Planning application

Meiklelaught Farm Saltcoats Ayrshire KA21 6NF

Granted North Ayrshire 23/00731/PPM Planning Permission (major)

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

The Construction and Operation Of A 30 MW Battery Energy Storage System with Associated Infrastructure, Substation, Security Fencing, CCTV, And Landscaping

As published by the council, reference 23/00731/PPM

Application record

Reference
23/00731/PPM
Type
Planning Permission (major)
Status
Approved subject to Conditions
Decision
Granted As published: Approved subject to Conditions
Received
29 Sep 2023
Validated
12 Oct 2023
Decided
22 Nov 2023
Ward
Ardrossan
Parish
Saltcoats Community Council
Decision by
Committee
Postcode
KA21 6NF

Timeline

Dates from the published record

  1. 29 Sep 2023

    Received by North Ayrshire

  2. 12 Oct 2023

    Validated

    Checked as complete and ready for consideration.

  3. 22 Nov 2023

    Decision issued: Approved subject to Conditions

  4. 1 Sep 2026

    Added to PlanIndex

Cases linked to this one on the register

  • Application: 18/00067/PP (Approved subject to Conditions)
  • Application: 23/00546/EIA (Scoping/Screening Agreed)

Who's behind it

Company information only, from the register and Companies House

AAH Planning Consultants Fao Paul Booth Agent, a planning consultancy

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

GPC 1127 Ltd Applicant, registered in Altrincham

Active · incorporated 2023 · Altrincham

1 application on PlanIndex

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

29 documents on file for this application

  • Decision notice Decision · 13 Dec 2023
  • Flooding response Consultation Response · 14 Nov 2023
  • Environmental health response Consultation Response · 07 Nov 2023
  • Boundary treatment and landscaping plan Approved Drawing · 03 Nov 2023
  • Site plan Approved Drawing · 03 Nov 2023
  • Location plan Approved Drawing · 30 Oct 2023
  • Wosas response Consultation Response · 26 Oct 2023
  • Roads response Consultation Response · 25 Oct 2023
  • Landscape and visual impact appraisal Report · 20 Oct 2023
  • Photoviews visulisations and methodology Report · 20 Oct 2023
  • Lvia appendix a Report · 20 Oct 2023
  • Lvia appendix b Report · 20 Oct 2023
  • Neighbour notification Neighbour Notification List · 13 Oct 2023
  • Cctv Approved Drawing · 10 Oct 2023
  • Aux transformer elevations Approved Drawing · 29 Sep 2023
  • Battery container detail Approved Drawing · 29 Sep 2023
  • Client substation and control room Approved Drawing · 29 Sep 2023
  • Design and access statement Report · 29 Sep 2023
  • Dno detail Approved Drawing · 29 Sep 2023
  • Grid connection route plan Approved Drawing · 29 Sep 2023
  • Impact assessment Report · 29 Sep 2023
  • Inverter detail Approved Drawing · 29 Sep 2023
  • Noise impact assessment Report · 29 Sep 2023
  • Pac report Report · 29 Sep 2023
  • Application for planning permission Application Form · 29 Sep 2023
  • Planning supporting statement Report · 29 Sep 2023
  • Storage container elevation Approved Drawing · 29 Sep 2023
  • Transformer elevation Approved Drawing · 29 Sep 2023
  • Transport statement Report · 29 Sep 2023

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

North Ayrshire granted permission on 22 November 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About full applications

A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.

In North Ayrshire

  • 26/00566/PP Granted

    Croyde Alma Road Brodick Isle Of Arran North Ayrshire KA27 8AZ

    Demolition of existing side extensions with replacement single side extension

    Received 24 Aug, published by the council 14 Sep 2026 Full applications
  • 26/00676/PP Awaiting decision

    Roebank Hotel And Wedding Venue Roebank Road Beith North Ayrshire KA15 2DX

    Part change of use of hotel/wedding venue to form dwellinghouse

    Received 5 Oct, published by the council 7 Oct 2026 Full applications
  • 26/00589/PP Granted

    5 Bowfield Road West Kilbride North Ayrshire KA23 9LB

    Erection of replacement detached double garage to include the demolition of existing timber garage

    Received 31 Aug, published by the council 8 Sep 2026 Full applications
  • 26/00606/PP Granted

    Ayrshire Central Hospital Kilwinning Road Irvine North Ayrshire KA12 8SS

    Erection of 28 dwelling houses for social rent to include the demolition of existing buildings, formation of access roads, parking, open space, landscaping, SuDS and ancillary infrastructure

    Received 4 Sep, published by the council 14 Sep 2026 Full applications
  • 26/00520/PP Granted

    Overtoun Of Broadstone Gateside Beith North Ayrshire KA15 1HF

    Siting of residential caravan for a temporary period of up to 5 years

    Received 31 Jul, published by the council 11 Aug 2026 Full applications