Skip to content
PlanIndex Get alerts
Menu

Planning application

National Grid Substation Land Off Broadgate Oldham

Awaiting decision Oldham CND/356920/26

Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.

Proposal

Discharge of condition 3 (Noise) associated with application VAR/353062/24.

As published by the council, reference CND/356920/26

Application record

Reference
CND/356920/26
Status
Awaiting decision
Received
2 Oct 2026
Validated
2 Oct 2026
Ward
Chadderton South
Decision by
Schedule 1

Site history

Applications at this address on the Oldham register

This site has had 2 applications since 2022: 1 approved, 0 refused.

  • FUL/350175/22 Granted

    National Grid Substation Land Off Broadgate Oldham

    The development of an electrical connection between the approved Whitegate Battery Storage Facility (planning application reference: FUL/348501/22) and National Grid's Substation off Broadgate, Oldham.

    Decided 18 Jan 2023 Full applications

Timeline

Dates from the published record

  1. 2 Oct 2026

    Received by Oldham

  2. 7 Oct 2026

    Added to PlanIndex

  3. Decision

    Awaiting decision

    Decision expected by 27 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.

    Oldham took a median of 68 days over the applications it decided in the last year.

Cases linked to this one on the register

  • Application: VAR/353062/24 (Decided)

Documents

Plans, drawings, consultee responses and the officer's report

3 documents on file for this application

  • APPLICATIONFORMREDACTED Application Form · 01 Oct 2026
  • 26-313 WHITEGATE BESS - NOISE COMMISSIONING TEST Case Documents · 01 Oct 2026
  • CONDITION 3 COVER LETTER General Documents · 01 Oct 2026

Watch members (£5 a month) open the document list from here.

Open the documents

What happens while it is decided

This application is with Oldham for determination, against a statutory target of eight weeks. Over the last year Oldham's median decision took 68 days. More in our guide to how long planning decisions take.

About this record

The published feed does not state which type of application this is; the register entry on Oldham's portal will say. Our guide explains the common types.