Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

Granted Peterborough 10/00719/FUL Planning Application (Full)

Works: Extension Demolition

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

As published by the council, reference 10/00719/FUL

Application record

Reference
10/00719/FUL
Type
Planning Application (Full)
Status
Decided
Decision
Permitted
Received
28 May 2010
Validated
28 May 2010
Decided
30 Jul 2010
Ward
Orton Waterville
Parish
Orton Waterville
Decision by
Committee Decision
Postcode
PE2 5RQ

Site history

Applications at this address on the Peterborough register

This site has had 9 applications since 2010: 2 approved, 0 refused.

  • 12/00220/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of condition C7 ( Landscape scheme), C10 (Service yard area) and C27 (Community use scheme) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 16 Apr 2012 Conditions
  • 11/01854/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of condition C8 ( Final travel plan), C9 ( Kitchen ventilation), C10 (Service yard details) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 25 Jan 2012 Conditions
  • 11/00631/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of external lighting element of condition C3 (CCTV, walls/fences and external lighting) of planning permission 10/00719/FUL dated 30.07.10 (Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building)

    Decided 15 Jun 2011 Conditions
  • 11/00130/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of CCTV element of condition 3 (CCTV, walls/fences and external lighting) of Planning Permission 10/00719/FUL (Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building)

    Decided 17 Mar 2011 Conditions
  • 10/01443/NONMAT Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Non material amendment to planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 16 Nov 2010 Amendments
  • 10/01424/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of condition C6, C29, C30, C31 of planning permission 10/00719/FUL dated 30.07.10 - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 29 Nov 2010 Conditions
  • 10/01176/FUL Granted

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Provision of a new maintenance depot within the grounds of the Ormiston Bushfield Academy and relocation of the 4 x existing containers from an adjacent site

    Decided 20 Oct 2010 Full applications
  • 10/01121/NONMAT Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Non-material amendment to application 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 26 Oct 2010 Amendments

Timeline

Dates from the published record

  1. 28 May 2010

    Received by Peterborough

  2. 30 Jul 2010

    Decision issued: Permitted

  3. 26 Aug 2026

    Added to PlanIndex

Cases linked to this one on the register

11 later applications on the register refer to this one:

  • 12/00458/DISCHG Decided

    Ormiston Bushfield Academy Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of conditions C32 (bat and bird boxes) and C34 (roosting or hibernating bats) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 21 May 2012 Conditions
  • 12/00220/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of condition C7 ( Landscape scheme), C10 (Service yard area) and C27 (Community use scheme) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 16 Apr 2012 Conditions
  • 11/01854/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of condition C8 ( Final travel plan), C9 ( Kitchen ventilation), C10 (Service yard details) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 25 Jan 2012 Conditions
  • 11/00631/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of external lighting element of condition C3 (CCTV, walls/fences and external lighting) of planning permission 10/00719/FUL dated 30.07.10 (Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building)

    Decided 15 Jun 2011 Conditions
  • 11/00130/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of CCTV element of condition 3 (CCTV, walls/fences and external lighting) of Planning Permission 10/00719/FUL (Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building)

    Decided 17 Mar 2011 Conditions
  • 10/01443/NONMAT Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Non material amendment to planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 16 Nov 2010 Amendments
  • 10/01424/DISCHG Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of condition C6, C29, C30, C31 of planning permission 10/00719/FUL dated 30.07.10 - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 29 Nov 2010 Conditions
  • 10/01299/DISCHG Decided

    Ormiston Bushfield Academy Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of condition C2, C3, C4, C7, C13, C22, C26 of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 3 Dec 2010 Conditions
  • 10/01261/DISCHG Decided

    Ormiston Bushfield Academy Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Discharge of condition C25 (playing fields) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 25 Nov 2010 Conditions
  • 10/01140/DISCHG Decided

    Orminston Bushfield Academy Ortongate Peterborough PE2 5RQ

    Discharge of condition C33 (amphibian fence) of planning permission 10/00719/FUL

    Decided 1 Oct 2010 Conditions
  • 10/01121/NONMAT Decided

    Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    Non-material amendment to application 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided 26 Oct 2010 Amendments

Documents

Plans, drawings, consultee responses and the officer's report

97 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Peterborough granted permission on 30 July 2010, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

Nearby applications

Within 500 metres

  • Ormiston Bushfield Academy Bushfield Orton Goldhay Peterborough PE2 5RQ

    12/00458/DISCHG Submitted 3 Apr 2012 1m away

    Discharge of conditions C32 (bat and bird boxes) and C34 (roosting or hibernating bats) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided Conditions Extension Demolition 8 docs
  • Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    11/01854/DISCHG Submitted 30 Nov 2011 1m away

    Discharge of condition C8 ( Final travel plan), C9 ( Kitchen ventilation), C10 (Service yard details) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided Conditions Extension Demolition 9 docs
  • Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    12/00220/DISCHG Submitted 23 Feb 2012 1m away

    Discharge of condition C7 ( Landscape scheme), C10 (Service yard area) and C27 (Community use scheme) of planning permission 10/00719/FUL - Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building

    Decided Conditions Extension Demolition 11 docs
  • Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    11/00130/DISCHG Submitted 10 Feb 2011 1m away

    Discharge of CCTV element of condition 3 (CCTV, walls/fences and external lighting) of Planning Permission 10/00719/FUL (Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building)

    Decided Conditions Extension Demolition 3 docs
  • Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    11/00631/DISCHG Submitted 10 May 2011 1m away

    Discharge of external lighting element of condition C3 (CCTV, walls/fences and external lighting) of planning permission 10/00719/FUL dated 30.07.10 (Construction of a new two storey high academy school building, incorporating the library, young people's centre and early years centre, and demolition of the existing academy, library and Sheridan Centre buildings. Provision of associated external areas, including sports fields, a floodlit all weather pitch, car parking and public plaza, with associated access, alterations to cycle way and boundary treatments. Extension to the existing Bushfield Sports Centre, the re-cladding of its front elevation and the construction of a new colonnade feature. The refurbishment and extension of the existing changing pavilion building)

    Decided Conditions Extension Demolition 5 docs
  • Bushfield Community College Bushfield Orton Goldhay Peterborough PE2 5RQ

    10/01176/FUL Submitted 25 Aug 2010 100m away

    Provision of a new maintenance depot within the grounds of the Ormiston Bushfield Academy and relocation of the 4 x existing containers from an adjacent site

    Granted Full applications 16 docs

In Peterborough

  • 25/01181/FUL Granted

    Christ The Servant King Church Silver Hill Hampton Centre Peterborough PE7 8FF

    Change of use of land to a private car park serving Christ the Servant King Chur

    26 Jan 2026 Full applications
  • 26/002197/FUL Granted

    Garage site adjacent to 45, Bluebell Avenue, Peterborough, PE1 3XQ

    Demolition of existing garages and replace with permeable block paving parking spaces, enclosed with new fencing to boundaries with neighbouring homes

    7 Apr 2026 Full applications
  • 26/002397/FUL Granted

    Ducati Peterborough Peterborough Road Wansford Peterborough PE8 6JN

    Change of use from workshop (B2) to mixed use B2 and Sui Generis (car showroom)

    20 May 2026 Full applications
  • 26/002836/FUL Status unknown

    15 South Parade Peterborough PE3 6BG

    13-unit residential development consisting of 9 flats, 4 maisonettes, and associ

    3 Sep 2026 Full applications
  • 26/002499/FUL Refused

    Moor Farm House, Moor Road, Milking Nook, Peterborough, PE6 7PQ