Planning application
31 Royal Oak Drive Newport NP18 1JE
Permission granted. Work must normally begin within five years of the decision or the permission lapses.
Proposal
RETROSPECTIVE APPLICATION FOR THE RETENTION OF A RAISED DECK TO THE FRONT OF THE PROPERTY
As published by the council, reference 22/1123
Application record
- Reference
- 22/1123
- Type
- Full
- Status
- Decided
- Decision
- Granted with Conditions
- Received
- 24 Nov 2022
- Validated
- 18 Jan 2023
- Decided
- 6 Apr 2023
- Ward
- Ringland
- Decision by
- Delegated
- Postcode
- NP18 1JE
Timeline
Dates from the published record
-
24 Nov 2022
Received by Newport
-
18 Jan 2023
Validated
Checked as complete and ready for consideration.
-
6 Apr 2023
Decision issued: Granted with Conditions
-
7 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
10 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Newport granted permission on 6 April 2023, subject to any conditions on the decision notice. Work must normally begin within five years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
44 Royal Oak Drive Newport NP18 1JE
PROPOSED TWO STOREY REAR EXTENSION
Granted Full applications Extension 11 docs -
4 The Coldra Newport NP18 2LP
LAWFUL DEVELOPMENT CERTIFICATE (PROPOSED) FOR ATTIC CONVERSION INCLUDING HIP TO GABLE ROOF EXTENSION AND REAR DORMER AND GARAGE CONVERSION INCLUDING HIP TO GABLE ROOF EXTENSION
Refused Lawful development Extension Loft or dormer 14 docs -
4 The Coldra Newport NP18 2LP
71% historically approved · decision due ~18 Apr
LAWFUL DEVELOPMENT CERTIFICATE FOR PROPOSED ATTIC CONVERSION INCLUDING FLAT ROOF DORMER AND HIP TO GABLE ROOF EXTENSIONS AND A GARAGE CONVERSION WITH HIP TO GABLE ROOF
Awaiting decision Lawful development Extension Loft or dormer 14 docs -
46 The Coldra Newport NP18 2LR
DEMOLISH DETACHED GARAGE AND ERECT SINGLE STOREY REAR AND SIDE EXTENSION WITH LOFT CONVERSION
Granted Full applications Extension Loft or dormer +1 16 docsSmall domestic -
10 Tom Mann Close Newport South Wales NP19 9DR
LAWFUL DEVELOPMENT CERTIFICATE FOR A PROPOSED SINGLE STOREY REAR EXTENSION
Granted Lawful development Extension 6 docsSmall domestic -
10 Tom Mann Close Newport South Wales NP19 9DR
81% historically approved · decision due ~8 Sep
LAWFUL DEVELOPMENT CERTIFICATE FOR A PROPOSED SINGLE STOREY REAR EXTENSION AND DEMOLITION OF CONSERVATORY
Decided Extension DemolitionSmall domestic
Other full applications
In Newport
-
26/0397 Granted
Glen View Ponthir Road Newport South Wales NP18 3NW
DEMOLITION OF EXISTING GARAGE AND REAR EXTENSION AND ERECTION OF SINGLE STOREY SIDE AND REAR EXTENSION
-
26/0368 Granted
Streethub Unit On Footpath Outside Monmouthshire House John Frost Square Newport South Wales
PROPOSED INSTALLATION OF 1NO. NEW BT STREET HUB, INCORPORATING 2NO. DIGITAL 75" LCD ADVERT SCREENS, AND ASSOCIATED BT PHONE KIOSK REMOVAL
-
26/0216 Refused
Land Adjacent To Unit 3 Esperanto Way Newport South Wales
PROPOSED CHANGE OF USE FROM OFFICE (B1) TO EVENTS VENUE AND ASSOCIATED WORKS
-
26/0010 Granted
The Grove Bowdens Lane Penhow Newport NP26 3AA
DEMOLITION OF AN EXISTING SEMI-DETACHED DWELLING AND CONSTRUCTION OF A REPLACEMENT TWO-STOREY DETACHED DWELLING, TOGETHER WITH ASSOCIATED WORKS AND USE OF DETACHED HOLIDAY ACCOMMODATION OUTBUILDING AS PRIMARY RESIDENCE FOR DURATION OF CONSTRUCTION PERIOD
-
26/0241 Granted
Liberty Steel Corporation Road Newport NP19 4XE
ENGINEERING WORKS TO CONSTRUCT RAISED BUND AND ACCESS RAMP AROUND APPROVED DATA CENTRE TO A CREST OF APPROXIMATELY 9.75M AOD, PARTIAL DEMOLITION OF A BUILDING, THE IMPORTATION OF FILL MATERIAL TO CREATE THE BUND & RAMP, SURFACING WORKS AND ALTERATIONS TO BUILDING ELEVATIONS TO ACCOMMODATE LEVEL CHANGES