Land Between Strathy North And South Wind Farms Strathy

Granted Highland 25/03497/PNO Prior Notifications - others

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Prior Notification under Reg. 62 for Strathy South Wind Farm Grid Connection: Underground Cable (UGC)

As published by the council, reference 25/03497/PNO

Application record

Reference
25/03497/PNO
Type
Prior Notifications - others
Status
Decided
Decision
Prior Approval Granted
Received
14 Sep 2025
Validated
21 Oct 2025
Decided
21 Jan 2026
Ward
North, West And Central Sutherland
Parish
Melvich Community Council
Decision by
Delegated Decision

Site history

Applications at this address on the Highland register

This site has had 2 applications since 2025: 1 approved, 0 refused.

  • 26/00588/PNO Withdrawn

    Land Between Strathy North And South Wind Farms Strathy

    Prior Notification under Reg. 62 for proposed ground investigation works in relation to Strathy South Wind Farm Grid Connection

    Decided 1 Apr 2026 Prior approval

Timeline

Dates from the published record

  1. 14 Sep 2025

    Received by Highland

  2. 21 Oct 2025

    Validated

    Checked as complete and ready for consideration.

  3. 21 Jan 2026

    Decision issued: Prior Approval Granted

  4. 11 Aug 2026

    Added to PlanIndex

Documents

Plans, drawings, consultee responses and the officer's report

8 documents on file for this application

A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.

Trade members open them from here.

Open the documents

What this grant of permission means

Highland granted permission on 21 January 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About prior approval applications

Prior approval applies where permitted development rights already grant the principle of the work, leaving the council only the specific matters the rules name, commonly within 56 days. More in our guide to planning application types.

In Highland

  • 26/03781/PNO Awaiting decision

    Easter Balfreish Cawdor Nairn IV12 5XY

    Erection of shed - Class 18

    31 Aug 2026 Prior approval
  • 26/03786/PNO Awaiting decision

    Skelpick And Rhifail Estates Sutherland

    Peatland Restoration - Class 20A

    31 Aug 2026 Prior approval
  • 26/03776/PNO Awaiting decision

    Ben Klibreck SSSI - Blanket Bog

    Peatland restoration - Class 20A

    31 Aug 2026 Prior approval
  • 26/03260/PNO Granted

    Land 625M NW Of Braesyde Gairlochy Spean Bridge

    Formation of forestry ATV track (restocking; 1060m long; 2.5m wide) Class 22

    30 Jul 2026 Prior approval
  • 26/03726/PNO Awaiting decision

    Land 130M East Of Tigh Breagha Kildary

    Erection of agricultural building (Class 18)

    28 Aug 2026 Prior approval