Proposal
Formation of an energy storage facility, including storage units, ancillary structures, substation compound containing transformers, erection of a control building, security and deer fencing, landscaping and associated works
As published by the council, reference 23/00009/PAN
Application record
- Reference
- 23/00009/PAN
- Type
- Proposal of Application Notice
- Status
- Decided
- Decision
- PAN notice sufficient
- Received
- 26 May 2023
- Validated
- 1 Jun 2023
- Decided
- 14 Jun 2023
- Ward
- Blairgowrie And Glens
- Parish
- Mount Blair
- Decision by
- Committee Decision
Timeline
Dates from the published record
-
26 May 2023
Received by Perth and Kinross
-
1 Jun 2023
Validated
Checked as complete and ready for consideration.
-
14 Jun 2023
Decision issued: PAN notice sufficient
-
15 Nov 2026
Added to PlanIndex
Documents
6 documents on file for this application
A planning file usually holds the application form, the consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWorking a patch? Trade sends you every new job in your area each morning. 14 days free.
After the decision
Perth and Kinross has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Perth and Kinross's portal will say. Our guide explains the common types.
Nearby applications
Within 0.3 miles
-
Green Burn Wind Farm Bridge Of Cally
Section 42 application to modify Condition 1 (duration) of permission 15/01691/FLM
Granted Full applications 48 docsMajor scheme