Skip to content
PlanIndex Get alerts
Menu

Planning application

LA09/2025/1268/F

36 Canal Quay Coalisland

Granted Mid Ulster Full

Proposal

Single storey extension to the rear of the existing dwelling.

As published by the council, reference LA09/2025/1268/F

Timeline

Dates from the published record

  1. 9 Dec 2025

    Received by Mid Ulster

  2. 10 Dec 2025

    Validated

    Checked as complete and ready for consideration.

  3. 19 Mar 2026

    Decision issued: Permission Granted

  4. 29 Jul 2026

    Added to PlanIndex

What a grant of permission means

The process from here

Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.

Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.

About full applications applications

How this application type works

A full application seeks permission for a complete, detailed proposal in one go: siting, design, access and landscaping are all fixed at this stage. It is the standard route for new buildings, conversions and changes of use. The statutory target is eight weeks for smaller schemes and thirteen weeks for major development, though complex cases often take longer by agreement.

More on full applications applications in our guide

Nearby applications

Within 500 metres

  • LA09/2025/0837/F Withdrawn

    12 Canal Quay Coalisland BT71 4LR

    Retention of existing Dog Grooming Parlour

    8 Aug 2025 138m away Full applications
  • 12 Canal Quay Coalisland BT71 4LR

    Retention of existing dog grooming parlour including extension of curtilage of site

    13 Oct 2025 138m away Full applications
  • LA09/2026/0720/F Awaiting decision

    Site adjacent to 2 Millbrook Close Washingbay Road Coalisland

    Eerection of 3 no. dwellings within existing 'Millbrook' housing development comprising of 1 no. pair of semi-detached and 1 no. detached dwelling.

    10 Jul 2026 241m away Full applications
  • LA09/2026/0641/F Awaiting decision

    17 Columbas Villas Coalisland Tyrone BT71 4PX

    Single storey extension to rear of dwelling to provide bedroom,bathroom and utility room

    18 Jun 2026 246m away Full applications
  • LA09/2026/0552/F Awaiting decision

    Site On Gortgonis Road Coalisland adjacent to Sports Field and Occupied By existing Community Center

    Application ref LA09/2018/1384/F . We wish to vary condition 4 to allow the development to commence before completion of the new accesses. The school is to open in Sept 2027. To allow sufficient time to construct the new buildings to meet this date work will need to commence on the new structures in the first week of July 2026, however it has become apparent that the works to from the new access will not be complete at this time . This is due to factors outside the control of the applicant and the appointed contractor. NIE are required to relocate existing cabling in the roadway and their programme for this will delay the developers works in forming the new access. If the school is to open in the new academic year works to form the access and new buildings will need to initial run in parallel. It is our understanding that the condition is to partly to mitigate against the risk developers completing development and then failing to provide the access. We feel that there is no risk in this instance as the developer is a Statutory Body (EA) and contracts for all works are in place. The contractor will neccessarily be providing traffiic control around the works areas to facilitate the operations on site and formation of the new roadways . The intensification of use to the site will not occcur until completion. We therefore do not belive that varying the condition will present a greater road safety risk. A programme showing the critical dates which demonstrates the need for the works to both the newaccess and school to be carried out simultaniously is attached. The attached drawing shows the oriiginal phasing plan . By varying the condition we would hope to carry out phases 2+3 and possibly the initial stages of phase 4 in parallel time with phase 1. The exact timings being dependant on the progress of the works by NIE . The intent is to have phase 1 completed as expeditiously and as early in the contract as possible.

    27 May 2026 327m away Full applications
  • LA09/2026/0522/PAN Awaiting decision

    4 Washingbay Road Coalisland BT71 4ND

    Demolition of existing buildings, erection of discount foodstore, access, parking, landscaping and associated site works.

    19 May 2026 377m away

In Mid Ulster

  • LA09/2026/0757/F Awaiting decision

    95 Annaghmakeown Road Dungannon BT70 3DD

    Front & rear single storey extensions including associated alterations and raised patio area to front

    27 Jul 2026 Full applications
  • LA09/2026/0755/F Awaiting decision

    Between Nos 60 and 62 Carricknakielt Road Maghera

    Infill dwelling and garage

    24 Jul 2026 Full applications
  • LA09/2026/0753/F Awaiting decision

    Land adjacent and North of 76 Aughrim Road Magherafelt

    Expansion of existing rural business to provide 3no. light industrial units with associated parking

    24 Jul 2026 Full applications
  • LA09/2026/0754/F Awaiting decision

    18 Hillside Crescent Moy BT71 7SS

    Extension to dwelling

    24 Jul 2026 Full applications
  • 103A Dunnamore Road Cookstown

    Amended access from previously approved under LA09/2023/0003/F, to use existing access and lane

    12 Jun 2026 Full applications