Planning application
Land On The West Side Of Celtic Way Celtic Lakes Newport South Wales
Permission granted. Work must normally begin within five years of the decision or the permission lapses.
Proposal
CONSTRUCTION OF 2NO. UNITS UNDER USE CLASS B1, B2 & B8
As published by the council, reference 23/0996
Application record
- Reference
- 23/0996
- Type
- Full (Major)
- Status
- Decided
- Decision
- Granted with Conditions
- Received
- 2 Nov 2023
- Validated
- 15 Jan 2024
- Decided
- 4 Dec 2024
- Ward
- Tredegar Park And Marshfield
- Parish
- Coedkernew Community Council
- Decision by
- Committee
Timeline
Dates from the published record
-
2 Nov 2023
Received by Newport
-
15 Jan 2024
Validated
Checked as complete and ready for consideration.
-
4 Dec 2024
Decision issued: Granted with Conditions
-
14 Aug 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Agent on file, a construction firm registered in Cardiff
42 applications on PlanIndex · across 5 councils · 68% granted
Trade members see who it is, their full track record, and every application they have filed.
See who's behind itDocuments
Plans, drawings, consultee responses and the officer's report
46 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within five years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE
81% historically approved · decision due ~11 Sep
INSTALLATION OF EXTERNAL BUILDING EXTRACT DUCTS, AIR INTAKE/EXTRACT LOUVRES, CONDENSER UNITS AND ENCLOSURES AND ASSOCIATED WORKS
Awaiting decision -
Celtic Technology Centre Celtic Way Celtic Lakes Newport South Wales NP10 8BE
81% historically approved · decision due ~24 Sep
PARTIAL DISCHARGE OF CONDITIONS 10 (SERVICE TESTING AND MAINTENANCE PLAN), 16 (EXTERNAL LIGHTING), 20 (CYCLE PARKING DETAILS), 21 (EV CHARGING), 22 (TRAVEL PLAN) AND 23 (PEDESTRIAN CROSSING AND FOOTWAY) OF 25/0711 S73 APPLICATION TO VARY CONDITIONS 1 (APPROVED PLANS), 7 (LANDSCAPING AND PLANTING SCHEME), 10 (NOISE ASSESSMENT) AND 11 (NOISE SURVEY) OF 20/0039 ERECTION OF 4NO. THREE-STOREY DATA CENTRE BUILDINGS COMPRISING B8 USE AND ANCILLARY B1 USE, PROVISION OF EMERGENCY GENERATORS, SECURITY LODGE, HARD AND SOFT LANDSCAPING, INTERNAL ACCESS ROADS, CAR PARKING AND SUSTAINABLE DRAINAGE. AMENDMENTS INCLUDE CHANGES TO BUILDING FOOTPRINTS AND DESIGN, LOCATION OF GENERATORS, CHANGES TO DRAINAGE STRATEGY AND LANDSCAPING AND OTHER LAYOUT CHANGES
Awaiting decision -
Celtic Technology Centre Celtic Way Celtic Lakes Newport South Wales NP10 8BE
81% historically approved · decision due ~24 Sep
NMA APPLICATION TO VARY CONDITION 2 (NOISE) OF 24/0747 CONSTRUCTION OF AN ELECTRICITY SUBSTATION COMPOUND COMPRISING TRANSFORMERS, SWITCHGEARS AND ELECTRICAL EQUIPMENT, SURFACE WATER DRAINAGE, MEANS OF ACCESS, LANDSCAPING, THE INSTALLATION OF BURIED ELECTRICITY TRANSMISSION CIRCUITS, CREATION OF A HABITAT COMPENSATION SITE AND ASSOCIATED WORKS
Decided -
IP5 Celtic Way Celtic Lakes Newport South Wales NP10 8BE
81% historically approved · decision due ~12 Aug
INSTALLATION OF 1NO. GENERATOR AND ASSOCIATED FLUES & WORKS
Decided -
Quinn Radiators Celtic Way Celtic Lakes Newport NP10 8FS
81% historically approved · decision due ~19 Oct
PARTIAL DISCHARGE OF CONDITION 12 (TRAVEL PLAN) OF 26/0379 S73 APPLICATION TO VARY CONDITIONS 1 (APPROVED PLANS), 3 (LANDSCAPING), 4 (LEMP), 15 (PARKING), 16 (CYCLE STORAGE DETAILS), 17 (FOUL DRAINAGE) AND TO REMOVE CONDITION 6 (DORMICE METHOD STATEMENT) OF 24/0006 DEMOLITION OF REMAINDER OF EXISTING PRINCIPAL BUILDING AND REMAINING STRUCTURES AND CONSTRUCTION OF NEW DATA CENTRE (USE CLASS B8) ACROSS TWO MAIN BUILDINGS PLUS ANCILLARY STRUCTURES ANDS OTHER ASSOCIATED WORKS. AMENDMENTS INCLUDE CHANGES TO LAYOUT AND LANDSCAPING TO ACCOMMODATE SAB REQUIREMENTS, AMENDMENTS AND ADDITIONS TO ADMIN AND DATA HALL BUILDINGS, DESIGN AND SPECIFICATION OF GENERATORS, REVISIONS TO EXTERNAL LIGHTING AND REVISED DETAILS OF ANCILLARY STRUCTURES INCLUDING NEW CONDITION FOR FUTURE PRIMARY SUBSTATION
Awaiting decision Demolition -
Quinn Radiators Celtic Way Celtic Lakes Newport NP10 8FS
81% historically approved · decision due ~10 Aug
PARTIAL DISCHARGE OF CONDITION 14 (AIR QUALITY MANAGEMENT PLAN) OF 25/0379 S73 APPLICATION TO VARY CONDITIONS 1 (APPROVED PLANS), 3 (LANDSCAPING), 4 (LEMP), 15 (PARKING), 16 (CYCLE STORAGE DETAILS), 17 (FOUL DRAINAGE) AND TO REMOVE CONDITION 6 (DORMICE METHOD STATEMENT) OF 24/0006 DEMOLITION OF REMAINDER OF EXISTING PRINCIPAL BUILDING AND REMAINING STRUCTURES AND CONSTRUCTION OF NEW DATA CENTRE (USE CLASS B8) ACROSS TWO MAIN BUILDINGS PLUS ANCILLARY STRUCTURES ANDS OTHER ASSOCIATED WORKS. AMENDMENTS INCLUDE CHANGES TO LAYOUT AND LANDSCAPING TO ACCOMMODATE SAB REQUIREMENTS, AMENDMENTS AND ADDITIONS TO ADMIN AND DATA HALL BUILDINGS, DESIGN AND SPECIFICATION OF GENERATORS, REVISIONS TO EXTERNAL LIGHTING AND REVISED DETAILS OF ANCILLARY STRUCTURES INCLUDING NEW CONDITION FOR FUTURE PRIMARY SUBSTATION
Decided Demolition
Other full applications applications
In Newport
-
26/0397 Granted
Glen View Ponthir Road Newport South Wales NP18 3NW
DEMOLITION OF EXISTING GARAGE AND REAR EXTENSION AND ERECTION OF SINGLE STOREY SIDE AND REAR EXTENSION
-
26/0368 Granted
Streethub Unit On Footpath Outside Monmouthshire House John Frost Square Newport South Wales
PROPOSED INSTALLATION OF 1NO. NEW BT STREET HUB, INCORPORATING 2NO. DIGITAL 75" LCD ADVERT SCREENS, AND ASSOCIATED BT PHONE KIOSK REMOVAL
-
26/0216 Refused
Land Adjacent To Unit 3 Esperanto Way Newport South Wales
PROPOSED CHANGE OF USE FROM OFFICE (B1) TO EVENTS VENUE AND ASSOCIATED WORKS
-
26/0010 Granted
The Grove Bowdens Lane Penhow Newport NP26 3AA
DEMOLITION OF AN EXISTING SEMI-DETACHED DWELLING AND CONSTRUCTION OF A REPLACEMENT TWO-STOREY DETACHED DWELLING, TOGETHER WITH ASSOCIATED WORKS AND USE OF DETACHED HOLIDAY ACCOMMODATION OUTBUILDING AS PRIMARY RESIDENCE FOR DURATION OF CONSTRUCTION PERIOD
-
26/0241 Granted
Liberty Steel Corporation Road Newport NP19 4XE
ENGINEERING WORKS TO CONSTRUCT RAISED BUND AND ACCESS RAMP AROUND APPROVED DATA CENTRE TO A CREST OF APPROXIMATELY 9.75M AOD, PARTIAL DEMOLITION OF A BUILDING, THE IMPORTATION OF FILL MATERIAL TO CREATE THE BUND & RAMP, SURFACING WORKS AND ALTERATIONS TO BUILDING ELEVATIONS TO ACCOMMODATE LEVEL CHANGES