Planning application
81 Western Avenue Newport NP20 3QY
Works: Extension Demolition Small domestic
Read from the description, not a valuation. How we read the register
Permission granted. Work must normally begin within five years of the decision or the permission lapses.
Proposal
PROPOSED DEMOLITION OF EXISTING GARAGE, TWO STOREY SIDE EXTENSION AND SINGLE STOREY REAR EXTENSION
As published by the council, reference 21/0599
Application record
- Reference
- 21/0599
- Type
- Full
- Status
- Decided
- Decision
- Granted with Conditions
- Received
- 2 Jun 2021
- Validated
- 2 Jun 2021
- Decided
- 12 Aug 2021
- Ward
- Allt-yr-Yn
- Decision by
- Delegated
- Postcode
- NP20 3QY
Timeline
Dates from the published record
-
2 Jun 2021
Received by Newport
-
12 Aug 2021
Decision issued: Granted with Conditions
-
7 Aug 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Agent on file, an architecture practice registered in Cardiff
84 applications on PlanIndex · across 4 councils · 92% granted
Trade members see who it is, their full track record, and every application they have filed.
See who's behind itDocuments
Plans, drawings, consultee responses and the officer's report
12 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Trade members open them from here.
Open the documentsWhat this grant of permission means
Newport granted permission on 12 August 2021, subject to any conditions on the decision notice. Work must normally begin within five years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 500 metres
-
126 Western Avenue Newport NP20 3QX
FIRST FLOOR SIDE AND REAR EXTENSION AND A REAR BOX DORMER
Refused Full applications Extension Loft or dormer 9 docs -
132 Western Avenue Newport NP20 3QX
PROPOSED OUTBUILDING AND RAISED DECKING IN REAR GARDEN (PART RETROSPECTIVE)
Granted Full applications 7 docs -
11 Vancouver Drive Newport NP20 3QT
PROPOSED DEMOLITION OF EXISTING REAR PORCH, DETACHED REAR STORE AND PART OF THE GARAGE AND CONSTRUCTION OF SINGLE STOREY SIDE/REAR EXTENSION, ALONG WITH REPLACEMENT OF FRONT PORCH (RETROSPECTIVE)
Granted Full applications Extension Demolition 9 docsSmall domestic -
18 Melbourne Way Newport NP20 3RE
DEMOLISH EXISTING GARAGE AND BUILD TWO STOREY SIDE EXTENSION
Granted Full applications Extension Demolition 6 docs -
18 Melbourne Way Newport NP20 3RE
NON MATERIAL AMENDMENT TO VARY CONDITION 1 (APPROVED PLANS) OF PLANNING PERMISSION 25/1023 DEMOLISH EXISTING GARAGE AND BUILD TWO STOREY SIDE EXTENSION
Refused Amendments Extension Demolition 4 docs -
Greenmeadow Glasllwch Lane Newport NP20 3PT
SINGLE STOREY REAR EXTENSION
Granted Full applications Extension 13 docsSmall domestic
Other full applications
In Newport
-
26/0397 Granted
Glen View Ponthir Road Newport South Wales NP18 3NW
DEMOLITION OF EXISTING GARAGE AND REAR EXTENSION AND ERECTION OF SINGLE STOREY SIDE AND REAR EXTENSION
-
26/0368 Granted
Streethub Unit On Footpath Outside Monmouthshire House John Frost Square Newport South Wales
PROPOSED INSTALLATION OF 1NO. NEW BT STREET HUB, INCORPORATING 2NO. DIGITAL 75" LCD ADVERT SCREENS, AND ASSOCIATED BT PHONE KIOSK REMOVAL
-
26/0216 Refused
Land Adjacent To Unit 3 Esperanto Way Newport South Wales
PROPOSED CHANGE OF USE FROM OFFICE (B1) TO EVENTS VENUE AND ASSOCIATED WORKS
-
26/0010 Granted
The Grove Bowdens Lane Penhow Newport NP26 3AA
DEMOLITION OF AN EXISTING SEMI-DETACHED DWELLING AND CONSTRUCTION OF A REPLACEMENT TWO-STOREY DETACHED DWELLING, TOGETHER WITH ASSOCIATED WORKS AND USE OF DETACHED HOLIDAY ACCOMMODATION OUTBUILDING AS PRIMARY RESIDENCE FOR DURATION OF CONSTRUCTION PERIOD
-
26/0241 Granted
Liberty Steel Corporation Road Newport NP19 4XE
ENGINEERING WORKS TO CONSTRUCT RAISED BUND AND ACCESS RAMP AROUND APPROVED DATA CENTRE TO A CREST OF APPROXIMATELY 9.75M AOD, PARTIAL DEMOLITION OF A BUILDING, THE IMPORTATION OF FILL MATERIAL TO CREATE THE BUND & RAMP, SURFACING WORKS AND ALTERATIONS TO BUILDING ELEVATIONS TO ACCOMMODATE LEVEL CHANGES