Skip to content
PlanIndex Get alerts
Menu

Planning application

Land East and South East Of Dunton Hall Kingsbury Road Curdworth

Granted North Warwickshire PAP/2021/0473

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Development of a 349.9 MW Battery Energy Storage System with associated infrastructure including access road for construction

As published by the council, reference PAP/2021/0473

Application record

Reference
PAP/2021/0473
Status
Permitted
Decision
Granted
Received
3 Aug 2021
Validated
5 Aug 2021
Decided
4 Mar 2022
Ward
Curdworth
Parish
Curdworth
Decision by
Planning & Development Board

Site history

Applications at this address on the North Warwickshire register

This site has had 3 applications since 2021: 3 approved, 0 refused.

  • DOC/2022/0109 Granted

    Land east and south east of Dunton Hall Kingsbury Road Curdworth

    Approval of details required by conditions 7 (Construction Management Plan) of planning permission PAP/2021/0473 dated 04/03/2022.

    Decided 10 Jul 2023 Conditions
  • DOC/2022/0095 Granted

    Land East and South East Of Dunton Hall Kingsbury Road Curdworth

    Application to discharge conditions 10 (Ecology) and 20 (Surface Water Management) of Planning Permission PAP/2021/0473 dated 4 March 2022

    Decided 10 Oct 2023 Conditions

Timeline

Dates from the published record

  1. 3 Aug 2021

    Received by North Warwickshire

  2. 5 Aug 2021

    Validated

    Checked as complete and ready for consideration.

  3. 4 Mar 2022

    Decision issued: Granted

  4. 14 Aug 2026

    Added to PlanIndex

Cases linked to this one on the register

5 later applications on the register refer to this one:

  • 2026/0614/NMA Decided

    Land East of Dunton Hall Kingsbury Road Curdworth

    Non Material Amendment of application PAP/2025/0372 (Application to vary condition(s) 1 (plans), 6 (CMP) 7(colour of containers etc), 8 (finished floor levels), 10(lighting), 12(drainage scheme), 16 (bunds) 17 (LEMP), 18 (water supplies), 19(maintenance), 20(dust mitigation) and 21(noise mitigation) of planning permission PAP/2025/0224 dated 19 July 2025 for Application to vary condition 3 (time limiting restriction of operational life) of Planning permission PAP/2021/0473 dated 04/03/2022 for the development of a Battery Energy Storage System with associated infrastructure including access road for construction) to allow for 2No. Additional CCTV cameras, post and rail fence & relocation of trees

    Submitted 6 Aug 2026 Amendments
  • 2026/0289/NMA Granted

    Hams Hall Battery Energy Storage System Site Kingsbury Road Curdworth B76 0BA

    Non Material Amendment of Planning Permission PAP/2025/0062 for "Proposed underground cable and ancillary electrical works to connect the Battery Energy Storage System approved under planning application ref. PAP/2021/0473 to the Hams Hall National Grid electricity substation at coordinates 419378, 292553. Works include a temporary access track to facilitate construction", dated 07/05/2025; relating to change in the description to remove reference to PAP/2021/0473 as PAP/2025/0372 is the current approval

    Decided 10 Aug 2026 Amendments
  • DOC/2022/0110 Granted

    Land to the east and south east of Dunton Hall Kingsbury Road Curdworth

    Approval of details required by conditions 8 (colour of equipment) and 9 (floor levels) of planning permission PAP/2021/0473 dated 04/03/2022.

    Decided 20 Sep 2023 Conditions
  • DOC/2022/0109 Granted

    Land east and south east of Dunton Hall Kingsbury Road Curdworth

    Approval of details required by conditions 7 (Construction Management Plan) of planning permission PAP/2021/0473 dated 04/03/2022.

    Decided 10 Jul 2023 Conditions
  • DOC/2022/0095 Granted

    Land East and South East Of Dunton Hall Kingsbury Road Curdworth

    Application to discharge conditions 10 (Ecology) and 20 (Surface Water Management) of Planning Permission PAP/2021/0473 dated 4 March 2022

    Decided 10 Oct 2023 Conditions

Documents

Plans, drawings, consultee responses and the officer's report

48 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

North Warwickshire granted permission on 4 March 2022, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on North Warwickshire's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres