the front garage wall by approximately 1.15m to facilitate the first-floor accommodation
-
26/00424/FULPP Awaiting decision
160 Alexandra Road Farnborough Hampshire GU14 6RY
Erection of a two storey rear/side extension
-
26/00420/FULPP Awaiting decision
50 Sidlaws Road Farnborough Hampshire GU14 9JN
Erection of a single storey side and rear extension, convert garage to habitable accommodation and new pitched roof over porch
-
26/00417/FULPP Awaiting decision
61 Queensmead Farnborough Hampshire GU14 7RL
External alterations including replacement of existing windows and insertion of new windows in front, side and rear elevations and insertion of new door in front elevation
-
26/00407/FULPP Awaiting decision
Village Hotel Pinehurst Road Farnborough Hampshire GU14 7BF
Installation of an EV charging hub comprising electrical upstands, a substation, an LV switchgear pillar, line markings and associated electrical infrastructure