MCLAREN SUPPORT SERVICES LTD, McLaren Technology Centre, Chertsey Road, Woking, Surrey, GU21 4YH

Granted Runnymede RU.26/0431 Outline

Works: Extension

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Consultation by Woking Borough Council for: Full planning application for a revised extension to the McLaren Technology Centre (MTC) to accommodate a test rig, together with the provision of an external condenser compound, within the rear service yard at the McLaren Campus, Woking.

As published by the council, reference RU.26/0431

Application record

Reference
RU.26/0431
Type
Outline
Status
FINAL DECISION
Decision
No objection
Received
31 Mar 2026
Validated
31 Mar 2026
Decided
14 Apr 2026
Postcode
GU21 4YH

Site history

Applications at this address on the Runnymede register

This site has had 3 applications since 2025: 3 approved, 0 refused.

  • RU.26/0309 Granted

    MCLAREN SUPPORT SERVICES LTD, McLaren Technology Centre, Chertsey Road, Woking, Surrey, GU21 4YH

    Consultation by Woking Borough Council for: Full planning application for an extension to the McLaren Technology Centre (MTC) switchboard room, together with the erection of a freestanding UKPN electrical substation and ancillary metering kiosk within the rear service yard.

    Decided 10 Mar 2026 Outline
  • RU.25/1205 Granted

    MCLAREN SUPPORT SERVICES LTD, McLaren Technology Centre, Chertsey Road, Woking, Surrey, GU21 4YH

    Consultation by Woking Borough Council for Planning Application Application PLAN/2025/0678, under Part 14, Class J, Schedule 2 of The Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended) to determine if prior approval is required for the installation of 5,680 solar PV panels on the existing flat roof of McLaren Production Centre, Woking, GU21 4YH. Panels will be mounted using low-profile fixings to ensure equipment is mounted less than 1m from the surface of the flat roof surface. All panels are greater than 1m from the external edges of the roofs. The solar PV equipment will be removed at the end of it's useful life.

    Decided 8 Sep 2025 Outline

Timeline

Dates from the published record

  1. 31 Mar 2026

    Received by Runnymede

  2. 14 Apr 2026

    Decision issued: No objection

  3. 11 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

2 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Runnymede granted permission on 14 April 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About outline applications

An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • MCLAREN SUPPORT SERVICES LTD, McLaren Technology Centre, Chertsey Road, Woking, Surrey, GU21 4YH

    RU.25/1205 Submitted 3 Sep 2025 0m away

    Consultation by Woking Borough Council for Planning Application Application PLAN/2025/0678, under Part 14, Class J, Schedule 2 of The Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended) to determine if prior approval is required for the installation of 5,680 solar PV panels on the existing flat roof of McLaren Production Centre, Woking, GU21 4YH. Panels will be mounted using low-profile fixings to ensure equipment is mounted less than 1m from the surface of the flat roof surface. All panels are greater than 1m from the external edges of the roofs. The solar PV equipment will be removed at the end of it's useful life.

    Granted Outline 2 docs
  • MCLAREN SUPPORT SERVICES LTD, McLaren Technology Centre, Chertsey Road, Woking, Surrey, GU21 4YH

    RU.26/0309 Submitted 9 Mar 2026 0m away

    Consultation by Woking Borough Council for: Full planning application for an extension to the McLaren Technology Centre (MTC) switchboard room, together with the erection of a freestanding UKPN electrical substation and ancillary metering kiosk within the rear service yard.

    Granted Outline Extension 2 docs
  • MCLAREN SUPPORT SERVICES LTD McLaren Technology Centre Chertsey Road Woking Surrey GU21 4YH

    PLAN/2026/0204 Submitted 12 Mar 2026 99m away

    Full planning application for a revised extension to the McLaren Technology Centre (MTC) to accommodate a test rig, together with the provision of an external condenser compound, within the rear service yard at the McLaren Campus, Woking.

    Granted Full applications Extension 27 docs
  • MCLAREN SUPPORT SERVICES LTD McLaren Technology Centre Chertsey Road Woking Surrey GU21 4YH

    PLAN/2026/0150 Submitted 24 Feb 2026 106m away

    Full planning application for an extension to the McLaren Technology Centre (MTC) switchboard room, together with the erection of a freestanding UKPN electrical substation and ancillary metering kiosk within the rear service yard.

    Granted Full applications Extension 25 docs
  • MCLAREN SUPPORT SERVICES LTD McLaren Technology Centre Chertsey Road Woking Surrey GU21 4YH

    PLAN/2025/0678 Submitted 26 Aug 2025 306m away

    Application under Part 14, Class J, Schedule 2 of The Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended) to determine if prior approval is required for the installation of 5,680 solar PV panels on the existing flat roof of McLaren Production Centre, Woking, GU21 4YH. Panels will be mounted using low-profile fixings to ensure equipment is mounted less than 1m from the surface of the flat roof surface. All panels are greater than 1m from the external edges of the roofs. The solar PV equipment will be removed at the end of it's useful life.

    Granted Outline 22 docs

In Runnymede

  • RU.26/0490 Granted

    83 Wendover Road Staines-upon-Thames Surrey TW18 3DD

    Certificate of Proposed Lawfulness for the erection of a summer house

    15 May 2026 Outline
  • RU.26/0483 Refused

    LITTLE WILLOWS Green Road Thorpe Egham Surrey TW20 8QL

    Permission in Principle for the erection of a single storey dwelling.

    12 May 2026 Outline
  • RU.26/0517 Granted

    149 Eastworth Road Chertsey KT16 8DU

    Certificate of Proposed Lawful Development for single storey side extension and erection of front porch

    7 May 2026 Outline
  • RU.26/0573 Granted

    79 Bois Hall Road Addlestone Surrey KT15 2JN

    Certificate of Proposed Lawful Development for a single storey rear extension and boiler flue

    13 May 2026 Outline
  • RU.26/0580 Granted

    149 Eastworth Road Chertsey Surrey KT16 8DU

    Prior Approval for a single storey rear extension with a depth of 4 metres beyond the rear wall of the original dwelling house with a maximum height of 3.8 metres and eaves height of 3 metres

    13 May 2026 Outline