Planning application
Glanllynfi Garth Wind Farm Located Between Dyffryn, Maesteg And Garth And Blaengarw Pontycymer And Ponty-y-rhyl
Decided. The decision notice on the council portal carries the outcome in full, including any conditions.
Proposal
DNS EIA scoping consultation: Construction and operation of a wind farm of up to eight turbines (with a maximum blade tip height of 180 m) and associated infrastructure including access tracks and substation.
As published by the council, reference P2026/0130
Application record
- Reference
- P2026/0130
- Type
- Nat. Sig. Infrastructure Project/DNS
- Status
- Decided
- Decision
- Scoping Opinion
- Received
- 3 Mar 2026
- Validated
- 3 Mar 2026
- Decided
- 18 Mar 2026
- Ward
- Cymmer & Glyncorrwg
- Parish
- Blaengwrach Community Council
- Decision by
- Delegated Decision
Timeline
Dates from the published record
-
3 Mar 2026
Received by Neath Port Talbot
-
18 Mar 2026
Decision issued: Scoping Opinion
-
28 Jul 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
Documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsAfter the decision
Neath Port Talbot has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Neath Port Talbot's portal will say. Our guide explains the common types.
Nearby applications
Within 0.3 miles
-
12 Scotch Street Abergwynfi SA13 3YS
Single storey rear extension - Certificate of lawful development (Proposed) (amended elevation plans received 20/03/2023)
Decided Lawful development Extension 5 docsSmall domestic