Planning application
Land at FORMER FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Works: Demolition
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Site 1: Temporary storage of wind turbine blades on site of demolished Fawley Power Station Boiler House; Site 2: Temporary storage of wind turbine blades on the site of the Fawley Power Station Control Room and the adjoining car park.
As published by the council, reference 23/10050
Application record
- Reference
- 23/10050
- Type
- Full Planning Permission
- Status
- Decided
- Decision
- Granted As published: Grant Temporary Permission
- Received
- 17 Jan 2023
- Validated
- 17 Jan 2023
- Decided
- 3 May 2023
- Ward
- Fawley, Blackfield, Calshot & Langley
- Parish
- Fawley
- Decision by
- Development Control Committee
- Postcode
- SO45 1TW
Timeline
Dates from the published record
-
17 Jan 2023
Received by New Forest National Park
-
3 May 2023
Decision issued: Grant Temporary Permission
-
7 Sep 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
1 later application on the register refers to this one:
-
25/10972 Granted
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Removal of condition 1 and Variation of condition 2 of Planning Permission 23/10050 to enable the approved temporary storage use to continue until 31st December 2026
Who's behind it
Company information only, from the register and Companies House
Adams Infrastructure Planning Ltd. Agent, a planning consultancy registered in Winchester
Dissolved · incorporated 2012 · Winchester
1 application on PlanIndex
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
31 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
New Forest National Park granted permission on 3 May 2023, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Request for an EIA Screening Opinion Under Part 2 (6) of The Town And Country Planning (Environmental Impact Assessment) Regulations 2017 (As Amended) to confirm if an environmental impact assessment (EIA) is required in respect of a proposed Temporary use of the land for storage and distribution
Decided Outline 5 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Request for an EIA Screening Opinion Under Part 2 (6) of The Town And Country Planning (Environmental Impact Assessment) Regulations 2017 (As Amended) to confirm if an environmental impact assessment (EIA) is required in respect of a proposed Temporary use of the land for storage and distribution
Decided Outline 5 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Removal of condition 1 and Variation of condition 2 of Planning Permission 23/10050 to enable the approved temporary storage use to continue until 31st December 2026
Granted Amendments 43 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Variation of Condition 1 of Planning Permission 24/10861 to extend the use for storage and distribution (Use Class B8) until 31st December 2026
Granted Amendments 42 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY SO45 1TW
Variation of Condition 1 of Planning Permission 24/11096 to extend the mixed use of land for haulage and B8 storage until 31st December 2026
Granted Amendments 32 docs -
SITE OF FAWLEY POWER STATION, FAWLEY ROAD, FAWLEY, SO45 1TW
Use of land to provide open storage of gravel (use class B8) and associated works including provision of containment bunds, drainage channels and excavation, temporary permission sought for 5 years (Variation of Condition 3 (Timescale) of planning permission 18/11145)
Granted Other 5 docs
Other full applications
In New Forest National Park
-
26/10783 Granted
4 ATHELING ROAD, HYTHE SO45 6BR
Garage extension
-
26/10820 Granted
2 WENDOVER CLOSE, BARTON-ON-SEA, NEW MILTON BH25 7LX
Single-storey rear extension
-
26/10818 Granted
APRIL FOLLY, 14 THORESBY COURT, NEW MILTON BH25 5UJ
Replacement porch; additional window to front elevation
-
26/10816 Granted
SPINNAKER LODGE, 40 KEYHAVEN ROAD, MILFORD-ON-SEA SO41 0QY
Single-storey rear extension; new conservatory roof; rooflights; front porch infill; fenestration alterations.
-
26/10780 Granted
LAND ADJACENT 1 NEW COTTAGES, BICKTON LANE, BICKTON, FORDINGBRIDGE SP6 2EZ
Manege