Planning application
26/10691
BLOCK 40A, FAWLEY REFINERY, MARSH LANE, HARDLEY, FAWLEY SO45 1TX
Proposal
Demolition of redundant maintenance workshop (Demolition Prior Approval)
As published by the council, reference 26/10691
Timeline
Dates from the published record
-
21 Jul 2026
Received by New Forest
-
26 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
The statutory target is eight weeks for most applications and thirteen for major development. Extensions of time are common.
What happens while it is decided
The process from here
This application is with New Forest for determination. The council publicises it, consults neighbours and technical bodies where required, and weighs the responses against local and national planning policy.
The statutory target is eight weeks for most applications and thirteen for major development, though extensions of time are common. Comments carry most weight while the case is undecided, so check the council portal for the deadline if you want to respond.
About other applications
How this application type works
This application sits outside the common categories, which can include county matters such as minerals and waste, works by statutory undertakers, demolition notifications and other less frequent procedures. The council record linked below sets out the specific procedure that applies, and the description above is taken directly from the published register.
Nearby applications
Within 500 metres
-
26/10546 Granted
ESSO PETROLEUM COMPANY LIMITED, MARSH LANE, FAWLEY SO45 1TX
Demolition of two redundant storage buildings on the old polimeri site (Demolition Prior Notification)
-
25/11019 Granted
BLOCK 42A, EXXONMOBIL CHEMICAL LIMITED, MARSH LANE, FAWLEY SO45 1TX
Demolition of redundant equipment associated with Benzene unit (DEMOLITION PRIOR NOTIFICATION APPLICATION)
-
26/10024 Granted
BLOCK 4, FAWLEY REFINERY, CADLAND ROAD, HARDLEY, FAWLEY SO45 1TX
Demolition of redundant facilities in block 4 (Demolition Prior Notification)
-
26/10308 Granted
BLOCK 05, FAWLEY REFINERY, CADLAND ROAD, HARDLEY, FAWLEY SO45 1TX
Demolition of PS2 facilities and redundant PS1 furnaces in block 05 (Demolition Prior Notification)
-
26/10205 Granted
ESSO PETROLEUM COMPANY LIMITED, MARSH LANE, FAWLEY SO45 1TX
Demolition of Redundant CS3 and CS4 units (Demolition Prior Notification)
-
26/10691 Awaiting decision
BLOCK 40A, FAWLEY REFINERY, MARSH LANE, HARDLEY, FAWLEY SO45 1TX
Demolition of redundant maintenance workshop (Demolition Prior Approval)
Other other applications
In New Forest
-
26/10611 Granted
MARCHWOOD WASTE TRANSFER STATION, BURY ROAD, MARCHWOOD SO40 4UD
Retention of existing dry recycables transfer bay and use of part of site for storage of empty containers/bins and installation of a new sweepings bay and additional weighbridge with BNG mitigation area
-
26/10682 Awaiting decision
MARCHWOOD MILITARY PORT, CRACKNORE HARD, MARCHWOOD SO40 4ZG
Demolition of buildings in the assault course and dog kennels (Demolition Prior Notification)
-
26/10546 Granted
ESSO PETROLEUM COMPANY LIMITED, MARSH LANE, FAWLEY SO45 1TX
Demolition of two redundant storage buildings on the old polimeri site (Demolition Prior Notification)
-
26/10536 Refused
PROVOST FARM, ROCKBOURNE SP6 3NR
Agricultural building to store hay, straw and agricultural machinery (Prior Approval Application)
-
26/10028 Granted
NEA FARM QUARRY, SALISBURY ROAD, ELLINGHAM HARBRIDGE & IBSLEY BH24 3PF
New development comprising the proposed extraction of sand & gravel & deep sand (incorporating the diversion of public footpaths) with restoration to agriculture, commercial forestry, deciduous woodland & heathland & associated development including: 1. The construction of a mineral washing plant at Burnt Hill together with the storage of Plumley Wood mineral at Burnt Hill with restoration of the site to heathland; 2. Extension of existing field conveyor system from Nea Farm Quarry to Plumley Wood (via Burnt Hill) including bridge sections over Harbridge Drove & public footpath at Plumley Wood; 3. The phased redevelopment of Blashford Plant site including the extension of the plant site & recycling operations into Lodge Field; 4. Variation of conditions of Planning Permission No. 06/88238 including key variations to condition 2 (extension of time), 6 (hours of working), 24 (stockpile heights), 27 (screen bunding at Blashford) & 48 (storage capacity of recycled aggregates/arisings)