Planning application
Flag Fen Sewage Treatment Third Drove Fengate Peterborough PE1 5YT
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Erection of two GRP kiosks to house cake dewatering equipment associated polymer makeup equipment
As published by the council, reference 14/02170/FUL
Application record
- Reference
- 14/02170/FUL
- Type
- Planning Application (Full)
- Status
- Decided
- Decision
- Granted As published: Permitted
- Received
- 15 Dec 2014
- Validated
- 15 Dec 2014
- Decided
- 9 Feb 2015
- Ward
- East
- Parish
- Peterborough
- Decision by
- Delegated Decision (Officer)
- Postcode
- PE1 5YT
Timeline
Dates from the published record
-
15 Dec 2014
Received by Peterborough
-
9 Feb 2015
Decision issued: Permitted
-
25 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
15 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Peterborough granted permission on 9 February 2015, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Flag Fen Sewage Treatment Third Drove Fengate Peterborough PE1 5QR
Construction of MCC Kiosk and training Portacabin
Granted Full applications 12 docs -
Flag Fen Sewage Treatment Third Drove Fengate Peterborough PE1 5QR
Extension to site access road and erection of sludge cake export silo
Granted Full applications Extension 2 docs -
Flag Fen Sewage Treatment Third Drove Fengate Peterborough PE1 5QR
Installation of telemetry equipment
Granted Telecoms 3 docs -
Flag Fen Sewage Treatment Third Drove Fengate Peterborough PE1 5QR
Mess room for workers
Granted Full applications 2 docs -
Flag Fen Sewage Treatment Third Drove Fengate Peterborough PE1 5QR
Proposed wind farm development - request for scoping opinion
Decided Outline -
Peterborough Power Station - Nene Wash
Peterborough Power Station - Nene Wash Tess 132kV (PCH 7 - PIA7) overhead line BT21 earthwire replacement
Decided Prior approval 2 docs
Other full applications
In Peterborough
-
26/002951/FUL Status unknown
Land East of Staplee Way, Parnwell, Peterborough, PE1 4YT
Erection of 4no. B2/B8 Buildings with Associated Works
-
26/002968/FUL Status unknown
331 Lincoln Road Peterborough PE1 2PF
Proposed Change of Use from Class E to Sui Generis Adult Gaming Centre (AGC), sh
-
26/002999/FUL Status unknown
Limes Farm, Main Street, Barnack, Stamford, PE9 3DN
Demolition of predominantly modern farm buildings to enable partial site redevel
-
26/002739/FUL Refused
88 Sycamore Avenue Dogsthorpe Peterborough PE1 4JU
Change of use from C3 to C2 (children's Home)
-
26/002960/FUL Awaiting decision
Land Adjacent to 75, High Street, Maxey, Peterborough, PE6 9EE
Erection of a one and a half storey detached dwelling with integral garage