Planning application
Land East Of Hook Road North Warnborough
Still open. Anyone can comment while the consultation period runs, and comments go to the council rather than to us.
Proposal
Approval of Condition 5 - biodiversity enhancement measures - Condition 7 - landscaping - Condition 8 - drainage maintenance and Condition 18 - external materials pursuant to 23/02094/FUL - Erection of 13 dwellings with associated access, parking, affordable housing, public open space, SUDs and landscaping
As published by the council, reference 26/01172/CON
Application record
- Reference
- 26/01172/CON
- Status
- Registered
- Validated
- 14 Jul 2026
Site history
Applications at this address on the Hart register
This site has had 5 applications since 2026.
-
26/01360/NMMA Awaiting decision
Land East Of Hook Road North Warnborough
Minor amendments to the approved dwellings pursuant to 23/02095/FUL - Erection of 9 dwellings with associated access, parking, affordable housing, public open space, SUDs and landscaping
-
26/01179/CON Awaiting decision
Land East Of Hook Road North Warnborough
Approval of Condition 3 - Construction Traffic Management Plan (CTMP) and Condition 6 - Construction Environmental Management Plan (CEMP) pursuant to 23/02094/FUL - Erection of 13 dwellings with associated access, parking, affordable housing, public open space, SUDs and landscaping
-
26/01154/CON Awaiting decision
Land East Of Hook Road North Warnborough
Approval of Conditon 2 - levels - pursuant to 23/02094/FUL - Erection of 13 dwellings with associated access, parking, affordable housing, public open space, SUDs and landscaping
-
26/01155/CON Decided
Land East Of Hook Road North Warnborough
Details pursuant to conditions 9 (archaeological WSI) and 10 (archaeological report) of planning permission ref. 23/02094/FUL (erection of 13 dwellings with associated access, parking, affordable housing, public open space, SUDs and landscaping).
Timeline
Dates from the published record
-
14 Jul 2026
Validated
Checked as complete and ready for consideration.
-
26 Jul 2026
Added to PlanIndex
-
Decision
Awaiting decision
Decision expected by 8 September 2026, 8 weeks from validation under the statutory target for most applications. Extensions of time are common and are agreed case by case.
Hart took a median of 56 days over the applications it decided in the last year.
What happens while it is decided
This application is with Hart for determination, against a statutory target of eight weeks. Over the last year Hart's median decision took 56 days. More in our guide to how long planning decisions take.
About this record
The published feed does not state which type of application this is; the register entry on Hart's portal will say. Our guide explains the common types.