Skip to content
PlanIndex Get alerts
Menu

Planning application

Land at Guildford Park Road Car Park, Guildford Park Road, Guildford, GU2 7NN

Granted Guildford 25/P/01522

Permission granted. Work must normally begin within three years of the decision or the permission lapses.

Proposal

Full planning application for the erection of residential apartment blocks and townhouses (248 Us...

As published by the council, reference 25/P/01522

Application record

Reference
25/P/01522
Status
Decided
Decision
Granted As published: Approve
Received
6 Nov 2025
Validated
6 Nov 2025
Decided
22 Oct 2026
Ward
Onslow
Parish
Onslow
Decision by
Delegated
Postcode
GU2 7NN

Site history

Applications at this address on the Guildford register

This site has had 7 applications since 2025: 1 approved, 0 refused.

  • 26/D/00159/5 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford, GU2 7NN

    Discharge of condition 18 (Site waste management plan) of planning permission 25/P/01522 approved...

    Submitted 29 Oct 2026
  • 26/D/00159/1 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of condition 9 (Arboricultural assessments) of planning permission 25/P/01522 approved ...

    Submitted 28 Oct 2026
  • 26/D/00159/3 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of condition 11 (Construction environmental management plan) of planning permission 25/...

    Submitted 28 Oct 2026
  • 26/D/00159/2 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of condition 22 (Construction management plan) of planning permission 25/P/01522 approv...

    Submitted 28 Oct 2026
  • 26/D/00159/4 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of condition 23 (Environmental Mitigation Strategy) of planning permission 25/P/01522 a...

    Submitted 28 Oct 2026
  • 26/D/00159 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of Condition 4 (remediation strategy) of planning permission 25/P/01522 approved 22/10/...

    Submitted 28 Oct 2026

Timeline

Dates from the published record

  1. 6 Nov 2025

    Received by Guildford

  2. 30 Jul 2026

    Added to PlanIndex

  3. 22 Oct 2026

    Decision issued: Approve

  4. 22 Oct 2026

    Status changed to Decided

    Previously Awaiting decision.

Cases linked to this one on the register

5 later applications on the register refer to this one:

  • 26/D/00159/5 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford, GU2 7NN

    Discharge of condition 18 (Site waste management plan) of planning permission 25/P/01522 approved...

    Submitted 29 Oct 2026
  • 26/D/00159 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of Condition 4 (remediation strategy) of planning permission 25/P/01522 approved 22/10/...

    Submitted 28 Oct 2026
  • 26/D/00159/1 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of condition 9 (Arboricultural assessments) of planning permission 25/P/01522 approved ...

    Submitted 28 Oct 2026
  • 26/D/00159/2 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of condition 22 (Construction management plan) of planning permission 25/P/01522 approv...

    Submitted 28 Oct 2026
  • 26/D/00159/4 Awaiting decision

    Land at Guildford Park Road Car Park, Guildford Park Road, Guildford GU2 7NN

    Discharge of condition 23 (Environmental Mitigation Strategy) of planning permission 25/P/01522 a...

    Submitted 28 Oct 2026

Documents

Plans, drawings, consultee responses and the officer's report

191 documents on file for this application

  • Draft s106/soi Section 106 · 24 Sep 2026
  • Surrey wildlife trust Correspondence · 19 Aug 2026
  • Pad/scc s106 contributions Correspondence · 27 Mar 2026
  • Amended scc education infrastructure cil justification statement Application Document · 19 Mar 2026
  • Committee report Report · 06 Mar 2026
  • The guildford society Correspondence · 03 Mar 2026
  • Surrey cc highways Correspondence · 13 Feb 2026
  • Planning and affordable housing statement addendum Application Document · 12 Feb 2026
  • Design & access statement - planning addendum Application Document · 12 Feb 2026
  • Correction to no. of habitable room and bathroom count Application Document · 12 Feb 2026
  • Natural england appropriate assessment response Correspondence · 11 Feb 2026
  • Natural england Correspondence · 11 Feb 2026
  • Natural england - comment Correspondence · 05 Feb 2026
  • Comments from scc highways Correspondence · 02 Feb 2026
  • Scc highways Correspondence · 29 Jan 2026
  • Uk power networks - comment Correspondence · 27 Jan 2026
  • Design & conservation - comment Correspondence · 27 Jan 2026
  • Surrey & sussex police - comment Correspondence · 27 Jan 2026
  • Design & conservation - comment Correspondence · 26 Jan 2026
  • Network rail Correspondence · 22 Jan 2026
  • Tim holman - tree officer Consultee Comment · 19 Jan 2026
  • Scc suds comments Correspondence · 16 Jan 2026
  • The guildford society - objection Correspondence · 15 Jan 2026
  • Surrey suds - object Correspondence · 09 Jan 2026
  • Surrey county suds comments Correspondence · 22 Dec 2025
  • Surrey heartlands consultation response Correspondence · 16 Dec 2025
  • Network rail - comment Correspondence · 11 Dec 2025
  • Surrey highways - comment Correspondence · 09 Dec 2025
  • Environment agency - comment Correspondence · 09 Dec 2025
  • Thames water - comment Correspondence · 08 Dec 2025
  • Historic england Correspondence · 08 Dec 2025
  • Surrey countryside access - comment Correspondence · 05 Dec 2025
  • Archaeological officer - comment Correspondence · 04 Dec 2025
  • Surrey suds - comment Correspondence · 04 Dec 2025
  • Affinity water Correspondence · 04 Dec 2025
  • Superseded scc education infrastructure cil justification statement Correspondence · 27 Nov 2025
  • Natural england - comment Correspondence · 27 Nov 2025
  • Gbc affordable housing - comment Correspondence · 26 Nov 2025
  • Surrey hills national landscape planning adviser Correspondence · 20 Nov 2025
  • Design out crime officer Correspondence · 20 Nov 2025
  • Site waste management plan Application Document · 11 Nov 2025
  • Biodiversity metric Application Document · 11 Nov 2025
  • Habitat regulations assessment Application Document · 11 Nov 2025
  • Arboricultural survey report Application Document · 11 Nov 2025
  • Bat survey Application Document · 11 Nov 2025
  • Reptile survey Application Document · 11 Nov 2025
  • Great crested newt habitat suitability index assessment and edna survey Application Document · 11 Nov 2025
  • Extended preliminary ecological appraisal Application Document · 11 Nov 2025
  • Bng report Application Document · 11 Nov 2025
  • Agricultural method statement Application Document · 11 Nov 2025
  • Internal daylight & sunlight report Application Document · 11 Nov 2025
  • Neighbours daylight & sunlight report Application Document · 11 Nov 2025
  • Block a level 04 ga plan Drawing · 11 Nov 2025
  • Block a level 05 ga plan Drawing · 11 Nov 2025
  • Block a roof level ga plan Drawing · 11 Nov 2025
  • Block b roof level ga plan Drawing · 11 Nov 2025
  • Block b level 05 ga plan Drawing · 11 Nov 2025
  • Block b level 04 ga plan Drawing · 11 Nov 2025
  • Block b level 03 ga plan Drawing · 11 Nov 2025
  • Block b level 02 ga plan Drawing · 11 Nov 2025
  • Block b level 01 ga plan Drawing · 11 Nov 2025
  • Block b level 00 ga plan Drawing · 11 Nov 2025
  • Block c roof level ga plan Drawing · 11 Nov 2025
  • Block c level 05 ga plan Drawing · 11 Nov 2025
  • Block c level 04 ga plan Drawing · 11 Nov 2025
  • Block c level 03 ga plan Drawing · 11 Nov 2025
  • Block c level 02 ga plan Drawing · 11 Nov 2025
  • Block c level 01 ga plan Drawing · 11 Nov 2025
  • Block c level 00 ga plan Drawing · 11 Nov 2025
  • Block d roof level ga plan Drawing · 11 Nov 2025
  • Block d level 05 ga plan Drawing · 11 Nov 2025
  • Block d level 04 ga plan Drawing · 11 Nov 2025
  • Block d level 03 ga plan Drawing · 11 Nov 2025
  • Block d level 02 ga plan Drawing · 11 Nov 2025
  • Block d level 01 ga plan Drawing · 11 Nov 2025
  • Block d level 00 ga plan Drawing · 11 Nov 2025
  • Town house roof level plan Drawing · 11 Nov 2025
  • Town house roof level 02 plan Drawing · 11 Nov 2025
  • Town house level 01 plan south end Drawing · 11 Nov 2025
  • Town house level 01 plan Drawing · 11 Nov 2025
  • Town house level 00 plan south end Drawing · 11 Nov 2025
  • Town house level 00 plan Drawing · 11 Nov 2025
  • Town house roof level plan Drawing · 11 Nov 2025
  • Town house level 02 plan Drawing · 11 Nov 2025
  • Town house level 01 plan north end Drawing · 11 Nov 2025
  • Town house level 01 plan north end Drawing · 11 Nov 2025
  • Town house level 00 plan north end Drawing · 11 Nov 2025
  • Town house level 00 plan Drawing · 11 Nov 2025
  • Proposed soft landscape 3 Drawing · 11 Nov 2025
  • Proposed soft landscape 2 Drawing · 11 Nov 2025
  • Proposed soft landscape 1 Drawing · 11 Nov 2025
  • Proposed hardlandscape 1 Drawing · 11 Nov 2025
  • Proposed hardlandscape 2 Drawing · 11 Nov 2025
  • Proposed boundary plan Drawing · 11 Nov 2025
  • Landscape sections 2 Drawing · 11 Nov 2025
  • Landscape sections 1 Drawing · 11 Nov 2025
  • Landscape masterplan 3 Drawing · 11 Nov 2025
  • Landscape masterplan 2 Drawing · 11 Nov 2025
  • Landscape masterplan 1 Drawing · 11 Nov 2025
  • Landscape masterplan wideview Drawing · 11 Nov 2025
  • Design & access pt1 Application Document · 11 Nov 2025
  • Design & access pt2 Application Document · 11 Nov 2025
  • Drawing issue register Application Document · 11 Nov 2025
  • Site-wide roof level ga plan Drawing · 11 Nov 2025
  • Site-wide roof level 05 ga plan Drawing · 11 Nov 2025
  • Site-wide level 04 ga plan Drawing · 11 Nov 2025
  • Site-wide level 03 ga plan Drawing · 11 Nov 2025
  • Site-wide level 02 ga plan Drawing · 11 Nov 2025
  • Site-wide level 01 ga plan Drawing · 11 Nov 2025
  • Site-wide level 00 ga plan Drawing · 11 Nov 2025
  • Schedule of areas Application Document · 11 Nov 2025
  • Flood risk assessment and drainage strategy 1 Application Document · 11 Nov 2025
  • Flood risk assessment and drainage strategy 2 Application Document · 11 Nov 2025
  • Flood risk assessment and drainage strategy 3 Application Document · 11 Nov 2025
  • Flood risk assessment and drainage strategy 4 Application Document · 11 Nov 2025
  • Flood risk assessment and drainage strategy 5 Application Document · 11 Nov 2025
  • Flood risk assessment and drainage strategy 6 Application Document · 11 Nov 2025
  • Flood risk assessment and drainage strategy 7 Application Document · 11 Nov 2025
  • Flood risk assessment and drainage strategy 8 Application Document · 11 Nov 2025
  • Travel plan Application Document · 11 Nov 2025
  • Transport assessment 3 Application Document · 11 Nov 2025
  • Transport assessment 2 Application Document · 11 Nov 2025
  • Transport assessment 1 Application Document · 11 Nov 2025
  • Fire statement Application Document · 11 Nov 2025
  • Noise impact assessment Application Document · 11 Nov 2025
  • Vibration assessment Application Document · 11 Nov 2025
  • Construction logistics plan Application Document · 11 Nov 2025
  • Delivery and servicing plan Application Document · 11 Nov 2025
  • Parking management plan Application Document · 11 Nov 2025
  • Operational waste management plan Application Document · 11 Nov 2025
  • Utilities & infrastructure assessment Application Document · 11 Nov 2025
  • Cover letter Application Document · 11 Nov 2025
  • Planning statement Application Document · 11 Nov 2025
  • Site waste management plan Application Document · 11 Nov 2025
  • Energy and sustainability statement Application Document · 11 Nov 2025
  • Heritage, townscape and visual impact assessment Application Document · 11 Nov 2025
  • Desk based assessment Application Document · 11 Nov 2025
  • Air quality assessment Application Document · 11 Nov 2025
  • Contaminated land assessment 1 Application Document · 11 Nov 2025
  • Contaminated land assessment 2 Application Document · 11 Nov 2025
  • Nationally described space standards (ndss) Application Document · 10 Nov 2025
  • Application form Application Form · 06 Nov 2025
  • Block a level 00 ga plan Drawing · 06 Nov 2025
  • Block a level 01 ga plan Drawing · 06 Nov 2025
  • Block a level 02 ga plan Drawing · 06 Nov 2025
  • Block a level 03 ga plan Drawing · 06 Nov 2025
  • Proposed ga elevation east Drawing · 06 Nov 2025
  • Proposed ga elevation west Drawing · 06 Nov 2025
  • Block a section bb Drawing · 06 Nov 2025
  • Block a section aa Drawing · 06 Nov 2025
  • Block b proposed ga elevation east Drawing · 06 Nov 2025
  • Block b proposed ga elevation west Drawing · 06 Nov 2025
  • Block b section bb Drawing · 06 Nov 2025
  • Block b section aa Drawing · 06 Nov 2025
  • Block a proposed ga elevation north Drawing · 06 Nov 2025
  • Block a proposed ga elevation south Drawing · 06 Nov 2025
  • Block c proposed ga elevation north Drawing · 06 Nov 2025
  • Block c proposed ga elevation south Drawing · 06 Nov 2025
  • Block c proposed ga elevation east Drawing · 06 Nov 2025
  • Block c proposed ga elevation west Drawing · 06 Nov 2025
  • Block c section bb Drawing · 06 Nov 2025
  • Block c section aa Drawing · 06 Nov 2025
  • Block d proposed ga elevation north Drawing · 06 Nov 2025
  • Block d proposed ga elevation south Drawing · 06 Nov 2025
  • Block d proposed ga elevation east Drawing · 06 Nov 2025
  • Block d proposed ga elevation west Drawing · 06 Nov 2025
  • Block d section bb Drawing · 06 Nov 2025
  • Block d section aa Drawing · 06 Nov 2025
  • Terraced homes elevations south end Drawing · 06 Nov 2025
  • Terraced homes elevations south Drawing · 06 Nov 2025
  • Terraced homes elevations north Drawing · 06 Nov 2025
  • Terraced homes elevations west Drawing · 06 Nov 2025
  • Terraced homes elevations east Drawing · 06 Nov 2025
  • Terraced homes section bb Drawing · 06 Nov 2025
  • Terraced homes section aa Drawing · 06 Nov 2025
  • Terraced homes elevations north Drawing · 06 Nov 2025
  • Terraced homes elevations south Drawing · 06 Nov 2025
  • Terraced homes elevations north end Drawing · 06 Nov 2025
  • Terraced homes elevations west Drawing · 06 Nov 2025
  • Terraced homes elevation east Drawing · 06 Nov 2025
  • Terraced homes section bb Drawing · 06 Nov 2025
  • Terraced homes section aa Drawing · 06 Nov 2025
  • Site location plan Drawing · 06 Nov 2025
  • Proposed site plan Drawing · 06 Nov 2025
  • Existing site plan Drawing · 06 Nov 2025
  • Townhouse site-wide elevation Drawing · 06 Nov 2025
  • Site-wide west elevation Drawing · 06 Nov 2025
  • Site-wide east elevation Drawing · 06 Nov 2025
  • Townhouse site-wide section Drawing · 06 Nov 2025
  • Site-wide section blocks Drawing · 06 Nov 2025
  • Arboricultural impact assessment Application Document · 06 Nov 2025

Watch members (£5 a month) open the document list from here.

Open the documents

What this grant of permission means

Guildford granted permission on 22 October 2026, subject to any conditions on the decision notice. Work must normally begin within three years or the permission lapses. More in our guide to what happens after a planning decision.

About this record

The published feed does not state which type of application this is; the register entry on Guildford's portal will say. Our guide explains the common types.

Nearby applications

Within 0.3 miles