Land East And West Of Little Staughton Solar Farm Kimbolton Road Hail Weston

Granted Huntingdonshire 26/00313/S73

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Variation of condition 2 (approved plans) of 22/01813/FUL

As published by the council, reference 26/00313/S73

Application record

Reference
26/00313/S73
Status
Approved
Decision
Granted As published: Approved
Received
16 Feb 2026
Validated
16 Feb 2026
Decided
27 Jul 2026

Site history

Applications at this address on the Huntingdonshire register

This site has had 5 applications since 2021: 3 approved, 0 refused.

  • 26/80081/COND Granted

    Land East And West Of Little Staughton Solar Farm Kimbolton Road Hail Weston

    Discharge of condition 13 (WSI) of 22/01813/FUL (installation of solar farm comprising the provision of photovoltaic panels, inverters, switchgear housings and transformer stations together with hardstanding, landscaping, access alterations, fencing and associated works)

    Decided 26 May 2026 Conditions
  • 26/80043/COND Granted

    Land East And West Of Little Staughton Solar Farm Kimbolton Road Hail Weston

    Discharge of Conditions 5 - Final Details, 14 - AMP, 15 - Soft Landscaping Scheme, 17 - PRoW Plans, 19 - Permissive Path, 21- Trees, 22- Arb Method Statement, 23- Drainage, 25 - CEMP, 26 - LEMP of permission 22/01813/FUL

    Decided 24 Jul 2026 Conditions
  • 25/80286/COND Awaiting decision

    Land East And West Of Little Staughton Solar Farm Kimbolton Road Hail Weston

    Discharge of conditions 11 (Traffic Management Plan), 20 (PROW Protective Measures), 24 (Soil Management) and 27 (Skylark Mitigation) of permission 22/01813/FUL

    Submitted 13 Oct 2025 Conditions
  • 21/70071/SCRE Withdrawn

    Land East And West Of Little Staughton Solar Farm Kimbolton Road Hail Weston

    50MW solar farm on the land around the existing Top Farm (and Little Staughton) solar farm

    Decided 11 Jun 2021 Outline

Timeline

Dates from the published record

  1. 16 Feb 2026

    Received by Huntingdonshire

  2. 23 Jul 2026

    Added to PlanIndex

  3. 27 Jul 2026

    Decision issued: Approved

  4. 29 Jul 2026

    Status changed to Pending decision

    Previously In progress.

What this grant of permission means

Huntingdonshire granted permission on 27 July 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Huntingdonshire's portal will say. Our guide explains the common types.