Planning application
Land 460M NE Of Fannich Lodge Lochluichart Garve
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
New Overhead and Underground Supply to Mast Site - consent for two new small sections (one 3 span and one 1 span) of 33kV overhead line which will connect onto an existing section of 33kV overhead line
As published by the council, reference 26/00311/S37
Application record
- Reference
- 26/00311/S37
- Type
- Section 37
- Status
- Decided
- Decision
- Granted As published: S37 Raise No Objection
- Received
- 22 Jan 2026
- Validated
- 22 Jan 2026
- Decided
- 11 Mar 2026
- Ward
- Wester Ross, Strathpeffer And Lochalsh
- Parish
- Garve And District Community Council
- Decision by
- Delegated Decision
Site history
Applications at this address on the Highland register
This site has had 2 applications since 2024: 2 approved, 0 refused.
-
24/02112/FUL Granted
Land 460M NE Of Fannich Lodge Lochluichart Garve
Installation of a 20m high lattice tower, ancillary equipment, compound, access track and associated development
Timeline
Dates from the published record
-
22 Jan 2026
Received by Highland
-
11 Mar 2026
Decision issued: S37 Raise No Objection
-
5 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
3 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Highland granted permission on 11 March 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Highland's portal will say. Our guide explains the common types.