Land At And Between Easterhouse (Gartcosh) Newarthill And Wishaw (Gowkthrapple) Substations

Decided North Lanarkshire 26/00789/ECU

Works: Extension

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

Consultation from Scottish Government (Energy Consent Unit) - Section 37 & Schedule 8: Application for Uprating of existing overhead lines XX and XR routes from 275kV to 400kV including replacement of existing conductors (overhead line wires), downleads, temporary accesses, tower foundation upgrades and tower strengthening and associated ancillary works. Internal alterations at Easterhouse (Gartcosh) substation and an extension to Wishaw Substation (Gowkthrapple) (EIA Development) ECU00006382

As published by the council, reference 26/00789/ECU

Application record

Reference
26/00789/ECU
Status
Comments
Decision
Comments
Received
30 Jun 2026
Validated
30 Jun 2026
Decided
27 Aug 2026

Timeline

Dates from the published record

  1. 30 Jun 2026

    Received by North Lanarkshire

  2. 6 Aug 2026

    Added to PlanIndex

  3. 27 Aug 2026

    Decision issued: Comments

  4. 10 Sep 2026

    Status changed to Comments

    Previously Pending Consideration.

After the decision

North Lanarkshire has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on North Lanarkshire's portal will say. Our guide explains the common types.