Skip to content
PlanIndex Get alerts
Menu

Planning application

Land 2KM NE Of Gilles Fencing Ardochy Invergarry

Decided Highland 25/04104/S36 Section 36

Decided. The decision notice on the council portal carries the outcome in full, including any conditions.

Proposal

Beinneun 2 Wind Farm - Erection and operation of a wind farm for a period of 40 years, comprising of up to 19 wind turbines with a maximum blade tip height of 200m, battery energy storage system (BESS), met mast, access tracks, borrow pits, substation, control building, and ancillary infrastructure. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00004972

As published by the council, reference 25/04104/S36

Application record

Reference
25/04104/S36
Type
Section 36
Status
Awaiting decision
Decision
S36 Raise Objection
Received
27 Oct 2025
Validated
27 Oct 2025
Decided
12 Feb 2026
Ward
Caol And Mallaig
Parish
Glengarry Community Council
Decision by
Delegated Decision

Timeline

Dates from the published record

  1. 27 Oct 2025

    Received by Highland

  2. 12 Feb 2026

    Decision issued: S36 Raise Objection

  3. 11 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

129 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

After the decision

Highland has decided this application; the outcome above is the register's own wording and the decision notice on the council portal carries the detail. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Highland's portal will say. Our guide explains the common types.