5 Angel Square Corporation Street Manchester M4 4DU
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Discharge of condition 3 (archaeology) attached to planning permission referenced 123438/FO/2019
As published by the council, reference CDN/20/0481
Application record
- Reference
- CDN/20/0481
- Type
- Approval of condition application
- Status
- Decided
- Decision
- Granted As published: Approved
- Received
- 24 Jul 2020
- Validated
- 24 Jul 2020
- Decided
- 11 Aug 2020
- Ward
- Piccadilly Ward
- Decision by
- Delegated Decision
- Postcode
- M4 4DU
Site history
Applications at this address on the Manchester register
This site has had 5 applications since 2019: 4 approved, 1 refused.
-
CDN/20/0450 Granted
5 Angel Square Corporation Street Manchester M4 4DU
Discharge of planning conditions 5 a (Materials) and 6 (Construction Management Plan) associated with planning permission 123438/FO/2019
-
CDN/20/0244 Granted
5 Angel Square Corporation Street Manchester M4 4DU
Discharge of planning condition 4 (a) (Surface Wate Drainage) associated with planning permission 123438/FO/2019
-
CDN/19/0860 Refused
5 Angel Square Corporation Street Manchester M4 4DU
Discharge of planning condition 3 (1) (written scheme of archaeological investigation) and condition 5 (a) associated with planning permission 123438/FO/2019
-
123438/FO/2019 Granted
5 Angel Square Corporation Street Manchester M4 4DU
Erection of a single storey primary substation on Corporation Street and Munster Street comprising a switch house and a transformer compound, together with related landscaping, access and highways' works, network connections and associated works
Timeline
Dates from the published record
-
24 Jul 2020
Received by Manchester
-
11 Aug 2020
Decision issued: Approved
-
21 Jul 2026
Added to PlanIndex
Who's behind it
Company information only, from the register and Companies House
Deloitte LLP Agent
764 applications on PlanIndex · across 23 councils · 99% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
5 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Manchester granted permission on 11 August 2020, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
152 Corporation Street Manchester M4 4DU
Discharge of condition 5 (Materials) and 9 (Plant) associated with planning permission 123438/FO/2019
Granted Conditions 9 docs -
5 Angel Square Corporation Street Manchester M4 4DU
Discharge of planning conditions 5 a (Materials) and 6 (Construction Management Plan) associated with planning permission 123438/FO/2019
Granted Conditions 3 docs -
5 Angel Square Noma Corporation Street Manchester M4 4DU
Non-Material Amendment to planning permission 123438/FO/2019 to facilitate amendments to the elevations of the Primary Substation and amendments to the surrounding landscaping to facilitate access arrangements
Granted Amendments 16 docs -
5 Angel Square Corporation Street Manchester M4 4DU
Discharge of planning condition 4 (a) (Surface Wate Drainage) associated with planning permission 123438/FO/2019
Granted Conditions 23 docs -
152 Corporation Street Manchester M4 4DU
Discharge of conditions 6 (Construction Management Plan), 7a (Local Labour) and 10a (Materials Programme) associated with planning permission 123437/FO/2019
Granted Conditions 5 docs -
5 Angel Square Manchester M4 4DU
Non material amendment to planning permission 123438/FO/2019 to amend implementation period of planning conditions 7 (drainage management), 10 (off site highways) and 11 (landscaping) and to amend condition 9 b (Plant) to allow alterations to verification period.
Granted Amendments 2 docs
Other condition discharge and variation applications
In Manchester
-
OTH-2026-000974 Granted
Marriott Residence Inn 40 Laystall St Manchester M1 2JP
Discharge of Condition 4 (Opening Hours) attached to Planning Permission 125369/JO/2019.
-
OTH-2026-000913 Split decision
5 Cotton Hill Manchester M20 4XR
Discharge of Conditions 3 (materials), 4 (waste storage), 6 (electric vehicle charging points), 7 (partial discharge - Secured by Design accreditation), 10 (detailed landscaping scheme) and 12 (construction method statement) attached to Planning Permission 133107/FO/2022.
-
OTH-2026-001266 Split decision
685 Moston Lane Manchester M40 5QD
Discharge of Conditions 8 (Cycle Storage), 9 (EV), 10 (Acoustic Insulation) & 11 (Security) attached to Planning Permission 142547/JO/2025.
-
OTH-2026-001305 Granted
440 Hollinwood Avenue Manchester M40 0AE
Discharge of Condition 15 (Invasive Species) attached to Planning Permission 142670/FO/2025.
-
OTH-2026-001642 Granted
66 Jersey Street Manchester M4 6JW
Discharge of Condition 10b (Ground Conditions) attached to Planning Permission 139289/JO/2024.