Planning application
Ealing Hospital Uxbridge Road Southall UB1 3HW
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Installation of roof mounted photovoltaic 222 panels (Class J, 56 days Prior Approval Process)
As published by the council, reference 261560PAPV
Application record
- Reference
- 261560PAPV
- Type
- PA Not PV Install/Alt/Rep PV
- Status
- Prior Approval Required and Given
- Decision
- Prior Approval Required and Given
- Received
- 13 Apr 2026
- Validated
- 30 Apr 2026
- Decided
- 25 Jun 2026
- Ward
- Norwood Green
- Decision by
- Delegated Decision
- Postcode
- UB1 3HW
Site history
Applications at this address on the Old Oak and Park Royal Development Corporation register
This site has had 5 applications since 2026: 4 approved, 0 refused.
-
262424FUL Awaiting decision
Ealing Hospital Uxbridge Road Southall UB1 3HW
Installation of a 1MW Water Source Heat Pump (WSHP) with associated GRP enclosures, buffer vessels, and thermal stores, including external pipework connecting to the plantroom.
-
261844FUL Granted
Ealing Hospital Uxbridge Road Southall UB1 3HW
Installation of 2no Air Source Heat pumps on the roof, associated steel support deck, pipework and electrical containment from the heat pumps along the roof and down the side of the building
-
261679FUL Granted
Ealing Hospital Uxbridge Road Southall UB1 3HW
Installation of handrails at roof level
-
260343PTT Granted
Ealing Hospital Uxbridge Road Southall UB1 3HW
TPO/2005/0660 T1 Beech Tree - Fell tree to ground level and replant a young Beech specimen.
Timeline
Dates from the published record
-
13 Apr 2026
Received by Old Oak and Park Royal Development Corporation
-
30 Apr 2026
Validated
Checked as complete and ready for consideration.
-
25 Jun 2026
Decision issued: Prior Approval Required and Given
-
27 Jul 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Vital Energi Utilities Ltd Agent, registered in Blackburn
Active · incorporated 2000 · Blackburn
21 applications on PlanIndex · across 8 councils · 94% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
16 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Old Oak and Park Royal Development Corporation granted permission on 25 June 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About outline applications
An outline application tests the principle of developing a site, holding back details such as appearance and landscaping as reserved matters for later approval. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
Ealing Hospital Uxbridge Road Southall UB1 3HW
75% historically approved · decision due ~12 Aug
Installation of a 1MW Water Source Heat Pump (WSHP) with associated GRP enclosures, buffer vessels, and thermal stores, including external pipework connecting to the plantroom.
Awaiting decision Full applications 17 docs -
Ealing Hospital Uxbridge Road Southall UB1 3HW
Installation of handrails at roof level
Granted Full applications 10 docs -
Ealing Hospital Uxbridge Road Southall UB1 3HW
Installation of handrails at roof level
Granted Full applications 10 docs -
Ealing Hospital Uxbridge Road Southall UB1 3HW
Installation of roof mounted photovoltaic 222 panels (Class J, 56 days Prior Approval Process)
Granted Outline 16 docs -
Ealing Hospital Uxbridge Road Southall UB1 3HW
Installation of 2no Air Source Heat pumps on the roof, associated steel support deck, pipework and electrical containment from the heat pumps along the roof and down the side of the building
Granted Full applications 12 docs -
Ealing Hospital Uxbridge Road Southall UB1 3HW
Installation of 2no Air Source Heat pumps on the roof, associated steel support deck, pipework and electrical containment from the heat pumps along the roof and down the side of the building
Granted Full applications 12 docs
Other outline applications
In Old Oak and Park Royal Development Corporation
-
262400CONS Decided
Gunnersbury Park, Popes Lane Ealing W3 8LQ
Temporary change of use of areas of Gunnersbury Park for the staging of temporary events between 01 January 2027 and 31 December 2031. Up to 22 live event days per calendar year, with a total of 115 days including set-up, inactive and removal days. Including the erection of associated temporary structures, fencing, ancillary concessions and facilities. (out of borough)
-
263099CONS Decided
Gunnersbury Park, Popes Lane Ealing W3 8LQ
Temporary change of use of areas of Gunnersbury Park for the staging of temporary events between 01 January 2027 and 31 December 2031. Up to 19 live event days per calendar year, with a total of 115 days including set-up, inactive and removal days, and trackway. Including the erection of associated temporary structures, fencing, ancillary concessions and facilities. (Out of Borough from Hounslow)
-
262743PACBSD Refused
26-30 Ealing Gateway Uxbridge Road Ealing W5 2AU
Change of use from office floorspace (Use Class E(g)(i)) to residential x 68 flats (Use Class C3) (Class MA, 56 day Prior Approval Process)
-
263151OPDCOB Granted
Imperial College Office Woodward Buildings 1 Victoria Road Acton W3 6FA
Installation of two wooden poster-boards to the fence at the intersection of Victoria Road and Chase Road. (Out of Borough Consultation from the OPDC)
-
263070OPDCOB Granted
Frogmore Industrial Estate Acton Lane Park Royal NW10 7NQ
Demolition of existing boundary walls and retaining walls, removal of existing hardstanding, removal of redundant drainage infrastructure, diversion of below ground services, soil remediation works, earthworks to regrade site levels, installation of piling mat and construction of piles, installation of hoardings, and installation of demountable site management buildings (Out of Borough from Old Oak and Park Royal Development Corporation)