Former Kingsnorth Power Station Power Station Access Road Hoo St Werburgh Rochester Medway ME3 9NQ
Works: Demolition
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Application for approval of reserved matters being Access, Appearance, Landscape, Scale and Layout for part of the site-wide infrastructure including spine road, associated landscaping, drainage and lighting pursuant to Outline Planning Permission ref. MC/21/0979 for the construction of flexible EG (iii)/B2/B8 use class buildings, sui generis uses for energy uses and a lorry park, together with servicing, parking, landscaping, drainage, remediation, demolition and earthworks.
As published by the council, reference MC/26/1894
Application record
- Reference
- MC/26/1894
- Status
- Registered
- Received
- 1 Oct 2026
- Validated
- 1 Oct 2026
- Ward
- Hoo St Werburgh & High Halstow
- Parish
- Hoo St. Werburgh
- Postcode
- ME3 9NQ
Timeline
Dates from the published record
-
1 Oct 2026
Received by Medway
-
6 Oct 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 26 November 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Medway took a median of 55 days over the applications it decided in the last year.
Related applications
Cases linked to this one on the register
- Application: MC/21/0979 (Decided)
Who's behind it
Company information only, from the register and Companies House
Stantec PLC Agent, registered in Warrington
Active · incorporated 2024 · Warrington
388 applications on PlanIndex · across 112 councils · 94% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
66 documents on file for this application
- REDACTED
- LOCATION PLAN
- TRAFFIC SIGNS AND ROAD MARKINGS (SHEET 4
- TRAFFIC SIGNS AND ROAD MARKINGS (SHEET 3
- CUT & FILL ANALYSIS (SHEET 4 OF 4)
- SPINE ROAD TRAFFIC SIGNS AND ROAD MARKINGS (SHEET 2
- CUT & FILL ANALYSIS (SHEET 3 OF 4)
- TRAFFIC SIGNS AND ROAD MARKINGS (SHEET 1
- CUT & FILL ANALYSIS (SHEET 2 OF 4)
- DRAINAGE LAYOUT (SHEET 4 OF 4)
- DRAINAGE LAYOUT (SHEET 3 OF 4)
- DRAINAGE LAYOUT (SHEET 2 OF 4)
- DRAINAGE LAYOUT (SHEET 1 OF 4)
- LONGITUDINAL SECTIONS (SHEET 4 OF 5)
- LONGITUDINAL SECTIONS (SHEET 5 OF 5)
- SPINE ROAD LONGITUDINAL SECTIONS (SHEET 3 OF 5)
- LONGITUDINAL SECTIONS (SHEET 1 OF 5)
- SPINE ROAD LONGITUDINAL SECTIONS (SHEET 2 OF 5)
- CROSS SECTIONS (SHEET 4 OF 4)
- CONTOURS PLAN (SHEET 4 OF 4)
- CROSS SECTIONS (SHEET 3 OF 4)
- CROSS SECTIONS (SHEET 2 OF 4)
- CROSS SECTIONS (SHEET 1 OF 4)
- CONTOURS PLAN (SHEET 3 OF 4)
- CONTOURS PLAN (SHEET 2 OF 4)
- CONTOURS PLAN (SHEET 1 OF 4)
- SWEPT PATH ANALYSIS 12M BUS
- SWEPT PATH ANALYSIS 3.5T VAN
- SWEPT PATH ANALYSIS 16.5M HGV (SHEET 2 OF 3)
- SWEPT PATH ANALYSIS 16.5M HGV (SHEET 3 OF 3)
- SWEPT PATH ANALYSIS 16.5M HGV (SHEET 1 OF 3)
- GEOMETRIC LAYOUT & VISIBILITY (SHEET 4 O
- GEOMETRIC LAYOUT & VISIBILITY (SHEET 3 O
- GEOMETRIC LAYOUT & VISIBILITY
- GEOMETRIC LAYOUT & VISIBILITY
- GA (SHEET 4 OF 4)
- GA (SHEET 2 OF 4)
- GA (SHEET 3 OF 4)
- GA (ONE-SHEET)
- GA (SHEET 1 OF 4)
- NEW ACCESS ROAD BRIDGE OPTIONS REPORT (333103183-STN-XX-TN-CB-0001)
- OUTLINE OF STRUCTURAL PROPOSALS
- NEW ACCESS ROAD BRIDGE PRESTRESSED BEAM OPTION
- EXISTING CROSSING UPGRADE OPTIONS STUDY
- EAST PIPE CULVERT GA
- LANDSCAPE HARD AND SOFT GA SHEET 4 OF 7
- LANDSCAPE HARD AND SOFT GA SHEET 3 OF 7
- LANDSCAPE HARD AND SOFT GA SHEET 1 OF 7
- LANDSCAPE HARD AND SOFT GA SHEET 2 OF 7
- PLANTING SCHEDULE
- LANDSCAPE HARD AND SOFT GA OVERALL
- LANDSCAPE HARD AND SOFT GA SHEET 5 OF 7
- LANDSCAPE HARD AND SOFT GA SHEET 6 OF 7
- LANDSCAPE HARD AND SOFT GA SHEET 7 OF 7
- TYPICAL DETAILS SHEET 1
- TYPICAL DETAILS SHEET 2
- TYPICAL DETAILS SHEET 3
- TYPICAL DETAILS SHEET 4
- ECOLOGICAL APPRAISAL
- SURFACE WATER DRAINAGE STRATEGY SHEET 1
- SURFACE WATER DRAINAGE STRATEGY SHEET 2
- ARBORICULTURAL METHOD STATEMENT
- SPINE ROAD RMA COVER LETTER
- SPINE ROAD CUT & FILL ANALYSIS (SHEET 1 OF 4)
- PLANNING STATEMENT
- DESIGN AND ACCESS STATEMENT
Watch members (£5 a month) open the document list from here.
Open the documentsWhat happens while it is decided
This application is with Medway for determination, against a statutory target of eight weeks. Over the last year Medway's median decision took 55 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Medway's portal will say. Our guide explains the common types.
Nearby applications
Within 0.3 miles
-
Kingsnorth Power Station Power Station Access Road Hoo St Werburgh Rochester Medway ME3 9NQ
72% historically approved · decision due ~26 Nov
Details pursuant to condition 18 (External lighting) on planning permission MC/21/0979 - Outline planning application with all matters reserved except access (to be taken from Eschol Road) for the construction of flexible EG (iii)/B2/B8 use class buildings, sui generis uses for energy uses and a lorry park, together with servicing, parking, landscaping, drainage, remediation, demolition and earthworks
Awaiting decision Demolition 7 docs -
Kingsnorth Power Station Power Station Access Road Hoo St Werburgh Rochester Medway ME3 9NQ
72% historically approved · decision due ~3 Dec
Details pursuant to condition 39 (Air Quality Emissions Mitigation Statement) and parts 46 (a and b) (Supporting Statement 11-01-26-02 Heat Marketing Hierarchy Plan) Air Quality Emissions Mitigation Statement Covering Letter
Awaiting decision -
Kingsnorth Power Station Power Station Access Road Hoo St Werburgh Rochester Medway ME3 9NQ
72% historically approved · decision due ~5 Nov
Details pursuant to condition 24 (Archaeological work) on planning permission MC/21/0979 for Outline planning application with all matters reserved except access (to be taken from Eschol Road) for the construction of flexible EG (iii)/B2/B8 use class buildings, sui generis uses for energy uses and a lorry park, together with servicing, parking, landscaping, drainage, remediation, demolition and earthworks
Awaiting decision Demolition 3 docs -
Kingsnorth Power Station Power Station Access Road Hoo St Werburgh Rochester Medway ME3 9NQ
Details pursuant to conditions 36 (Waste Management Plan) and 45 (Waste Hierarchy Study) on planning permission MC/21/0979 - Outline planning application with all matters reserved except access (to be taken from Eschol Road) for the construction of flexible EG (iii)/B2/B8 use class buildings, sui generis uses for energy uses and a lorry park, together with servicing, parking, landscaping, drainage, remediation, demolition and earthworks
Decided Demolition 5 docs -
Kingsnorth Power Station Power Station Access Road Hoo St Werburgh Rochester Medway ME3 9NQ
Non-Material Amendment to Outline planning permission ref. MC/21/0979 to increase the amount of B8 (data centre) floorspace within the approved development parameters whilst retaining the overall maximum built floorspace amount and; changes to the Parameter plan in relation to the green corridor.
Granted Amendments 8 docs -
Kingsnorth Power Station Power Station Access Road Hoo St Werburgh Rochester Medway ME3 9NQ
72% historically approved · decision due ~28 Aug
Reserved matters application to consider matters of (appearance, layout, landscaping and scale) together with details to seek discharge of conditions 11 (Materials), 12 (Brick plinth), 13 (Hard and Soft landscaping), 14 (Tree survey), 15 (Landscape management plan), 16 (Boundary treatment), 17 (Landscape and Ecological management plan), 27 (Cycle storage), 29 (Refuse storage), 30 (Layout), 31 (Vehicle parking management plan), 38 (Ventilation and extraction) and 40 (Climate change and Energy efficiency statement) pursuant to outline permission MC/21/0979 - Construction of flexible EG (iii)/B2/B8 use class buildings, sui generis uses for energy uses and a lorry park, together with servicing, parking, landscaping, drainage, remediation, demolition and earthworks
Status unknown Reserved matters Demolition Trees 51 docs