Land On The South East Side of Scania Way Hardwick Industrial Estate King's Lynn Norfolk

Decided King’s Lynn and West Norfolk 25/01958/FM

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

HYBRID APPLCATION: FULL - Erection of a retail store with associated parking, highway infrastructure, access, landscaping, substation, plant equipment and other ways; and an OUTLINE - all matters reserved for the erection of two drive thru units with associated parking, landscaping and other works

As published by the council, reference 25/01958/FM

Application record

Reference
25/01958/FM
Status
Application Refused
Received
26 Nov 2025
Validated
8 Dec 2025
Decided
5 Oct 2026
Ward
South And West Lynn
Parish
North Runcton
Decision by
Delegated

Timeline

Dates from the published record

  1. 26 Nov 2025

    Received by King’s Lynn and West Norfolk

  2. 8 Dec 2025

    Validated

    Checked as complete and ready for consideration.

  3. 24 Jul 2026

    Added to PlanIndex

  4. 5 Oct 2026

    Decision issued

  5. 5 Oct 2026

    Status changed to Application Refused

    Previously Awaiting decision.

Who's behind it

Company information only, from the register and Companies House

Walsingham Planning Ltd Agent, a planning consultancy registered in Bourne End

Active · incorporated 2015 · Bourne End

515 applications on PlanIndex · across 138 councils · 91% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Lidl GB Ltd Applicant

39 applications on PlanIndex · across 17 councils · 100% granted

Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.

See their track record

Documents

Plans, drawings, consultee responses and the officer's report

107 documents on file for this application

  • DECISION Decision · 05 Oct 2026
  • OFFICER REPORT Report · 05 Oct 2026
  • HISTORIC ENVIRONMENT SERVICES COMMENTS Consultee Comment · 25 Sep 2026
  • ENVIRONMENTAL QUALITY - ASHLEY WHEELER Consultee Comment · 22 Sep 2026
  • AGENT CORRESPONDENCE Correspondence · 18 Sep 2026
  • REMEDIATION STRATEGY AND CAR-SOIL RISK ASSESSMENT Report · 18 Sep 2026
  • ARCHAEOLOGICAL FIELD EVALUATION REPORT Report · 17 Sep 2026
  • AGENT CORRESPONDENCE Report · 17 Sep 2026
  • HISTORIC ENVIRONMENT SERVICES CORRESPONDENCE Correspondence · 17 Sep 2026
  • EOT AGREED Correspondence · 11 Aug 2026
  • ARBORICULTURAL OFFICER - BRIAN OGDEN Consultee Comment · 17 Jul 2026
  • EOT AGREED Correspondence · 09 Jul 2026
  • PLANNING OFFICER EMAIL Correspondence · 08 Jul 2026
  • AGENT AGREEMENT TO EOT Correspondence · 11 Jun 2026
  • AGENT CORRESPONDENCE WITH LLFA Correspondence · 23 Apr 2026
  • LLFA CORRESPONDENCE Correspondence · 10 Apr 2026
  • WLMA CORRESPONDENCE Correspondence · 08 Apr 2026
  • LHA CONSULTEE RESPONSE Consultee Comment · 01 Apr 2026
  • AGENT CORRESPONDENCE Correspondence · 27 Mar 2026
  • MHC-131-24 CLASSIFIED LINK COUNT Report · 27 Mar 2026
  • POSSIBLE 1 IN 3 EMBANKMENT LOCATION TO ACCOMMODATE 5M FOOTWAY/CYCLEWAY Drawing · 27 Mar 2026
  • ECOLOGIST EMAIL Correspondence · 12 Mar 2026
  • BIODIVERSITY NET GAIN DESIGN STAGE REPORT Report · 10 Mar 2026
  • BNG METRIC Report · 10 Mar 2026
  • PRELIMINARY ECOLOGICAL APPRAISAL Report · 10 Mar 2026
  • AGENT CORRESPONDENCE Correspondence · 10 Mar 2026
  • EOT AGREED Correspondence · 09 Mar 2026
  • NCC CORRESPONDENCE Correspondence · 26 Feb 2026
  • SENIOR ENVIRONMENTAL QUALITY OFFICER RESPONSE Consultee Comment · 24 Feb 2026
  • AGENT CORRESPONDENCE Correspondence · 23 Feb 2026
  • ENVIRONMENT AGENCY COMMENTS Consultee Comment · 18 Feb 2026
  • ECOLOGIST EMAIL Correspondence · 18 Feb 2026
  • PRINCIPAL PLANNER EMAIL Correspondence · 17 Feb 2026
  • AGENT EMAIL Correspondence · 17 Feb 2026
  • PROPOSED SITE PLAN Drawing · 17 Feb 2026
  • PROPOSED LANDSCAPING BOUNDRY TREATMENT Drawing · 17 Feb 2026
  • PROPOSED DEVELOPMENT PLAN Drawing · 17 Feb 2026
  • NCC HIGHWAYS Correspondence · 17 Feb 2026
  • AGENT CORRESPONDENCE Correspondence · 29 Jan 2026
  • PHASE 2 GROUND INVESTIGATION Report · 29 Jan 2026
  • NCC HIGHWAYS CORRESPONDENCE Consultee Comment · 28 Jan 2026
  • HISTORIC ENVIRONMENT OFFICER RESPONSE Correspondence · 21 Jan 2026
  • REVISED PRELIMINARY ECOLOGICAL APPRAISAL Report · 20 Jan 2026
  • BNG METRIC Correspondence · 20 Jan 2026
  • BIODIVERSITY NET GAIN DESIGN STAGE REPORT Correspondence · 20 Jan 2026
  • AGENT CORRESPONDENCE Correspondence · 18 Jan 2026
  • PARISH COUNCIL COMMENTS Consultee Comment · 14 Jan 2026
  • ENVIRONMENTAL QUALITY - DAVID ALFORD Consultee Comment · 09 Jan 2026
  • LLFA COMMENTS Consultee Comment · 09 Jan 2026
  • AGENT CORRESPONDENCE Correspondence · 09 Jan 2026
  • ANGLIAN WATER COMMENTS Consultee Comment · 08 Jan 2026
  • ECOLOGY OFFICER - CLAIRE WIGGS Consultee Comment · 05 Jan 2026
  • ENVIRONMENTAL QUALITY - ASHLEY WHEELER Consultee Comment · 02 Jan 2026
  • EMERGENCY PLANNING - KEVIN KENT Consultee Comment · 02 Jan 2026
  • PROW COMMENTS Consultee Comment · 02 Jan 2026
  • HSE REPORT Report · 24 Dec 2025
  • WLMA COMMENTS Consultee Comment · 22 Dec 2025
  • HISTORIC ENVIRONMENT SERVICES COMMENTS Consultee Comment · 19 Dec 2025
  • HISTORIC ENV EMAIL Correspondence · 19 Dec 2025
  • CSNN SUZI PIMLOTT Consultee Comment · 18 Dec 2025
  • CADENT GAS SPECIFICATION FOR SAFE WORKING Report · 15 Dec 2025
  • OVERVIEW MAP OF WORKSITE Drawing · 15 Dec 2025
  • CADENT GAS CORRESPONDENCE Correspondence · 15 Dec 2025
  • NATURAL ENGLAND COMMENTS Consultee Comment · 15 Dec 2025
  • NCC CORRESPONDENCE Correspondence · 15 Dec 2025
  • OBJECTION CADENT GAS EMAIL Public Comment · 12 Dec 2025
  • OVERVIEW MAP OF WORKSITE Drawing · 12 Dec 2025
  • FIRE AND RESCUE SERVICES COMMENTS Consultee Comment · 11 Dec 2025
  • LLFA CORRESPONDENCE Consultee Comment · 11 Dec 2025
  • EMAIL ACK FORM 1 CIL Correspondence · 10 Dec 2025
  • CIL OFFICER - ROBYN WALKEY Consultee Comment · 10 Dec 2025
  • NORFOLK CONSTABULARY COMMENTS Consultee Comment · 10 Dec 2025
  • NORFOLK CONSTABULARY COMMENTS Consultee Comment · 10 Dec 2025
  • UK POWER NETWORKS CORRESPONDENCE Consultee Comment · 10 Dec 2025
  • AGENT CORRESPONDENCE Correspondence · 05 Dec 2025
  • PROPOSED BUILDING PLAN Drawing · 05 Dec 2025
  • AGENT EMAIL Correspondence · 04 Dec 2025
  • PROPOSED SECTIONS Drawing · 04 Dec 2025
  • PROPOSED DEVELOPMENT PLAN Drawing · 04 Dec 2025
  • PROPOSED HARD LANDSCAPING AND BOUNDRY TREATMENT PLAN Drawing · 04 Dec 2025
  • SUPERSEDED PROPOSED BUILDING PLAN Drawing · 04 Dec 2025
  • PROPOSED SITE PLAN Drawing · 04 Dec 2025
  • EXTERNAL LEVELS PLAN Drawing · 04 Dec 2025
  • INVALID LETTER (NOT INCORRECT FEE) Invalid Letter · 27 Nov 2025
  • APPLICATION FORM Application Form · 25 Nov 2025
  • FORM 1 CIL ADDITIONAL INFORMATION CIL Form · 25 Nov 2025
  • PLANNING AND RETAIL STATEMENT Correspondence · 25 Nov 2025
  • BIODIVERSITY NET GAIN DESIGN STATE REPORT Report · 25 Nov 2025
  • CONDITION ASSESSMENT Report · 25 Nov 2025
  • STATUTORY METRIC Report · 25 Nov 2025
  • PRELIMINARY ECOLOGICAL APPRAISAL Report · 25 Nov 2025
  • ENERGY USAGE AND SUSTAINABILITY STATEMENT Report · 25 Nov 2025
  • FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY Report · 25 Nov 2025
  • FLOOD RISK SEQUENTIAL ASSESSMENT Report · 25 Nov 2025
  • DESIGN AND ACCESS STATEMENT Correspondence · 25 Nov 2025
  • TRANSPORT ASSESSMENT Report · 25 Nov 2025
  • NOISE IMPACT ASSESSMENT Report · 25 Nov 2025
  • TRAVEL PLAN Report · 25 Nov 2025
  • APPENDIX A Report · 25 Nov 2025
  • APPENDIX B Report · 25 Nov 2025
  • APPENDIX C AND D Report · 25 Nov 2025
  • PHASE 1 SITE INVESTIGATION AND PRELIMINARY RISK ASSESSMENT Report · 25 Nov 2025
  • DETAILED SOFT LANDSCAPE PROPOSAL Drawing · 25 Nov 2025
  • PROPOSED ELEVATIONS Drawing · 25 Nov 2025
  • PROPOSED ROOF PLAN Drawing · 25 Nov 2025
  • SITE LOCATION PLAN Drawing · 25 Nov 2025
  • EXISTING SITE PLAN Drawing · 25 Nov 2025

Watch members (£5 a month) open the document list from here.

Open the documents

After the decision

King’s Lynn and West Norfolk has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on King’s Lynn and West Norfolk's portal will say. Our guide explains the common types.