Skip to content
PlanIndex Get alerts
Menu

Planning application

Land 515M SE Of Glenshellach Inchree Onich

Granted Highland 26/00904/S37 Section 37

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Simplified Notification - New Overhead and Underground Supply to Mast Site

As published by the council, reference 26/00904/S37

Application record

Reference
26/00904/S37
Type
Section 37
Status
Decided
Decision
S37 Raise No Objection
Received
2 Mar 2026
Validated
2 Mar 2026
Decided
8 Jul 2026
Ward
Fort William And Ardnamurchan
Parish
Nether Lochaber Community Council
Decision by
Delegated Decision

Site history

Applications at this address on the Highland register

This site has had 2 applications since 2026: 1 approved, 0 refused.

  • 26/02035/SCRE Decided

    Land 515M SE Of Glenshellach Inchree Onich

    A new 2 span overhead spur requires to be built in order to supply a mast site at Tom Lain, Coir Na Coille. The overhead apparatus will require Section 37 consent however it is just to the north of the Onich to North Ballachulish Woods SAC and the Onich to North Ballachulish Woods and Shore SSSI and so requires to be screened under Schedule 2 development. Note that the underground cable and free standing transformer pole are all permitted development and for additional information only. This application relates to the new overhead spur from pole 185a.

    Decided 5 Jun 2026 Outline

Timeline

Dates from the published record

  1. 2 Mar 2026

    Received by Highland

  2. 8 Jul 2026

    Decision issued: S37 Raise No Objection

  3. 27 Jul 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

6 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Highland granted permission on 8 July 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Highland's portal will say. Our guide explains the common types.

Nearby applications

Within 500 metres

  • Land 515M SE Of Glenshellach Inchree Onich

    26/02035/SCRE Submitted 7 May 2026 23m away

    A new 2 span overhead spur requires to be built in order to supply a mast site at Tom Lain, Coir Na Coille. The overhead apparatus will require Section 37 consent however it is just to the north of the Onich to North Ballachulish Woods SAC and the Onich to North Ballachulish Woods and Shore SSSI and so requires to be screened under Schedule 2 development. Note that the underground cable and free standing transformer pole are all permitted development and for additional information only. This application relates to the new overhead spur from pole 185a.

    Decided Outline 8 docs