Planning application
Gate Burton Energy Park West Lindsey/Bassetlaw Https://national-infrastructure-consenting. Planninginspectorate.gov.uk/projects/EN010131
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
APPLICATION TO PINS FOR A DEVELOPMENT CONSENT ORDER FOR DEVELOPMENT COMPRISING SOLAR PHOTOVOLTAIC (PV) GENERATING PANELS AND ON-SITE ENERGY STORAGE FACILITIES AND GRID CONNECTION INFRASTRUCTURE WITH GENERATION STORAGE AND EXPORT OF UP TO 500 (MW) ELECTRICAL GENERATION CAPACITY
As published by the council, reference 2024/0276/NSIP
Application record
- Reference
- 2024/0276/NSIP
- Type
- National Significant Infrastructure Proj
- Status
- Decided
- Decision
- Approved by Secretary of State
- Received
- 22 Feb 2023
- Validated
- 22 Feb 2023
- Decided
- 1 Jul 2024
Timeline
Dates from the published record
-
22 Feb 2023
Received by Mansfield
-
1 Jul 2024
Decision issued: Approved by Secretary of State
-
17 Aug 2026
Added to PlanIndex
What this grant of permission means
Mansfield granted permission on 1 July 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Mansfield's portal will say. Our guide explains the common types.