Planning application
P2025/0606
Groundhog Uk Ltd Ynysygerwn Avenue Aberdulais Neath Port Talbot SA10 8HH
Proposal
Side extension to existing factory to house new production line
As published by the council, reference P2025/0606
Timeline
Dates from the published record
-
21 Aug 2025
Received by Neath Port Talbot
-
15 Oct 2025
Decision issued: Approved
-
28 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within five years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About full applications applications
How this application type works
A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.
Nearby applications
Within 500 metres
-
P2025/0878 Granted
GroundHog UK Ltd Unit 1 Ynysygerwn Avenue Aberdulais Neath Port Talbot SA10 8HH
Details in association with the partial discharge of condition 3 (Criteria (i) only - contaminated land desk top study) of P2025/0606 (Side extension to existing factory to house new production line) granted 15.10.2025
-
P2025/0813 Granted
Unit 1 Ynysygerwn Avenue Aberdulais Neath Port Talbot SA10 8HH
Details to be agreed in association with condition 4 (noise impact assessment) of P2025/0606 (Side extension to existing factory to house new production line) granted 15.10.2025
-
P2026/0097 Granted
Unit 1 Ynysygerwn Avenue Aberdulais Neath Port Talbot SA10 8HH
Details in association with the discharge of condition 3 (contaminated land desk top study) and 5 (remediation scheme) of P2025/0606 (Side extension to existing factory to house new production line) granted 15.10.2025 (Condition 3 already partially discharged under reference P2025/0878 on 09.01.2026)
-
P2026/0110 Decided
Unit 2 Ynysygerwn Avenue Aberdulais Neath Port Talbot SA10 8HH
Certificate of Lawful Development (Proposed) for the installation of a solar panel system (additional information received 05.03.26).
Other full applications applications
In Neath Port Talbot
-
P2026/0404 Withdrawn
3 Tai'r Ynys Fawr Pontrhydyfen Neath Port Talbot SA12 9RU
Rear single storey bedroom, shower room and porch extension
-
P2026/0159 Granted
44 Leyshon Road Gwaun Cae Gurwen Neath Port Talbot SA18 1EN
Proposed two storey rear extension (amended location and site plan received 24/06/2026).
-
P2026/0263 Granted
3 Heol Y Gwrgan Margam Neath Port Talbot SA13 2DG
Retention and completion of a detached garage
-
P2026/0491 Awaiting decision
7 Plas Road Rhos Pontardawe Neath Port Talbot SA8 3HD
Retrospective application for a single storey rear extension in addition to a raised decking area.
-
P2026/0353 Granted
61 Neath Road Briton Ferry Neath Port Talbot SA11 2DX
Proposed replacement of a uPVC framed shop front to aluminium