Skip to content
PlanIndex Get alerts
Menu

Planning application

25/0899/NM

Pembroke Power Station, PWLLCROCHAN, Pembroke, Pembrokeshire, SA71 5SS

Granted Pembrokeshire Non-Material Amendment

Proposal

Non-material amendment to planning permission 25/0899/PA (Construction of a Battery Energy Storage System (BESS) including Battery Containers and Power Conversion Systems; lighting, security fencing, hard and soft landscaping, drainage, vehicle access/circulation, temporary construction laydown areas, ancillary equipment and other associated infrastructure; and an underground electrical cable connection to the National Grid Substation).

As published by the council, reference 25/0899/NM

Timeline

Dates from the published record

  1. 20 Jan 2026

    Received by Pembrokeshire

  2. 6 Feb 2026

    Decision issued: Conditionally Approved

  3. 28 Jul 2026

    Added to PlanIndex

What a grant of permission means

The process from here

Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.

Work must normally begin within five years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.

About amendments applications

How this application type works

An amendment application changes a permission that already exists. Non-material amendments cover small adjustments with no wider effect, while minor material amendments, usually made by varying a condition, allow modest design changes without a fresh application. Anything beyond that needs a new permission, so the scope here is deliberately narrow.

More on amendments applications in our guide

Nearby applications

Within 500 metres

  • 25/0654/DC Refused

    Land at Entrance To Pembroke Power Station, Pwllcrochan, Pembroke, SA71 5SS

    Discharge of pre-commencement requirements of condition 3 (Construction Environmental Management Plan) and 4 (Construction Transport Management Plan) of planning permission Ref. 24/0600/PA (Construction of a Battery Energy Storage System with Associated Development).

    23 Oct 2025 23m away Conditions
  • 25/0733/DC Granted

    Land at Entrance To Pembroke Power Station, Pwllcrochan, Pembroke, SA71 5SS

    Discharge of conditions 8 (surface water) and 11 (levels) to planning permission 24/0600/PA (Construction of a Battery Energy Storage System (BESS) including Battery Containers and Power Conversion Systems; lighting, security fencing, hard and soft landscaping, drainage, vehicle access/circulation, temporary construction laydown areas, ancillary equipment and other associated infrastructure; and an underground electrical cable connection to the National Grid Substation)

    17 Nov 2025 23m away Conditions
  • 25/0443/NM Granted

    Land at Entrance to Pembroke Power Station, Pwllcrochan, Pembroke, SA71 5SS

    Amendments to approved plans (condition 2) of planning permission 24/0600/PA (Construction of a Battery Energy Storage System (BESS) including Battery Containers and Power Conversion Systems; lighting, security fencing, hard and soft landscaping, drainage, vehicle access/circulation, temporary construction laydown areas, ancillary equipment and other associated infrastructure; and an underground electrical cable connection to the National Grid Substation)

    18 Aug 2025 23m away Amendments
  • 25/0542/DC Granted

    Land at Entrance To Pembroke Power Station, Pwllcrochan, Pembroke, SA71 5SS

    Discharge of conditions 6 (colour), 10 (landscaping), 15 (LEMP) and 17 (otter survey) of planning permission 24/0600/PA (Construction of a Battery Energy Storage System (BESS) including Battery Containers and Power Conversion Systems; lighting, security fencing, hard and soft landscaping, drainage, vehicle access/circulation, temporary construction laydown areas, ancillary equipment and other associated infrastructure; and an underground electrical cable connection to the National Grid Substation - Land at Entrance To Pembroke Power Station, Pwllcrochan, Pembroke, SA71 5SS)

    15 Sep 2025 23m away Conditions
  • 25/0694/NM Granted

    West Pennar Camp, U6308 Entrance To Pembroke Power Station, Pwllcrochan, Pembroke, SA71 5SS

    Non material amendment to permission 24/0600/PA (Construction of a Battery Energy Storage System (BESS) including Battery Containers and Power Conversion Systems; lighting, security fencing, hard and soft landscaping, drainage, vehicle access/circulation, temporary construction laydown areas, ancillary equipment and other associated infrastructure; and an underground electrical cable connection to the National Grid Substation).

    5 Nov 2025 25m away Amendments

In Pembrokeshire

  • 26/0223/NM Granted

    Dragon Lng, Main Road, WATERSTON, Milford Haven, Pembrokeshire, SA73 1DR

    Amended restoration scheme for West Perimeter Road access (modification of details approved pursuant to conditions 9 and 11 of planning permission ref. DNS CAS-01859-K1M7Y6 (Three Wind Turbines and Ancillary Development)

    26 Jun 2026 Amendments
  • 26/0218/NM Refused

    Land to the East of Pilgrims Way, Roch, Pembrokeshire, SA62 6BQ

    Non-Material Amendment to Planning Permission ref: 25/0065/PA - Variation of Condition 2 (approved plans), 4 (drainage), 11 (landscaping), 14 (external lighting) and 15 EEMP of Planning Permission 23/0568/PA (Proposed residential development of 52 units)

    25 Jun 2026 Amendments
  • 26/0205/NM Refused

    Florissant, Lower Lamphey Road, Pembroke, Pembrokeshire, SA71 4AF

    Non-material amendment to Planning Permission 25/1040/PA (Alterations and extensions to a dwelling and erection of a detached garage) to reposition the garage and amend fenestration.

    23 Jun 2026 Amendments
  • 26/0128/PA Granted

    The Sail Loft, Hakin Point, HAKIN, Milford Haven, Pembrokeshire, SA73 3DG

    Variation of Condition 2 (approved plans) 6 (biodiversity) & 7 (green infrastructure) of Planning Permission 24/1156/PA (Alterations and extension)

    26 May 2026 Amendments
  • 26/0279/NM Awaiting decision

    Land off The Kilns, Llangwm, Haverfordwest, SA62 4HG

    Non-material amendment to planning permission 24/0120/PA (Construction of 67no. Dwelling houses with Access, Estate Roads and Associated Infrastructure).

    17 Jul 2026 Amendments