Planning application
P2026/0421
42km Off SW Coast Of Pembrokeshire
Proposal
DNS EIA scoping consultation: Gwynt Glas Offshore Wind Farm a large-scale floating offshore wind energy project
As published by the council, reference P2026/0421
Timeline
Dates from the published record
-
29 Jun 2026
Received by Neath Port Talbot
-
17 Jul 2026
Decision issued: Scoping Opinion
-
28 Jul 2026
Added to PlanIndex
After the decision
The process from here
The council has decided this application; the published outcome sits in the record above and the decision notice on the council portal carries the detail, including any conditions.
If permission was granted, work must normally begin within five years of the decision. If it was refused, the applicant can appeal within the statutory time limit or submit a revised scheme.
About outline applications
How this application type works
An outline application tests the principle of developing a site before the detail is worked up. Some or all of the particulars, such as appearance, layout, scale, access and landscaping, are held back as reserved matters for later approval. Permission at outline stage does not by itself allow building to start; the reserved matters must be approved first.
Other outline applications
In Neath Port Talbot
-
P2026/0426 Awaiting decision
Cryddan Brook Flood Alleviation Scheme Melyn Neath
Request for Screening opinion under Regulation 6 of the Town and Country Planning (Environment Impact Assessment) (Wales) Regulations 2017 for a proposed Flood Alleviation Scheme
-
P2025/0792 Granted
Land East Of Minyrawel Pen Yr Alltwen Rhos Pontardawe Neath Port Talbot
Outline application for residential development for up to 8 dwellings with approval sought for access, and all other matters reserved
-
P2026/0410 Awaiting decision
Abernant Colliery Pontardawe SA8 4SX
Request for Screening opinion under Regulation 6 of the Town and Country Planning (Environment Impact Assessment) (Wales) Regulations 2017 for a proposed biomass gasification Combined Heat and Power (CHP) waste-to-hydrogen production facility
-
P2026/0328 Decided
Cymmer Port Talbot
Request for Screening opinion under Regulation 6 of the Town and Country Planning (Environmental Impact Assessment) (Wales) Regulations 2017, for the Proposed Cymmer Carriageway Realignment Works.
-
P2026/0224 Refused
Land To Rear Of 9 Maes Llwynonn Cadoxton Neath Port Talbot SA10 8AQ
Outline application for 1.no detached dwelling and associated parking with access, layout and scale to be considered (appearance and landscaping reserved).