Planning application
Hale Wharf, Ferry Lane, London, N17 9NF
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Approval of details pursuant to condition A30 (completion of remediation and a report that provides verification that the required works have been carried out) attached to the Hybrid Planning Permission Reference: HGY/2016/1719 - Part discharge.
As published by the council, reference HGY/2019/3018
Application record
- Reference
- HGY/2019/3018
- Type
- Approval of details reserved by a condition
- Status
- Decision Made
- Decision
- Granted As published: Approve with Conditions
- Received
- 24 Oct 2019
- Validated
- 24 Oct 2019
- Decided
- 19 Dec 2019
- Ward
- Tottenham Hale
- Decision by
- Delegated Decision
- Postcode
- N17 9NF
Timeline
Dates from the published record
-
24 Oct 2019
Received by Haringey
-
19 Dec 2019
Decision issued: Approve with Conditions
-
25 Aug 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
20 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Haringey granted permission on 19 December 2019, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About condition discharge and variation applications
This application deals with conditions on an existing permission, supplying the details a condition requires or asking to vary or remove one, without reopening the permission itself. More in our guide to planning application types.
Nearby applications
Within 0.3 miles
-
Windlass Apartments, 4 Hale Wharf, Ferry Lane, Tottenham, London, N17 9QH
2no. Non-Illuminated Projecting ID signs (0.65m X 0.55m X 0.11m) to be installed on Blocks C and K.
Granted Advertising 4 docs -
Ground Floor Commercial Unit, Approach House, Hale Wharf, Ferry Lane, Tottenham, London, N17 9AD
Installation of new kitchen extract system in association with ground floor restaurant use
Granted Full applications 16 docs -
Block K Ground Floor Commercial Unit, Hale Wharf, Ferry Lane, London, N17 9NF
Change of use from permitted commercial use (Use Class E (a) (b) (c) and Sui Generis) to residential amenity space (Use Class C3).
Withdrawn Full applications 7 docs -
Hale Service Centre, Old Filling Station,, Ferry Lane, London, N17 9NG
Retrospective application for retention of scaffolding structure for a temporary period to facilitate wall repairs and maintenance to main service centre building.
Granted Full applications 10 docs -
The Ferry Boat Inn Public House, 1, London, N17 9NG
Decision due ~4 Mar
Installation of replacement signs including 1 x externally illuminated pole mounted sign, 2 x externally illuminated fascia signs and 2 x non-illuminated freestanding post signs.
Status unknown Advertising -
The Ferry Boat Inn Public House, 1, London, N17 9NG
Decision due ~4 Mar
External alterations involving renovation of the existing facades and window frames along with new signage and external lighting. Works include construction of a new timber-clad external bar, extension of existing pergola in connection with relocated fixed seating booths, construction of a replacement rear storage shed, installation of raised timber decking platform to accommodate additional seating, refurbishment of the existing patio area including tiled insets and installation of external lighting including wall mounted hanging lights to the front elevation.
Status unknown Full applications Extension Windows or glazingSmall domestic
Other condition discharge and variation applications
In Haringey
-
HGY/2026/1915 Granted
12 Canning Crescent, Wood Green, London, N22 5SR
Approval of details reserved by a condition 10 (Landscape), condition 12 (Method of Construction Statement), condition 13 (investigative work - contaminants), condition 15 (NRMM), condition 16 (Air Quality and Dust Management Plan), and condition 17 (Considerate Constructors Scheme) attached to planning application Ref: HGY/2024/3115
-
HGY/2026/2763 Awaiting decision
11 Sheldon Avenue, Hornsey, London, N6 4JS
Approval of details pursuant to conditions 4 (Refuse and Cycle Storage), 5 (Cycle Parking), 6 (Hard and Soft Landscaping), 12 (ASHP), 13 (Water Butt) and 16 (Self-build Dwelling) attached to planning permission ref: HGY/2024/2154.
-
HGY/2025/3223 Granted
98 High Street, Hornsey, London, N8 7NT
Approval of Details pursuant to condition 3 (materials) ref: HGY/2024/2879
-
HGY/2026/2587 Granted
Tottenham Substation, Watermead Way, London, N17 0SG
Approval of Schedule 2 Requirement 11 (1 and 2) (Contaminated Land and Groundwater) relating to Stage 4a (as approved under HGY/2026/0364) of The National Grid (North London Reinforcement Project) Order 2014 attached to development consent order HGY/2014/3601
-
HGY/2025/1866 Granted
1-6 Crescent Mews, Hornsey, London, N22 7GG
Approval of details pursuant to condition 24 (Overheating Report) attached to planning permission HGY/2019/1183