Hs2 Phase One Overheadline Diversion Tamworth Road, Middleton and Kingsbury Road, Marston Warwickshire
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
National Grid diversion works to the ZF overhead line site restoration scheme in accordance with Schedule 16 paragraph 5 (1) to the High Speed Rail (London - West Midlands) Act 2017
As published by the council, reference HS2/2020/0008
Application record
- Reference
- HS2/2020/0008
- Status
- Permitted
- Decision
- Granted
- Received
- 9 Oct 2020
- Validated
- 9 Oct 2020
- Decided
- 19 Nov 2020
- Ward
- Curdworth
- Parish
- Curdworth
- Decision by
- Delegated
Timeline
Dates from the published record
-
9 Oct 2020
Received by North Warwickshire
-
19 Nov 2020
Decision issued: Granted
-
25 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
7 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
North Warwickshire granted permission on 19 November 2020, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on North Warwickshire's portal will say. Our guide explains the common types.
Nearby applications
Within 500 metres
-
Proposed Irrigation Pool At Land 360 Metres South Of Cuttle Mill Fisheries Cuttle Mill Lane Curdworth Warwickshire
Replacement Irrigation pool for farm land
Granted Full applications 9 docs -
Hs2 Birmingham And Fazeley Canal Viaduct Kingsbury Road Curdworth
Plans and Specifications submission under Schedule 17 to the High Speed Rail (London - West Midlands) Act 2017 for works comprising: Construction of a railway viaduct over the Birmingham and Fazeley Canal incorporating an underbridge over the realigned Seeney Lane, and ancillary works including earthworks to form balancing and ecological ponds, earthworks to form drainage ditches, earthworks to form maintenance access tracks and provision of permanent vehicle parking areas.
Granted 43 docs -
Hs2 Marston Box Structure Kingsbury Road Curdworth Warwickshire
Sch17 Application - Plans and Specifications for the M42 Marston Box Structure
Granted 29 docs