East Anglia Three Offshore Windfarm

Granted Mid Suffolk DC/21/00065 Discharge of Requirement

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Approval of details reserved by Requirement 23 (External Lighting and Control of Artificial Light Emissions (Parts 1 and 2)) pursuant to The East Anglia THREE Offshore Wind Farm Order 2017

As published by the council, reference DC/21/00065

Application record

Reference
DC/21/00065
Type
Discharge of Requirement
Status
Granted
Decision
Granted
Received
18 Dec 2020
Validated
19 Dec 2020
Decided
22 Feb 2021
Decision by
Delegated Decision

Site history

Applications at this address on the Mid Suffolk register

This site has had 3 applications since 2020: 3 approved, 0 refused.

  • DC/21/00046 Granted

    East Anglia Three Offshore Windfarm

    Approval of details reserved by Requirements 18 (Surface and Foul Water Drainage) and 22 (Code of Construction Practice (Parts 1-2A) pursuant to The East Anglia THREE Offshore Wind Farm Order 2017

    Decided 24 Feb 2021 Conditions
  • DC/21/00064 Granted

    East Anglia Three Offshore Windfarm

    Approval of details reserved by Requirement 23 (External Lighting and Control of Artificial Light Emissions (Parts 3 and 4)) pursuant to The East Anglia THREE Offshore Wind Farm Order 2017

    Decided 22 Feb 2021 Conditions

Timeline

Dates from the published record

  1. 18 Dec 2020

    Received by Mid Suffolk

  2. 19 Dec 2020

    Validated

    Checked as complete and ready for consideration.

  3. 22 Feb 2021

    Decision issued: Granted

  4. 22 Sep 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

9 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Mid Suffolk granted permission on 22 February 2021, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About condition discharge and variation applications

This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.

Nearby applications

Within 0.3 miles

  • East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk

    DC/21/00067 Submitted 21 Dec 2020 50 yards away

    Approval of details reserved by Requirement 24 (Control of noise during operational phase (Part 2)) pursuant to The East Anglia ONE Offshore Wind Farm Order 2014

    Granted Conditions 6 docs
  • East Anglia Three Offshore Windfarm

    DC/21/00046 Submitted 18 Dec 2020 50 yards away

    Approval of details reserved by Requirements 18 (Surface and Foul Water Drainage) and 22 (Code of Construction Practice (Parts 1-2A) pursuant to The East Anglia THREE Offshore Wind Farm Order 2017

    Granted Conditions 8 docs
  • East Anglia Three Offshore Windfarm

    DC/21/00064 Submitted 18 Dec 2020 50 yards away

    Approval of details reserved by Requirement 23 (External Lighting and Control of Artificial Light Emissions (Parts 3 and 4)) pursuant to The East Anglia THREE Offshore Wind Farm Order 2017

    Granted Conditions 7 docs
  • East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk

    DC/26/02120 Submitted 19 May 2026 50 yards away

    East Anglia 3 Onshore Converter Station - Application pursuant to discharge of requirements 24 and 25(2)(f). to agree out of hours working (a request for out of hours working on the following dates May: 24th, 25th & 31st (07:00 hrs to 17:00hrs) and June: 7th, 14th, 21st & 28th (07:00 hrs to 17:00hrs)

    Granted Conditions 3 docs
  • East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk

    DC/26/02120 Submitted 19 May 2026 50 yards away

    East Anglia 3 Onshore Converter Station - Application pursuant to discharge of requirements 24 and 25(2)(f). to agree out of hours working (a request for out of hours working on the following dates May: 24th, 25th & 31st (07:00 hrs to 17:00hrs) and June: 7th, 14th, 21st & 28th (07:00 hrs to 17:00hrs)

    Granted Conditions 3 docs
  • East Anglia Three Offshore Windfarm Tye Lane Bramford Suffolk

    DC/26/02487 Submitted 10 Jun 2026 50 yards away

    East Anglia Three - Onshore Cable Route: Out of hours working request for the following dates June: 21st, 28th, July: 05th, 12th 19th and 26th (10:00 - 16:00).

    Granted Conditions 3 docs

In Mid Suffolk

  • DC/26/04105 Awaiting decision

    Old Stoke Farmhouse Straight Road Battisford Stowmarket Suffolk IP14 2NB

    Discharge of Conditions Application for DC/26/01654 - Conditions 3 (Fenestration Details), 4 (Eaves & Verge Details) and 5 (Material Details)

    Received 21 Sep, published by the council 22 Sep 2026 Conditions
  • DC/26/04075 Awaiting decision

    St Nicholas's Church Church Lane Bedfield Suffolk

    Discharge of Conditions Application for DC/25/01110 - Conditions 5 (Roofing Materials) and 8 (Written Scheme of Investigation)

    Received 18 Sep, published by the council 22 Sep 2026 Conditions
  • DC/26/04084 Awaiting decision

    Hill Farm Valley Lane Great Finborough Stowmarket Suffolk IP14 3BB

    Discharge of Conditions Application for DC/25/00356 - Conditions 4 (Windows and Doors), 5 (Render), 6 (Mechanical Ventilation), 8 (External Facing Materials), 9 (Eaves and Verges) and 11 (Bat Licence)

    Received 18 Sep, published by the council 22 Sep 2026 Conditions
  • DC/26/04049 Awaiting decision

    Port One Business And Logistics Park Bramford Road Little Blakenham Part In The Parish Of Great Blakenham

    Discharge of Conditions Application for DC/22/06288 - Conditions 9 (Green Corridor) and 10 (Bramford Road and Pound Lane Landscaping)

    Received 17 Sep, published by the council 22 Sep 2026 Conditions
  • DC/26/04050 Awaiting decision

    Port One Business And Logistics Park Bramford Road Little Blakenham Part In The Parish Of Great Blakenham

    Discharge of Conditions Application for DC/22/06288 - Conditions 43 (External Plant Unit 14/Phase 1), 55 (Wildlife Sensitive Lighting Design Scheme Unit 14/Phase 1) and 56 (Biodiversity Enhancement Strategy Unit 14/Phase 1)

    Received 17 Sep, published by the council 22 Sep 2026 Conditions