Planning application
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
Withdrawn before a decision, so it carries no planning weight. A revised scheme can be submitted at any time.
Proposal
Submission of 'Commissioning Notice' in accordance with Part 3 of Thames Tideway Tunnel DCO Requirement DEPCS14 for the Deptford Church Street Site.
As published by the council, reference DC/25/142118
Application record
- Reference
- DC/25/142118
- Type
- Thames Tunnel Application
- Status
- Withdrawn
- Decision
- Closed internally
- Received
- 13 Nov 2025
- Decided
- 14 Nov 2025
Site history
Applications at this address on the Lewisham register
This site has had 9 applications since 2019: 8 approved, 0 refused.
-
DC/25/141955 Granted
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal application to discharge Schedule 3 Requirement DEPCS5 (Parts 3 and 4) (Contaminated Land) at the Deptford Church Street site.
-
DC/19/114751 Granted
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal Application - Partial discharge of Schedule 3 Requirement DEPCS 6 ? Worksite Specific Traffic Management Plan (Phase 3 works) - Deptford Church Street worksite.
-
DC/19/114786 Granted
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal application to partially discharge Schedule 3 Requirement PW6 CoCP Part A Section 5 ? Worksite Specific Construction Logistics Plan (WSCLP)(Phase 3 works) at Deptford Church Street worksite.
-
DC/19/114594 Granted
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 Submission to partially discharge Schedule 3 Requirement DEPCS 8 ? Highway works (Deptford Church Street) for the Deptford Church Street worksite.
-
DC/19/114473 Granted
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal application for the partial discharge Schedule 3 Requirement DEPCS 1, CoCP Part B for the Deptford Church Street (DEPCS) worksite.
-
DC/19/114468 Granted
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 notification of commencement of Approved Traffic Order under Article 16, Schedule 9 - Access to Works
-
DC/19/112359 Granted
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal Application to partially discharge Schedule 3 Requirement PW6 CoCP Part A Section 7 ? Air Quality Management Plan for the Deptford Church Street worksite.
-
DC/19/112306 Granted
DEPTFORD CHURCH STREET SITE, THAMES TUNNEL, LONDON
Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 formal Application to partially discharge Schedule 3 Requirement PW6 CoCP Part A Section 6 ? Noise and Vibration Management Plan for the Deptford Church Street worksite.
Timeline
Dates from the published record
-
13 Nov 2025
Received by Lewisham
-
14 Nov 2025
Decision issued: Closed internally
-
10 Aug 2026
Added to PlanIndex
What withdrawal means
The applicant withdrew this application before Lewisham decided it, and is free to submit a revised scheme at any time. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Lewisham's portal will say. Our guide explains the common types.