Planning application
Wembley National Stadium Olympic Way London
Permission granted. Work must normally begin within three years of the decision or the permission lapses.
Proposal
Proposed variation of Condition 1 (event cap) of planning permission reference 17/0368 (dated 18/08/2017), to allow for 17 additional major sporting Tottenham Hotspur Football Club (THFC) events between 15 January 2019 and 12 May 2019.
As published by the council, reference 2018/03737/OBS
Application record
- Reference
- 2018/03737/OBS
- Type
- Observations to Other Borough
- Status
- No Objection to Proposal (OBS only)
- Decision
- Granted As published: No Objection to Proposal (OBS only)
- Received
- 14 Nov 2018
- Validated
- 14 Nov 2018
- Decided
- 12 Dec 2018
- Ward
- Out Of Borough
- Decision by
- Delegated Decision
Timeline
Dates from the published record
-
14 Nov 2018
Received by Hammersmith and Fulham
-
12 Dec 2018
Decision issued: No Objection to Proposal (OBS only)
-
21 Sep 2026
Added to PlanIndex
Documents
Plans, drawings, consultee responses and the officer's report
6 documents on file for this application
A planning file usually holds the application form, drawings and site plans, consultee responses, the officer's report and the decision notice.
Watch members (£5 a month) open the document list from here.
Open the documentsWhat this grant of permission means
Hammersmith and Fulham granted permission on 12 December 2018, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.
About this record
The published feed does not state which type of application this is; the register entry on Hammersmith and Fulham's portal will say. Our guide explains the common types.