Planning application
26/01344/EIASCR
Rosendale Road, Between Norwood Road And Tritton Road London SE24
Proposal
Screening Opinion in respect of an Environmental Impact Assessment (EIA) pursuant to Regulation 6 of the Town and Country Planning (Environmental Impact Assessment) Regulations, 2017 for the creation of a cycle lane, along with changes to junction geometry, footways, signage, vehicle and cycle parking and other associated works to the highway along Rosendale Road, as Phase 3 of the Brockwell Park to Gipsy Hill Healthy Route between the A205 South Circular and Park Hall Road (connecting to Phase 1 and Phase 2 two-way cycle tracks installed along the eastern side of Rosendale Road south of Norwood Road).
As published by the council, reference 26/01344/EIASCR
Timeline
Dates from the published record
-
27 Apr 2026
Received by Lambeth
-
29 Apr 2026
Decision issued: Grant Permission
-
25 Jul 2026
Added to PlanIndex
What a grant of permission means
The process from here
Permission has been granted, usually subject to conditions listed on the decision notice, some of which must be discharged before work starts. The decision notice on the council portal sets out exactly what was approved.
Work must normally begin within three years of the decision or the permission lapses. Neighbours cannot appeal a grant; challenging one means judicial review of how the decision was made, within tight time limits.
About outline applications
How this application type works
An outline application tests the principle of developing a site before the detail is worked up. Some or all of the particulars, such as appearance, layout, scale, access and landscaping, are held back as reserved matters for later approval. Permission at outline stage does not by itself allow building to start; the reserved matters must be approved first.
Nearby applications
Within 500 metres
-
26/01345/EIASCR Granted
Rosendale Road, Between Norwood Road, Tritton Road And Roads Leading To Gipsy Hill London SE24
Screening Opinion in respect of an Environmental Impact Assessment (EIA) pursuant to Regulation 6 of the Town and Country Planning (Environmental Impact Assessment) Regulations, 2017 for the creation of a cycle lane, along with changes to junction geometry, footways, signage, vehicle and cycle parking and other associated works to the highway along Rosendale Road, as Phase 3 of the Brockwell Park to Gipsy Hill Healthy Route between the A205 South Circular and Park Hall Road (connecting to the Phase 1 and Phase 2 two-way cycle tracks installed along the eastern side of Rosendale Road and connecting south to future Phase 4 cycle way leading to Gypsy Hill Station).
-
26/00676/LDCP Granted
280 Rosendale Road London Lambeth SE24 9DL
Application for a certificate of lawfulness (proposed) for the change of use from a dry cleaners (Class E) to a restaurant (Class E(b)).
-
26/01295/VOC Awaiting decision
279 Rosendale Road London SE24 9EJ
Variation of conditions 2 (Approved Plans), 3 (Construction Environmental Management Plan), 4 (contamination), 5 (sustainable design and construction), 6 (sustainability statement), 7 (overheating assessment), 8 (water saving), 9 (surface water drainage), 11(materials), 12 (external construction detailing), 13 (acoustic impact), 14 (glazing and mechanical ventilation), 15 (noise levels), 16 (sound insulation), 17 (sound insulation), 18 (landscaping), 19 (green roofs/walls), 20 (above ground planting), 21 (above ground planting), 22 (Fire Strategy, 25 (Urban Greening Factor) and 31 (Secured by Design) of planning permission 22/03635/FUL (Retention and restoration of front facade; demolition of buildings behind; the erection of a part two, four and five-storey building to provide 23 residential dwellings, commercial space on the ground floor [Use Class E(e) or E(f)], communal amenity space, cycle parking, and hard and soft landscaping; and other associated development.), granted on 19.12.2023. Variations sought: Amendments to ensure the approved development can be delivered in a practical, compliant and viable manner following detailed technical review and progression towards implementation. The changes principally relate to buildability, fire safety, accessibility, updated servicing arrangements, refinement of layouts, revised roof plant and lift overrun arrangements, updated landscaping, drainage and sustainability measures, together with minor elevational and material amendments. Variations to conditions are sought to reflect the amended drawings and updated technical information submitted with this application, while retaining the overall scale, design approach and policy compliance of the approved scheme.
-
11/02279/DET Granted
Peabody Estate Rosendale Road London SE24 9EQ
Approval of details pursuant to condition 3 (Arboricultural Method Statement) of planning permission ref: 09/02785/FUL (Estate wide environmental improvements involving resurfacing of roads and pavements, installation/upgrading of street/external lighting, provision of bin stores, revision of parking layout, provision of cycle parking, planting of trees and shrubs, boundary improvements/alterations, alterations to the main entrance on Rosendale Road including the erection of brick piers and metal arches, and hard and soft landscaping of communal areas) granted on: 12.11.2009.
-
11/02280/DET Granted
Peabody Estate Rosendale Road London SE24 9EQ
Approval of details pursuant to condition 7 (Samples and a schedule of materials) of planning permission ref: 09/02785/FUL (Estate wide environmental improvements involving resurfacing of roads and pavements, installation/upgrading of street/external lighting, provision of bin stores, revision of parking layout, provision of cycle parking, planting of trees and shrubs, boundary improvements/alterations, alterations to the main entrance on Rosendale Road including the erection of brick piers and metal arches, and hard and soft landscaping of communal areas) granted on: 12.11.2009.
-
11/01142/DET Granted
Peabody Estate Rosendale Road London SE24 9EQ
Approval of details pursuant to condition 9 (Method of Construction Statement) of planning permission ref: 09/02785/FUL (Estate wide environmental improvements involving resurfacing of roads and pavements, installation/upgrading of street/external lighting, provision of bin stores, revision of parking layout, provision of cycle parking, planting of trees and shrubs, boundary improvements/alterations, alterations to the main entrance on Rosendale Road including the erection of brick piers and metal arches, and hard and soft landscaping of communal areas) granted on: 12.11.2009.
Other outline applications
In Lambeth
-
26/01400/EIASCR Granted
374 - 380 Streatham High Road London SW16 6HP
Request for a Screening Opinion in respect of an Environmental Impact Assessment (EIA) pursuant to Regulation 6 of the Town and Country Planning (Environmental Impact Assessment) Regulations (2017) for the redevelopment of 374-380 Streatham High Road involving demolition of the existing building and construction of a part 23 / part 16 storey building, providing 259 co-living units, associated amenity space, and two ground floor retail units.
-
26/01033/G18 Granted
Waterloo Station London SE1 8SW
Application for prior approval under Part 18 of the GPDO for the removal and relocation of the existing access door at the rear of Unit G14 on Cab Road and replacement with solid masonry infill and a repositioned door.
-
26/01345/EIASCR Granted
Rosendale Road, Between Norwood Road, Tritton Road And Roads Leading To Gipsy Hill London SE24
Screening Opinion in respect of an Environmental Impact Assessment (EIA) pursuant to Regulation 6 of the Town and Country Planning (Environmental Impact Assessment) Regulations, 2017 for the creation of a cycle lane, along with changes to junction geometry, footways, signage, vehicle and cycle parking and other associated works to the highway along Rosendale Road, as Phase 3 of the Brockwell Park to Gipsy Hill Healthy Route between the A205 South Circular and Park Hall Road (connecting to the Phase 1 and Phase 2 two-way cycle tracks installed along the eastern side of Rosendale Road and connecting south to future Phase 4 cycle way leading to Gypsy Hill Station).
-
24/02189/PIP Refused
69A Kings Avenue London SW4 8DX
Permission in Principle for the redevelopment of the property to provide one additional house to the side
-
21/02668/EIAFUL Decided
The London Television Centre 60 - 72 Upper Ground London SE1 9LT
Demolition of all existing buildings and structures for a mixed-use redevelopment comprising offices, cultural spaces and retail uses with associated public realm and landscaping, servicing areas, parking and mechanical plant. This application is accompanied by an Environmental Statement (ES) which is available for inspection online with the planning application documents.