Planning application
Rosebank Cottage Lucton Herefordshire HR6 9PH
Works: New dwelling Demolition Domestic
Read from the description, not a valuation. How we read the register
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Proposed demolition of an existing garage and the erection of a two storey detached new build dwelling within the curtilage of the Grade II listed Rose Bank Cottage (For DOC 3, 4, 5, 6, 7, 8, 9, 10 & 20 see 253603)
As published by the council, reference P200626/F
Application record
- Reference
- P200626/F
- Type
- Planning Permission
- Status
- Determination Made
- Decision
- Granted As published: Approved with Conditions
- Received
- 21 Feb 2020
- Validated
- 3 Mar 2020
- Decided
- 12 Aug 2024
- Ward
- Bircher
- Parish
- Lucton
- Postcode
- HR6 9PH
Timeline
Dates from the published record
-
21 Feb 2020
Received by Herefordshire, County of
-
3 Mar 2020
Validated
Checked as complete and ready for consideration.
-
12 Aug 2024
Decision issued: Approved with Conditions
-
23 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
47 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Herefordshire, County of granted permission on 12 August 2024, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About full applications
A full application seeks permission for a complete, detailed proposal in one go, with siting, design, access and landscaping all fixed at this stage. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
New House Farm Lucton Leominster, Herefordshire HR6 9PQ
Conversion of agricultural barns into 4 No residential units
Granted Heritage and listed buildings 9 docs -
New House Farm Lucton Leominster, Herefordshire HR6 9PQ
Conversion of 2 barns into 4 no. residential units
Withdrawn Heritage and listed buildings 9 docs -
New House Farm Lucton Leominster, Herefordshire HR6 9PQ
Conversion of 2 barns into 4 no. residential units
Withdrawn Full applications 9 docs -
New House Farm Lucton Leominster, Herefordshire HR6 9PQ
Conversion of two agricultural barns into 4 No. residential units
Granted Full applications 9 docs -
Elstones Lucton Leominster, Herefordshire HR6 9PH
Conservatory
Granted Full applications Extension 9 docs -
Elfstone Lucton Leominster Herefordshire HR6 9PH
T1 - Field maple - fell to ground level as outgrown position by conservatory.
Decided Trees 3 docs
Other full applications
In Herefordshire, County of
-
P261364/F Granted
Land at White House Farm Eastnor Herefordshire HR8 1EH
Self-build conversion of Oast barn to residential dwelling, including demolition of two steel-framed Dutch Barns and construction of a detached garage.
-
P251893/F Granted
Rose Cottage Stokes Lane Stoke Lacy Bromyard Herefordshire HR7 4HD
Proposed change of use of former stable building to annex accommodation (retrospective) and siting of lodge for use as holiday accommodation and replace the existing package treatment plant with a new one
-
P262187/F Granted
Morrisons Supermarket Leominster Herefordshire HR6 8RH
Installation of commercial pod in car park.
-
P252065/F Withdrawn
Hop Pole Market Square Bromyard Herefordshire HR7 4BP
Proposed restoration and conversion of the Hop Pole Hotel to 7no apartments and retained commercial ground floor.
-
P260542/F Granted
Land at Stoke Edith Hereford Herefordshire
Variation of conditions 2 & 12 of planning permission 241510 (Proposedinstallation and operation of a renewable energy generation station comprising ground-mounted photovoltaic, inverter/transformer units, control room, substations, onsite grid connection equipment, site access, access gates, internal access tracks, security measures and other ancillary infrastructure) - revised site layout