Civic Centre Armada Way Plymouth PL1 2AA

Granted Plymouth 18/01117/LBC Listed Building Consent

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Structural investigations

As published by the council, reference 18/01117/LBC

Application record

Reference
18/01117/LBC
Type
Listed Building Consent
Status
Decided
Decision
Granted As published: Grant Conditionally
Received
22 Jun 2018
Validated
29 Jun 2018
Decided
8 Aug 2018
Ward
ST PETER AND THE WATERFRONT
Decision by
Delegated Decision
Postcode
PL1 2AA

Site history

Applications at this address on the Plymouth register

This site has had 23 applications since 2018: 14 approved, 0 refused.

  • 26/01388/CDMLB Awaiting decision

    Civic Centre, Armada Way Plymouth PL1 2AA

    Condition Discharge: Part-discharge Condition 11 (Terrazzo Floor Finish Details) of Listed Building Consent 23/00239/S19

    Submitted 5 Oct 2026
  • 26/01366/S19 Awaiting decision

    Civic Centre, Armada Way Plymouth PL1 2AA

    Variation of condition 4 (Demolition Works) of application 26/00780/S19 to reflect phasing

    Submitted 1 Oct 2026
  • 26/01361/CDMLB Awaiting decision

    Civic Centre, Armada Way Plymouth PL1 2AA

    Discharge of Condition 4 Demolition Method Statement of 26/00780/S19

    Submitted 30 Sep 2026
  • 26/01320/S73 Granted

    Civic Centre, Armada Way Plymouth PL1 2AA

    Variation of Condition 1 (Approved Plans) and Condition 27 (Accessible Housing) of application 26/00424/FUL to amend the details of the accessible units.

    Decided 29 Oct 2026
  • 26/00809/CDM Decided

    Civic Centre, Armada Way Plymouth PL1 2AA

    Part discharge of conditions 3 (Construction Environmental Management Plan) , 5 (Phasing) , 6 (Construction Traffic Management Plan) of 19/00439/FUL

    Decided 16 Oct 2026
  • 26/00810/AMD Granted

    Civic Centre, Armada Way Plymouth PL1 2AA

    Non material amendment: Variation of conditions 4 (Employment and Skills Strategy), 7 and 8 (District Heating), 10 (Residential Ventilation strategy), 17 (External Materials) to allow demolition works to take place

    Decided 14 Aug 2026 Amendments
  • 26/00780/S19 Granted

    Civic Centre, Armada Way Plymouth PL1 2AA

    Variation of conditions 5 (Sample Of Transom/Spandrel Panel Material), 6 (East And West Façade Detail), 7 (North And South Façade Detail), 13 (Works to First Floor Balcony), 15 (North Block Works External), 16 (North Block Works Internal ), 20 (Basement Works) of application 23/00239/S19 to allow demolition works to take place

    Decided 21 Aug 2026 Amendments
  • 26/00785/LBC Decided

    Civic Centre, Armada Way Plymouth PL1 2AA

    Targeted and limited programme of intrusive investigations to the external reinforced concrete frame and retained pre-cast concrete cladding panels.

    Decided 28 Jul 2026 Heritage and listed buildings
  • 26/00766/CDMLB Awaiting decision

    Civic Centre Armada Way Plymouth PL1 2AA

    Part discharge of conditions 12 (Internal Works to Tower) and 14 (Ground And First Floor Column Repairs) of 23/00239/S19

    Submitted 1 Jun 2026 Heritage and listed buildings
  • 26/00424/FUL Granted

    Civic Centre, Armada Way Plymouth PL1 2AA

    Conversion to residential apartments (Class C3), education space including ancillary cafe, salon, spa, office (Class F1a), restaurant (Class Eb), part demolition, alterations to elevations including new cladding, new public realm including external bridge and staircase, changes to parking, and associated works

    Decided 31 Jul 2026 Full applications

Timeline

Dates from the published record

  1. 22 Jun 2018

    Received by Plymouth

  2. 29 Jun 2018

    Validated

    Checked as complete and ready for consideration.

  3. 8 Aug 2018

    Decision issued: Grant Conditionally

  4. 31 Jul 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

12 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Plymouth granted permission on 8 August 2018, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About heritage and listed building applications

Listed building consent is needed for works that affect the special interest of a listed building, and carrying out such works without it is a criminal offence. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • Civic Centre Armada Way Plymouth PL1 2AA

    23/00239/S19 Submitted 15 Feb 2023 50 yards away

    Variation of Condition 4 (Demolition) and 13 (Works to First Floor Balcony) of application 19/00440/LBC

    Granted Amendments Demolition 12 docs
  • Civic Centre Armada Way Plymouth PL1 2AA

    23/00235/AMD Submitted 14 Feb 2023 50 yards away

    Non-material Amendment: Amendment to 4 pre-conditions wording to allow for initial enabling of demolition works to start of application 19/00439/FUL

    Decided Amendments Demolition 6 docs
  • Civic Centre Armada Way Plymouth PL1 2AA

    23/00237/CDMLB Submitted 14 Feb 2023 50 yards away

    Condition Discharge: Conditions 4, 11 & 14 of application 19/00440/LBC

    Granted Heritage and listed buildings 11 docs
  • Civic Centre, Armada Way Plymouth PL1 2AA

    26/00780/S19 Submitted 3 Jun 2026 50 yards away

    Variation of conditions 5 (Sample Of Transom/Spandrel Panel Material), 6 (East And West Façade Detail), 7 (North And South Façade Detail), 13 (Works to First Floor Balcony), 15 (North Block Works External), 16 (North Block Works Internal ), 20 (Basement Works) of application 23/00239/S19 to allow demolition works to take place

    Granted Amendments Demolition 12 docs
  • Civic Centre Armada Way Plymouth PL1 2AA

    26/00766/CDMLB Submitted 1 Jun 2026 50 yards away

    99% historically approved · decision due ~27 Jul

    Part discharge of conditions 12 (Internal Works to Tower) and 14 (Ground And First Floor Column Repairs) of 23/00239/S19

    Awaiting decision Heritage and listed buildings 23 docs
  • Civic Centre Armada Way Plymouth PL1 2AA

    23/00236/CDM Submitted 14 Feb 2023 50 yards away

    Condition Discharge: Conditions 3, 5, 6 & 9 of application 19/00439/FUL

    Granted Conditions 19 docs

In Plymouth

  • 26/01277/LBC Granted

    6 Penlee Gardens Plymouth PL3 4AN

    4no. wooden double glazed sash windows replacing existing uPVC.

    Received 14 Sep, published by the council 15 Sep 2026 Heritage and listed buildings
  • 26/01294/LBC Granted

    Lyster Court, 2 Craigie Drive Plymouth PL1 3JB

    Listed building consent for structural repair to the reinforced clinker-concrete and steel first-floor slab, achieved through the introduction of supplementary support steels

    Received 16 Sep, published by the council 23 Sep 2026 Heritage and listed buildings
  • 26/01088/LBC Granted

    44 Adelaide Street Stonehouse Plymouth PL1 3JF

    Replacement of external rear door

    Received 3 Aug, published by the council 9 Sep 2026 Heritage and listed buildings
  • 26/01470/LBC Awaiting decision

    Saltram House, Saltram Merafield Road Plymouth PL7 1UH

    Relocation and rehanging of the historic eastern door from the Chinese Bedroom within the South Bedrooms enfilade, together with targeted structural strengthening of the first-floor timber structure beneath the partition between the Green Dressing Room and Lord Morley's Room

    Received 22 Oct, published by the council 23 Oct 2026 Heritage and listed buildings
  • 26/01198/LBC Granted

    1 Berkeley Cottages Collingwood Road Plymouth PL1 5QT

    Replacement roof covering (part retrospective) and associated works

    Received 26 Aug, published by the council 28 Aug 2026 Heritage and listed buildings