Planning application
LA09/2025/1011/O
Land immediately North East of 18 Loughview Road Coalisland
Proposal
Dwelling
As published by the council, reference LA09/2025/1011/O
Timeline
Dates from the published record
-
26 Sep 2025
Received by Mid Ulster
-
29 Sep 2025
Validated
Checked as complete and ready for consideration.
-
29 Apr 2026
Decision issued: Permission Granted
-
29 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About outline applications
How this application type works
An outline application tests the principle of developing a site before the detail is worked up. Some or all of the particulars, such as appearance, layout, scale, access and landscaping, are held back as reserved matters for later approval. Permission at outline stage does not by itself allow building to start; the reserved matters must be approved first.
Nearby applications
Within 500 metres
-
LA09/2025/0870/F Awaiting decision
Lands Accessing South of Gortview Park and East of The Pine Bank Gardens, Coalisland
Erection of 10 dwellings and 18 apartments at lands to Gortgonis Road, Coalisland
-
LA09/2025/1312/LDE Granted
Lands to The rear of Knockmoy Park, Gortevein Terrace and Fronting Gortgonis Terrace, Coalisland
Erection of 22 dwellings and ancillary development, amendment to development previously approved by M/2015/0060/F
-
LA09/2025/0837/F Withdrawn
12 Canal Quay Coalisland BT71 4LR
Retention of existing Dog Grooming Parlour
-
LA09/2025/1069/F Granted
12 Canal Quay Coalisland BT71 4LR
Retention of existing dog grooming parlour including extension of curtilage of site
-
LA09/2026/0552/F Awaiting decision
Site On Gortgonis Road Coalisland adjacent to Sports Field and Occupied By existing Community Center
Application ref LA09/2018/1384/F . We wish to vary condition 4 to allow the development to commence before completion of the new accesses. The school is to open in Sept 2027. To allow sufficient time to construct the new buildings to meet this date work will need to commence on the new structures in the first week of July 2026, however it has become apparent that the works to from the new access will not be complete at this time . This is due to factors outside the control of the applicant and the appointed contractor. NIE are required to relocate existing cabling in the roadway and their programme for this will delay the developers works in forming the new access. If the school is to open in the new academic year works to form the access and new buildings will need to initial run in parallel. It is our understanding that the condition is to partly to mitigate against the risk developers completing development and then failing to provide the access. We feel that there is no risk in this instance as the developer is a Statutory Body (EA) and contracts for all works are in place. The contractor will neccessarily be providing traffiic control around the works areas to facilitate the operations on site and formation of the new roadways . The intensification of use to the site will not occcur until completion. We therefore do not belive that varying the condition will present a greater road safety risk. A programme showing the critical dates which demonstrates the need for the works to both the newaccess and school to be carried out simultaniously is attached. The attached drawing shows the oriiginal phasing plan . By varying the condition we would hope to carry out phases 2+3 and possibly the initial stages of phase 4 in parallel time with phase 1. The exact timings being dependant on the progress of the works by NIE . The intent is to have phase 1 completed as expeditiously and as early in the contract as possible.
Other outline applications
In Mid Ulster
-
LA09/2026/0760/O Awaiting decision
Approx. 100M NW of 27 Tycanny Road Tycanny Ballygawley
Application for Outline Planning permission for a dwelling on a farm
-
LA09/2026/0752/O Awaiting decision
Approximately 75M East of 49 Aughrim Rd Magherafelt
Replacement dwelling under PPS 21 CTY 3
-
LA09/2026/0751/O Awaiting decision
50M North East of 49 Kilrea Road Portglenone
Renewal of planning application LA09/2023/0482/O
-
LA09/2026/0742/O Awaiting decision
Land approximately 80M North West of 226 Hillhead Road Knockloughrim Magherafelt
Off site replacement dwelling under PPS 21 CTY 3 with retention of existing building as an outbuilding
-
LA09/2026/0738/O Awaiting decision
Lands immediately North East of 36 Ballymaguigan Road Magherafelt
Replacement dwelling and garage