Planning application
26/002338/FUL
40-42 Bridge Street, Peterborough, PE1 1DT
Proposal
Conversion of office to 6no. flats with replacement windows and amendments to the window arrangement on the rear facade, amendments to dormer at roof level, 3no. new dormer to the rear of the roof, and relocation of plant equipment
As published by the council, reference 26/002338/FUL
Timeline
Dates from the published record
-
7 May 2026
Received by Peterborough
-
3 Jun 2026
Validated
Checked as complete and ready for consideration.
-
23 Jul 2026
Added to PlanIndex
-
30 Jul 2026
Status changed to Pending Consideration
Previously Under Consultation.
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with Peterborough for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
12/00278/ADV Granted
Land Opposite 42 Bridge Street Peterborough
Freestanding 6-sheet advertising panel installed on the public highway
-
11/01730/ADV Granted
T Mobile 31 Bridge Street Peterborough PE1 1HA
1 Internally illuminated fascia panel1 Fascia panel
-
21/00005/SCREEN Decided
Junction 15 Peterborough
Screening opinion for Junction 15 Improvement scheme
-
11/01682/FUL Granted
Land Between 28 And 30, And 25 And 27 Bridge Street Peterborough
Construction of new War Memorial
-
12/00498/NONMAT Decided
Land Between 28 And 30, And 25 And 27 Bridge Street Peterborough
Non Material amendment for reduction of bollards and relocation of carved inscriptions to that approved under planning application 11/01682/FUL - Construction of new War Memorial
-
12/00497/DISCHG Decided
Land Between 28 And 30, And 25 And 27 Bridge Street Peterborough
Discharge of Condition C2 (materials) of planning permission 11/01682/FUL - Construction of new War Memorial
Other full applications applications
In Peterborough
-
26/002449/FUL Granted
Grange Farm, Old Oundle Road, Thornhaugh, Peterborough, PE8 6NR
Change of use of agricultural land to dog walking paddock
-
26/002404/FUL Granted
Grange Farm Old Oundle Road Thornhaugh Peterborough PE8 6NR
Change of use of agricultural storage area for the siting of 15 self-storage containers
-
26/002485/WCPP Granted
5, Grafton Avenue, Peterborough, PE3 9PD
25/01595/HHFUL - Variation of condition C3 (materials)
-
26/002328/FUL Granted
Ailsworth Methodist Church, Main Street, Ailsworth, Peterborough, PE5 7AF
Change of use from chapel (F1) to community shop (F2) and partial demolition of existing flat roof extension
-
26/002663/FUL Awaiting decision
The White Hart, Main Street, Ufford, Peterborough, PE9 3BH
Engineering and landscaping works to the front curtilage including the replacement and levelling of hard surfacing to form an altered patio area, installation of boundary planters and creation of a pedestrian opening and masonry steps through the existing curtilage retaining wall - retrospective