Planning application
Land South Of Appley Road North Of Bullen Road And East Of (West Acre Park) Hope Road Ryde Isle Of Wight
Works: Trees
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Condition compliance application on 20/01061/FUL relating to conditions 3 (Phasing plan), 4 (Construction access(es), 5 (Junction design), 12 (Construction Environment Management Plan), 13 (Dust), 14 (Noise and Vibration), 15 (Biodiversity Mitigation and Enhancement), 17 (Hard and Soft Landscaping), 18 (Foul and Surface Water), 20 (Arboreal Method Statement), 21 (tree protection fencing), and 32 (Great Crested Newts) to be discharged
As published by the council, reference 26/00164/DIS
Application record
- Reference
- 26/00164/DIS
- Type
- Discharge of Condition
- Status
- Decided
- Decision
- Granted As published: Condition Discharge
- Received
- 5 Feb 2026
- Validated
- 26 Feb 2026
- Decided
- 8 May 2026
- Ward
- Ryde Appley And Elmfield
- Parish
- Ryde
- Decision by
- Planning Officer Delegated Decision
Site history
Applications at this address on the Isle of Wight register
This site has had 2 applications since 2026: 1 approved, 0 refused.
-
26/00490/RVC Awaiting decision
Land South Of Appley Road North Of Bullen Road And East Of (West Acre Park) Hope Road Ryde Isle Of Wight
Variation of conditions 2,6,7 and 8 on 20/01061/FUL to allow for a revised scheme (Departure)(readvertised application)
Timeline
Dates from the published record
-
5 Feb 2026
Received by Isle of Wight
-
26 Feb 2026
Validated
Checked as complete and ready for consideration.
-
8 May 2026
Decision issued: Condition Discharge
-
10 Aug 2026
Added to PlanIndex
Related applications
Cases linked to this one on the register
- Application: 20/01061/FUL (Decided)
Who's behind it
Company information only, from the register and Companies House
BCM LLP Agent, registered in Nottingham
Active · incorporated 1992 · Nottingham
126 applications on PlanIndex · across 13 councils · 90% granted
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordWestridge Village (IOW) Ltd Applicant
2 applications on PlanIndex
Trade members see everything this firm has filed, how it was decided, and get an email the day it files again.
See their track recordDocuments
Plans, drawings, consultee responses and the officer's report
101 documents on file for this application
- ECOLOGY OFFICER
- CEMP - APPENDIX F - REVISED
- ECOLOGY OFFICER - 17TH APRIL COMMENT
- ECOLOGY OFFICER - 28TH APRIL COMMENT
- DISCHARGE OF CONDITIONS DECISION NOTICE
- CEMP - APPENDIX I
- ECOLOGY OFFICER
- REVISED CEMP - REVISION E
- REVISED - CEMP - APPENDIX H
- REVISED - SANG INFORMATION BOARD
- SANG INFORMATION BOARDS - SUPERSEDED
- REVISED - CEMP REVISION D - SUPERSEDED
- REVISED - CEMP APPENDIX G
- REVISED - CEMP APPENDIX H - SUPERSEDED
- REVISED - BEMP
- CURLEW MITIGATION BOARD
- ENVIRONMENTAL HEALTH
- COVER LETTER - REVISED
- CEMP - REVISED - SUPERSEDED
- BEMP PLAN - REVISED
- CURLEW INFORMATION BOARD
- SANG
- SANG BOARD - SUPERSEDED
- CEMP APPENDICES
- ENVIRONMENT HEALTH COMMENTS
- NATURESPACE
- ISLAND ROADS
- REVISED DRAINAGE MANAGEMENT PLAN
- REVISED CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
- REVISED CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN APPENDICIES
- MR JERRY WILLIS
- CONDITION 20 - ARBOREAL METHOD STATEMENT
- REVISED ISLAND ROADS COMMENTS
- LLFA COMMENTS
- ENVIRONMENTAL HEALTH COMMENTS
- REVISED COVER LETTER
- REVISED CEMP
- REVISED CEMP APPENDIX A
- REVISED CEMP APPENDIX B
- MR ISLAND ROADS
- MARTIN JONES
- SOUTHERN WATER
- SUPERSEDED - CONSTRACTION ENVIRONMENT MANAGEMENT PLAN
- CEMP APPENDIX C
- CEMP APPENDIX E
- CEMP APPENDIX F
- SUPERSEDED - 1466-5974 COVER LETTER
- SP20 PHASE DELIVERY PLAN-REVISION D
- CEMP APPENDIX D - PHASING PLAN DEC.
- SUPERSEDED - CEMP APPENDIX A - CONSTRUCTION MANAGEMENT PLAN DEC
- SUPERSEDED - CEMP APPENDIX B - CONSTRUCTION TRAFFIC ROUTES DEC
- APPLICATIONFORMREDACTED
- WA2A-SMA-XXX-XX-DR-C-0600- LOCATION PLAN P02
- WA2A-SMA-XXX-XX-DR-C-0601- SCHEME LAYOUT P06
- WA2A-SMA-XXX-XX-DR-C-0602- CLEARANCE LAYOUT P06
- WA2A-SMA-XXX-XX-DR-C-0603- FINISHES LAYOUT P06
- WA2A-SMA-XXX-XX-DR-C-0604- LEVELS LAYOUT P06.
- WA2A-SMA-XXX-XX-DR-C-0605- AGREEMENT PLAN P05.
- WA2A-SMA-XXX-XX-DR-C-0606- CONSTRUCTION DETAILS-SHEET 1 P04.
- WA2A-SMA-XXX-XX-DR-C-0608- VEHICLE TRACKING P03
- WA2A-SMA-XXX-XX-DR-C-0621- SCHEME LAYOUT (BULLEN RD) P06.P
- WA2A-SMA-XXX-XX-DR-C-0622- CLEARANCE LAYOUT (BULLEN RD) P05
- WA2A-SMA-XXX-XX-DR-C-0623- FINISHES LAYOUT (BULLEN RD) P05
- WA2A-SMA-XXX-XX-DR-C-0624- DRAINAGE & LEVELS LAYOUT (BULLEN RD) P05.
- WA2A-SMA-XXX-XX-DR-C-0625- CONSTRUCTION DETAILS (BULLEN RD) P04.
- WA2A-SMA-XXX-XX-DR-C-0626- SETTINGOUT LAYOUT (BULLEN RD) P04
- WA2A-SMA-XXX-XX-DR-C-0628- S278 VEHICLE TRACKING (BULLEN ROAD) P02
- WA2A-SMA-XXX-XX-DR-C-0629- S278 RETAINING WALL SECTIONS (BULLEN RD) P02.PDF
- JSL2874_570 LANDSCAPE MANAGEMENT & MAINTENANCE PLAN - PART 3
- JSL2874_570 LANDSCAPE MANAGEMENT & MAINTENANCE PLAN - PART 4.
- JSL2874_570 LANDSCAPE MANAGEMENT MAINTENANCE PLAN - PART 1
- JSL2874_570 LANDSCAPE MANAGEMENT & MAINTENANCE PLAN - PART 2
- JSL2874_200 PHASE 2 HARD LANDSCAPE PLAN.
- JSL2874_401 TREE PIT DETAILS SHEET 1 OF 2.
- SL2874_402 TREE PIT DETAILS SHEET 2 OF 2.
- JSL2874_507 PHASE 2 DETAILED SOFT LANDSCAPE PLAN SHEET 1 OF 3
- SL2874_508 PHASE 2 DETAILED SOFT LANDSCAPE PLAN SHEET 2 OF 3
- JSL2874_509 PHASE 2 DETAILED SOFT LANDSCAPE PLAN SHEET 3 OF 3
- JSL2874_550 TREE AND SHRUB SCHEDULE.
- AIA JUNE 25. TREE REPORT
- 5622.401L - SW DRAINAGE STRATEGY PRINCIPLES.
- 5622.402F - FW DRAINAGE STRATEGY PRINCIPLES
- 6669 - WEST ACRE RYDE IOW - DRAINAGE MAINTENANCE MANAGEMENT PLAN
- WA2A-SMA-XXX-XX-DR-C-0508 DRAINAGE LAYOUT-SHEET 1 - P04.
- WA2A-SMA-XXX-XX-DR-C-0509 DRAINAGE LAYOUT-SHEET 2 - P04
- WA2A-SMA-XXX-XX-DR-C-0510 DRAINAGE LAYOUT-SHEET 3 - P04.P
- WA2A-SMA-XXX-XX-DR-C-0511 DRAINAGE LAYOUT-SHEET 4 - P02
- WA2A-SMA-XXX-XX-DR-C-0512 DRAINAGE LAYOUT-SHEET 5 - P02
- JSL2874_720B TREE REMOVAL AND PROTECTION PLAN SHEET 1 OF 12
- JSL2874_721B TREE REMOVAL AND PROTECTION PLAN SHEET 2 OF 12
- JSL2874_722B TREE REMOVAL AND PROTECTION PLAN SHEET 3 OF 12
- JSL2874_723B TREE REMOVAL AND PROTECTION PLAN SHEET 4 OF 12
- JSL2874_724B TREE REMOVAL AND PROTECTION PLAN SHEET 5 OF 12
- JSL2874_725B TREE REMOVAL AND PROTECTION PLAN SHEET 6 OF 12
- GCN PWMS (FEBRUARY 2026).
- JSL2874_726B TREE REMOVAL AND PROTECTION PLAN SHEET 7 OF 12
- JSL2874_727B TREE REMOVAL AND PROTECTION PLAN SHEET 8 OF 12
- JSL2874_728B TREE REMOVAL AND PROTECTION PLAN SHEET 9 OF 12.
- JSL2874_729B TREE REMOVAL AND PROTECTION PLAN SHEET 10 OF 12
- JSL2874_730B TREE REMOVAL AND PROTECTION PLAN SHEET 11 OF 12.
- JSL2874_731B TREE REMOVAL AND PROTECTION PLAN SHEET 12 OF 12
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Isle of Wight granted permission on 8 May 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Land South Of Appley Road North Of Bullen Road And East Of Hope Road (West Acre Park) Ryde Isle Of Wight
Condition compliance application on 20/01061/FUL for condition 31 (Bat Surveys)
Granted Conditions 8 docs -
Land South Of Appley Road North Of Bullen Road And East Of (West Acre Park) Hope Road Ryde Isle Of Wight
83% historically approved · decision due ~19 Jun
Variation of conditions 2,6,7 and 8 on 20/01061/FUL to allow for a revised scheme (Departure)(readvertised application)
Awaiting decision Amendments 138 docs -
Swaylands Swaylands Close Ryde Isle Of Wight PO33 1FA
Condition compliance application on 26/00650/HOU for condition 3 (Arboreal Method Statement)
Granted 6 docs -
Swaylands Swaylands Close Ryde Isle Of Wight PO33 1FA
Demolition of conservatory and outbuilding; proposed single storey side extension
Granted Householder Extension Demolition 18 docsSmall domestic -
Orchard House Bullen Road Nettlestone Ryde Isle Of Wight PO33 1AU
Non material amendment on 21/01458/HOU to allow alterations to end wall of carport to be constructed out of red facing brickwork
Granted Amendments 4 docs -
Orchard House Bullen Road Nettlestone Ryde Isle Of Wight PO33 1AU
Demolition of existing two storey extension; Proposed two storey rear extension; veranda/open porch; carport and covered walkway
Granted Householder Extension Demolition 28 docsSmall domestic
Other condition discharge and variation applications
In Isle of Wight
-
26/01207/DIS Awaiting decision
Neutrik UK Ltd Cothey Way Ryde Isle Of Wight PO33 1QT
Condition compliance application on 25/01012/FUL relating to Condition 3 (Contamination) to be discharged
-
26/01169/DIS Awaiting decision
Masonic Hall 13 Solent Hill Freshwater Isle Of Wight PO40 9TG
Condition compliance application on P/00167/19 for conditions 4 (Landscaping), 5 (Construction Management Plan) and 6 (Arboreal Method Statement)
-
26/01147/DIS Awaiting decision
Toymaster 9 Union Street Ryde Isle Of Wight PO33 2DU
Condition compliance application on 23/02258/FUL for conditions 3 (Construction Management Code) and 4 (Materials and Finishes) in relation to flat 4 and semi-detached houses
-
26/00681/DIS Granted
Barnfield Solar Farm, East Of Wilmingham Lane, West Of Broad Lane, Yarmouth, And Parts Of Broad Lane, B3401 Thorley Street To Station Road, And Warlands Lane, And Shalfleet Substation, Warlands Lane, Shalfleet, Isle Of Wight
Condition compliance application on 22/01793/FUL relating to condition 11 (Construction Environmental Management Plan) to be discharged
-
26/01136/DIS Awaiting decision
Neutrik UK Ltd Cothey Way Ryde Isle Of Wight PO33 1QT
Condition compliance application on 25/01012/FUL relating to Conditions 4 (Construction Management Plan (CMP)), 5 (Engineering detail of junction), 9 (Pedestrian crossing points), 11 (construction environmental management plan (CEMP: Biodiversity), 12 (Habitat Management and Monitoring Plan (HMMP), 13 (Bird/swift boxes), 14 (Soft landscaping), 16 (Lighting), 18 (Delivery management plan) and the Biodiversity Net Gain (BNG) to be discharged